The 28-day time limit in s 86(2) of the Queensland Building Services Authority Act 1991 (Qld) for applications to QCAT to review decisions about scope of works, directions to rectify, and related matters is a mandatory substantive limitation on QCAT's jurisdiction that cannot be extended under s 61 of the QCAT Act. Building contractors who fail to apply within 28 days lose the right to review entirely. In s 71 debt recovery proceedings, the statutory right to recover is not conditioned upon the legal quality of anterior decisions by the authority, and defences challenging the authority's discretionary factual conclusions in the claims process are not available.