whether adjudication determination under Building and Construction Industry Security of Payment Act 1999 should be quashed
adjudicator determined that the payment schedule did not contain valid reasons for withholding payment and that the adjudication response advanced new reasons which the adjudicator was not permitted to consider
whether the adjudicator failed to comply with mandatory requirements of Act