A defects liability period in a subcontract that is defined by reference to the Date of Final Acceptance under a head contract is not absurd merely because the date is uncertain or may never occur. Parties have contractual freedom to fix dates by reference to future uncertain events. Subcontractors seeking release of retention monies tied to head contract milestones bear the onus of proving that the relevant milestone has been reached or should be deemed to have been reached.