Pre-contractual representations in a competitive tender process about the capabilities of a system to be supplied relate to the system to be delivered, not merely to the prototype demonstrated, and disclaimers about the need for further study are insufficient to withdraw such representations where the representor proceeds to contract. The cost of permanent staff diverted to a failed project is recoverable as wasted expenditure, measured either by the cost of replacement staff or the cost of the permanent staff while engaged on the project. Where a settlement sum from a co-defendant is to be set off against damages, the court may order that the sum first be reduced by the plaintiff's costs of pursuing the co-defendant.