The Court held that an adjudicator committed jurisdictional error and denied natural justice by permitting a claimant to advance variation claims in its adjudication application on a fundamentally different basis (excusable delay due to inclement weather) from that stated in the payment claim (delay due to heritage issues and a stop work order), and then using s 20(2B) to bar the respondent from raising contractual defences to the reformulated claims. The Court also held that the adjudicator's erroneous application of s 20(2B) to exclude the respondent's supporting calculations — which were in fact attached to the payment schedule — constituted a further denial of natural justice, and that the adjudicator's bare statement of satisfaction as to quantum without any reasoning constituted a failure to comply with the obligation to give reasons under s 22(3)(b), amounting to jurisdictional error.
The full text is available to signed-in members, including the 14 later cases that cite this judgment.