The correct test for validity of a payment claim under s 17(2)(a) of the Building and Construction Industry Payments Act 2004 (Qld) is whether the claim purports in a reasonable way to identify the construction work such that the basis of the claim is reasonably comprehensible to the recipient. The test of 'precision and particularity to apprise the parties of the real issues in dispute' applies to payment schedules, not payment claims. A payment claim is not a nullity unless the failure to identify is patent on its face. The question of whether a partially invalid payment claim is severable remains open in Queensland.
The full text is available to signed-in members, including the 24 later cases that cite this judgment.
3 of the 24 citing cases carry a classified treatment. How each court treated it is available to signed-in members.