Where the existence and extent of conflict with a planning scheme are the critical issues at first instance and the existence of conflict is not obvious, a Planning and Environment Court judge must provide adequate reasons identifying and construing the relevant scheme provisions and explaining the reasoning process; bare assertions of conflict without such analysis constitute an error of law. The same obligation applies to reasons for rejecting grounds advanced to justify approval notwithstanding conflict.