A payment claim under s 17(2)(a) of the BCIPA must identify the construction work or related goods and services on its face; a schedule listing only invoice numbers, dates and amounts, without attaching the invoices or describing the work, is insufficient. Whether claims for 'administration' and 'supervisory costs' fall within the BCIPA definitions of 'construction work' or 'related goods and services' is properly a matter for adjudication, not for the court on an application under s 19.
The full text is available to signed-in members, including the 8 later cases that cite this judgment.
2 of the 8 citing cases carry a classified treatment. How each court treated it is available to signed-in members.