DEVELOPMENT APPLICATION — part demolition — alterations and additions to existing building — conciliation conference — agreement between the parties — orders
Quick Take
1Under s 34(3) of the Land and Environment Court Act 1979 (NSW), the Court must dispose of proceedings in accordance with the parties' agreed decision if it is one the Court could have made in the proper exercise of its functions, which requires satisfaction of the relevant jurisdictional prerequisites but not consideration of the merits.
2On the facts, a gym that was lawfully established, and whose further consent was determined under a savings provision as if a rezoning had not commenced, enjoyed existing use rights under s 4.65 of the EPA Act after the rezoning prohibited recreation facilities (indoor). Consent could therefore be granted under cl 164 of the EPA Regulation 2021 to an intensification of that use on the same land.
3Under s 8.15(3) of the EPA Act, an applicant who amends a development application during a Class 1 appeal may be ordered to pay the council's costs thrown away as a result of the amendment.