Cessnock City Council v 123 259 932 Pty Ltd [2024] HCA 17 (8 May 2024)
Last Updated: 29 May 2024
HIGH COURT OF AUSTRALIA
GAGELER CJ,
GORDON,
EDELMAN, STEWARD, GLEESON, JAGOT AND BEECH‑JONES JJ
CESSNOCK CITY COUNCIL APPELLANT
AND
123 259 932 PTY
LTD RESPONDENT
Cessnock City Council v 123 259 932 Pty Ltd
[2024]
HCA 17
Date of Hearing: 13 February 2024
Date of Judgment: 8 May
2024
S115/2023
ORDER
Appeal dismissed with costs.
On appeal from the Supreme
Court of New South Wales
Representation
J T Gleeson SC
with L G Moretti for the appellant (instructed by Holding Redlich)
D L
Williams SC with B D Kaplan for the respondent (instructed by Dentons
Australia)
Notice: This copy of the Court's Reasons for Judgment is subject to formal
revision prior to publication in the Commonwealth Law
Reports.
CATCHWORDS
Cessnock City Council v 123 259 932 Pty
Ltd
Damages – Contract – Where appellant owned land on
which airport located – Where appellant and respondent entered
into
agreement by which respondent to lease prospective lot at airport – Where
appellant breached obligation in agreement to
take all reasonable action to
apply for and obtain registration of plan of subdivision – Where
respondent spent considerable
sums in anticipation of or reliance on appellant's
performance – Where expenditure wasted due to breach of contract by
appellant
– Where respondent entitled to be placed in the position it
would have been in had the contract been performed – Whether
respondent
entitled to recover wasted expenditure – Proper approach to method of
proof for plaintiff to establish position
plaintiff would have been in if
contract performed, where plaintiff incurred expenditure in anticipation of or
reliance on performance
of defendant's contractual obligation and defendant's
breach has effect that expenditure wasted.
Words and phrases –
"anticipation of", "assessment of damages", "breach of contract", "consequential
loss", "contract", "damages",
"expectation damages", "facilitation of proof",
"facilitation principle", "fair wind", "loss", "onus of proof", "presumption",
"presumption
of recoupment", "reasonably incurred", "reliance damages",
"reliance on", "uncertainty of proof", "wasted expenditure".
- GAGELER CJ.
This appeal concerns the recoverability in damages for breach of contract of
expenditure incurred by an innocent party
(a plaintiff), in reliance on an
expectation of performance of a contract, rendered futile as a result of
non-performance of the
contract by a defaulting party (a defendant).
- The
principle governing recovery of such "wasted expenditure" was stated in the
decision of the Court of Appeal of the Supreme Court
of New South Wales under
appeal as follows:[1]
"To sum up: a plaintiff who is unable or does not undertake to demonstrate
whether or to what extent the performance of a contract
would have resulted in a
profit may claim its wasted expenditure. In such a case, expenditure incurred by
a plaintiff in reliance
on a contractual promise made by the defendant and
'wasted' because of non-performance by the defendant is recoverable, except to
the extent that the defendant shows that the plaintiff would not have recouped
its expenditure had the contract been performed."
The Court of Appeal emphasised that recovery is limited by the principle of
remoteness of damage associated with Hadley v
Baxendale,[2] in respect of
which the Court of Appeal
added:[3]
"[T]he proper application of Hadley v Baxendale as a control on
remoteness of damage in a claim for wasted expenditure is whether, when the
contract was made, it was within the reasonable
contemplation of the parties
that the relevant expenditure would be incurred and, if the contract were
breached in the relevant manner,
wasted."
- In
my opinion, the Court of Appeal was correct. The principle governing the
recovery of damages for wasted expenditure can be generalised
as follows. A
plaintiff establishes a prima facie entitlement to recover damages for breach of
contract if and to the extent that
the plaintiff establishes that expenditure it
has incurred in reliance on an expectation of performance of the contract has in
fact
been wasted upon breach of the contract by the defendant. The prima facie
entitlement of the plaintiff prevails unless and except
to the extent that the
defendant establishes the counterfactual that the expenditure would still have
been wasted even if the contract
had been performed. Beyond the limitations
imposed through the application of standard limiting principles, such as
remoteness and
mitigation, no further limitation on recovery should be imposed.
