The fixing of a reference date by an adjudicator under s 9(2) of the Building and Construction Industry Security of Payment Act 2002 (Vic) is a jurisdictional fact reviewable by the Supreme Court. Judicial review of adjudication determinations is not confined to straightforward calculations of time or arbitrary/capricious determinations; jurisdictional facts may require evaluation and assessment. Pre-contractual negotiations are inadmissible to vary the terms of a written construction contract where the contract has a plain meaning.