An experienced demolition contractor who relies on a developer's representations that necessary consents have been obtained is not exculpated from a strict liability offence under s 125(1) of the EP&A Act. Section 10 dismissals are not usual for strict liability planning offences, particularly where the offence involves demolition of a heritage item and is not trivial. A 25 per cent discount for early guilty plea, remorse, and cooperation is appropriate.