- Specifically,
the principle governing the recovery of damages for wasted expenditure is not
erroneous or deficient insofar as the
principle as so stated: does not require
the plaintiff to establish an evidentiary foundation for presuming that the
plaintiff would
have recovered the expenditure had the contract been performed;
does not have a threshold requirement that the defendant has somehow
made it
"difficult" for the plaintiff to prove that the plaintiff would have made a
profit from performance of the contract; does
not distinguish between
expenditure incurred by the plaintiff in the course of or for the purpose of
performing its own obligations
under the contract and other expenditure incurred
by the plaintiff in reliance on an expectation of performance of the contract;
and imposes a legal onus on the defendant to establish the counterfactual that
the expenditure would have been wasted even if the
contract had been
performed.
- In
the balance of these reasons for judgment, I explain my understanding of the
justification for the recoverability of damages for
wasted expenditure according
to the stated principle of recovery: first at the level of legal principle, and
second by reference
to precedent in this Court. I undertake that task aware of a
vast academic literature,[4]
without seeking to engage with all competing academic
perspectives.
Legal principle
- The
"ruling principle"[5] with
respect to the recovery of compensatory damages for breach of contract at common
law is that stated in Robinson v
Harman:[6] "where a
[plaintiff] sustains a loss by reason of a breach of contract, [the plaintiff]
is, so far as money can do it, to be placed
in the same situation, with respect
to damages, as if the contract had been performed". The principle is universally
recognised to
prevent a plaintiff from being placed by an award of compensatory
damages in a better position than that which the plaintiff would
have been in
had the contract been
performed.[7]
- But
the statement of principle in Robinson v Harman does not in one sentence
encapsulate the totality of the necessary analysis. Critical to the operation of
the principle is to distinguish
between the "damages" ultimately to be assessed
and the "loss" or "damage" which the plaintiff has sustained by reason of a
breach
of contract: "damage" being "the phenomenon in respect of which an
assessment of damages is
made".[8] For there to be
compensatory damages, there must first be
damage.[9] The damage in
respect of which a plaintiff is entitled to be compensated by damages does not
lie in mere non-performance of a contract
but in the legally cognisable respect
or respects in which the position of the plaintiff has been made worse by
non-performance of
the contract in comparison to the position which the
plaintiff would have been in had the contract been performed. Non-performance
of
a contract has the potential to make a plaintiff worse off in different
respects, with the consequence that "[d]ifferent, even
cumulative, heads of
damage may be pleaded by a plaintiff, depending on the type of contract involved
and the kinds of breach and
damage occasioned, provided there is no double
recovery".[10]
- The
principle in Robinson v Harman operates both: (1) to set the framework
for determining the category or categories of damage which a plaintiff has
sustained by reason
of a defendant's non-performance of a contract; and (2) to
set a ceiling on the overall damages to which a plaintiff is entitled.
Distinguishing the damage from the ceiling on damages is important to
understanding the justification for and limit of the recoverability
of damages
for wasted expenditure.
- Expenditure
incurred by a plaintiff in reliance on an expectation of performance might well
be seen to be indicative of the minimum
benefit or gain which the plaintiff
might be taken to have expected from performance of the contract. Damages for
wasted expenditure
might on that basis be seen to be a "proxy" for damages
attributable to a category of damage constituted by the benefit or gain from
performance which the plaintiff might be taken to have lost by reason of
non-performance.[11] But it
is more than that. Wasted expenditure is itself a category of damage.
- That
much was long ago explained by the Supreme Court of the United States in
United States v
Behan,[12] in a passage
quoted and applied by the Full Court of the Supreme Court of New South Wales in
Banks v
Williams:[13]
"If the breach consists in preventing the performance of the contract, without
the fault of the other party, who is willing to perform
it, the loss of the
latter will consist of two distinct items or grounds of damage, namely: first,
what he has already expended towards
performance (less the value of materials on
hand); secondly, the profits that he would realize by performing the whole
contract.
The second item, profits, cannot always be recovered. They may be too
remote and speculative in their character, and therefore incapable
of that clear
and direct proof which the law requires."
Further:[14]
"[T]he primary measure of damages is the amount of the party's loss; and this
loss, as we have seen, may consist of two heads or
classes of damage –
actual outlay and anticipated profits. But failure to prove profits will not
prevent the party from recovering
his losses for actual outlay and expenditure.
