The Tribunal confirmed the QBCC's internal review decision allowing a homeowner's claim under the Queensland Home Warranty Scheme for 26 non-structural defect items, holding that the Tribunal had jurisdiction to review a decision to allow a claim where internal review had occurred, that the work was not substantially complete so the seven-month time limit for non-structural defect claims did not apply, and that the builder's reasons for the work being incomplete were irrelevant to entitlement under the scheme.