A contractual obligation to provide 'an occupation certificate' prior to settlement is satisfied by the provision of an interim occupation certificate under s 109H of the Environmental Planning and Assessment Act 1979 (NSW), and in the case of alterations to portions of an existing building, a final occupation certificate does not require completion of all works authorised by the development approval.