REFEREES - nature of proceedings on challenge to Referee’s Report
DAMAGES - where plaintiff relied upon expert’s advice in respect of the scope of works to rectify defects - where defendants had warned plaintiff that scope of works was exploratory, speculative and not urgent - where findings made that the work carried out was not urgent - where works found to be unnecessary and excessive - where Referee found that defendants not liable for such work - whether those aspects of Referee’s Report should be rejected
DAMAGES - where failure to comply with relevant Standard - where technical breach - whether plaintiff entitled to remedial work to achieve contractual conformity
Case Details
Citation[2016] NSWSC 1127
CourtNSWSC
JurisdictionNew South Wales