Practitioners advising on compensation for land dedicated under development consent conditions should note that an alternative hypothetical development that fails to address inherent natural constraints on the land (such as upstream flooding) cannot be assumed to be an available development for valuation purposes, even where the constraint overlaps with a 'public purpose' to be disregarded.
The full text is available to signed-in members, including the 4 later cases that cite this judgment.
1 of the 4 citing cases carry a classified treatment. How each court treated it is available to signed-in members.