Respondents to payment claims under the Security of Payment Act must ensure that payment schedules contain sufficient particularity as to reasons for withholding payment; a bare statement that payment will not be made until works are completed will not suffice, and surrounding communications cannot be relied upon to supplement the schedule unless expressly incorporated by reference.
The full text is available to signed-in members, including the 7 later cases that cite this judgment.
3 of the 7 citing cases carry a classified treatment. How each court treated it is available to signed-in members.