Establishing repudiation by a builder requires proof that the builder claimed amounts not contractually owed by reference to the contract's payment schedule, not merely by comparing total payments with the value of work done. Restitutionary claims for overpayment must similarly be assessed against the contractual payment regime, not by comparing payments with work value.
The full text is available to signed-in members, including the 4 later cases that cite this judgment.
2 of the 4 citing cases carry a classified treatment. How each court treated it is available to signed-in members.