An adjudicator's determination under the SOP Act will not be quashed for jurisdictional error where the adjudicator engaged in a process of evaluation of the value of construction work, even if the adjudicator's construction of the contract or assessment of value was erroneous, and the adjudicator's reasons are not to be examined with a fine-tooth comb or a requirement of legally correct language.
The full text is available to signed-in members, including the 12 later cases that cite this judgment.
3 of the 12 citing cases carry a classified treatment. How each court treated it is available to signed-in members.