Practitioners seeking to set aside statutory demands based on SOP Act debts by raising offsetting claims for loss of bargain damages must ensure that the party has not previously affirmed the contract, and that any purported termination is not precluded by the sub-contractor's valid statutory suspension of works under s 27 of the SOP Act.