Where parties are negotiating terms for participation in joint litigation and commence proceedings before reaching final agreement, the commencement of proceedings does not of itself give rise to a binding contract. The conduct must unequivocally point to the existence of the contract in the terms alleged; mere consistency with the alleged agreement is insufficient. Silence on a critical term in a purported acceptance (such as an indemnity demand) cannot be construed as acceptance of that term.