› whether s 40(2)(g) of the Mining Management Act (“the Act”) requires a mining management plan to include a plan and costing of closure activities after the planned closure of the mine
› Ground of review not made out.
Administrative Law
› Whether reviewable error of law
› Jurisdictional error
› whether the Minister calculated the security required to be provided by the operator in accordance with s 43A(1) of the Act
› Ground of review not made out.
Administrative Law
› Whether reviewable error of law
› Jurisdictional error
› whether the Minister’s decision to approve the 2020 Mining Management Plan and issue the Authorisation for carrying out the mining activities referred to in the 2020 Mining Management Plan was unreasonable for the reason that the Minister mistakenly believed that the 2020 Mining Management Plan was compliant with Assessment Report 86 issued by the NT EPA and the recommendations therein