CONTRACTS — Breach of contract — failure to pay — whether contract is unenforceable pursuant to s 4 of the Home Building Act 1989 (NSW)
Quick Take
1Project management and coordination work in relation to residential building falls within the exclusion in Schedule 1, clause 2(3)(i)(iii) of the Home Building Act 1989 (NSW) where all residential building work is done by a separately engaged licensed and insured contractor, so the project management contract is not rendered unenforceable by ss 7, 92(2) or 94 of that Act.
2A contractual interest rate of 2% per month (24% per annum) on late payments was held to be a penalty disproportionate to the claim, and the court instead awarded interest under s 100 of the Civil Procedure Act 2005 (NSW).
3Delay in rendering an invoice does not, without more, constitute a representation that payment will not be sought, and promissory estoppel was not established where there was no evidence of reliance or detriment.