Practitioners acting for contractors should note that where an adjudication determination is void for jurisdictional error, the contractor may immediately withdraw and make a new adjudication application without first obtaining a court declaration; practitioners acting for principals should note that a contractual take-out power cannot extinguish a statutory entitlement to a progress payment that arose on a reference date before the take-out notice was served.
The full text is available to signed-in members, including the 13 later cases that cite this judgment.
3 of the 13 citing cases carry a classified treatment. How each court treated it is available to signed-in members.