Where parties to a building contract based on AS4902-2000 delete cl 37.2(b) (the certificate of moneys due from Contractor to Principal), the Principal loses the ability to set off certified liquidated damages against progress payments, and the right to bring liquidated damages to account is preserved only at the final certificate stage under cl 37.4.