PROCEDURE — application to file cross-claim out of time — where Applicant's Defence had already pleaded proportionate liability provisions of Civil Liability Act — cross-claim seeks in the alternative to claim contribution pursuant to Law Reform (Miscellaneous Provisions) Act 1946 — whether loss and damage first suffered before or after 26 July 2004 — successive tortfeasors — whether same "damage" — discretionary considerations — leave granted to file cross-claim.
Case Details
Citation[2011] NSWSC 577
CourtNSWSC
JurisdictionNew South Wales
Unlock so much more with Barrister AI
The full text is available to signed-in members, including the 1 later case that cites this judgment.