... The claimant ... might stop upon a showing of losses. The two heads of
damage are
distinct, though closely related."
- To
similar effect is the relatively recent explanation of the distinction between
damages for wasted expenditure and damages for
loss of profits by the Court of
Appeal of England and Wales in Soteria Insurance Ltd v IBM United Kingdom
Ltd.[15] The
distinction was applied in that case to hold that damages for wasted expenditure
were recoverable even though damages for loss
of profits were excluded from
recovery by the terms of the
contract.[16] A submission
"that there was no such thing as wasted expenditure or even reliance loss" was
rejected: it was said in response that
"wasted expenditure is a recognised and
recoverable type of loss, well within the compensatory
principle".[17]
- To
characterise wasted expenditure as a distinct category of loss or damage, it is
unnecessary to go as far as Fuller and Perdue
did when they famously wrote of
the plaintiff in an action for breach of contract having a "reliance interest"
as well as an "expectation
interest" and postulated the availability of an award
of reliance damages having as its object "to put [the plaintiff] in as good
a
position as [the plaintiff] was in before the promise was
made".[18] Within the
framework set by the principle in Robinson v Harman, a sufficient
conceptual basis for characterising wasted expenditure as a distinct category of
damage lies in recognising that wasting
of past expenditure upon failure of
performance is a legally cognisable respect in which the plaintiff is worse off
as a result of
non-performance in comparison to
performance.[19] The
phenomenon in respect of which the plaintiff is entitled to be compensated is
the fact that non-performance by the defendant
has caused expenditure incurred
by the plaintiff to have been thrown away. Compensable damage lies in the simple
fact that the plaintiff
has incurred expenditure which, because of
non-performance, is incapable of yielding any benefit or gain to the plaintiff.
- Difficulty
of proof of any benefit or gain which the plaintiff might have expected from
performance of a contract might well furnish
a practical explanation for why a
particular plaintiff might choose to frame a claim for damages wholly or partly
as a claim for
wasted expenditure in a particular case. The reality that
difficulty of proof of such benefit or gain is frequently encountered in
practice by plaintiffs in a variety of different factual scenarios is a reason
for recognising wasted expenditure as a distinct category
of compensable damage.
Not all contracts are entered into with a view to direct and immediate profit:
some contracts are loss-leading,
some are speculative, some are integers in a
larger commercial enterprise, some are entered into not with a view to profit at
all
but in pursuit of a non-commercial benefit or gain as in a case of
government procurement.
- But
difficulty of proof of such benefit or gain as might have been expected from
performance of a contract, on this analysis, is
neither a precondition to nor a
justification for awarding damages for wasted expenditure in the circumstances
of a particular case.
The potential for damages to be awarded for wasted
expenditure in the circumstances of a particular case arises because wasted
expenditure
is without more a recognised category of compensable damage.
-
Wasted expenditure is easily proved and quantified. The damages attributable to
that damage are ordinarily established by nothing
more than the plaintiff
proving the quantum of the expenditure it has incurred in reliance on an
expectation of performance of the
contract whilst giving credit for any benefit
or gain it has obtained from the expenditure despite non-performance of the
contract.
- The
outworking of the Robinson v Harman principle in its operation as a
ceiling on the overall damages recoverable nevertheless requires that the
defendant be afforded an
opportunity to prove that the expenditure which the
plaintiff has established is in fact incapable of yielding it any benefit or
gain by reason of non-performance of the contract is expenditure which would
have yielded it no benefit or gain even if the contract
had been performed. For,
if one thing should be uncontroversial in this theoretically fraught area of the
common law, it is that
"[w]e will not in a suit for reimbursement for losses
incurred in reliance on a contract knowingly put the plaintiff in a better
position than [the plaintiff] would have occupied had the contract been fully
performed".[20]
- The
soundness of that approach to the outworking of the Robinson v Harman
principle in assessing damages attributable to damage constituted by wasted
expenditure is illustrated in a case of a contract entered
into by a plaintiff
as part of a larger profit-making venture by the decision of the United States
Court of Appeals for the Second
Circuit in L Albert & Son v Armstrong
Rubber Co.[21] The
correctness of L Albert & Son was accepted in The Commonwealth v
Amann Aviation Pty
Ltd,[22] about which more
will be said below, and has been accepted in courts in other common law
jurisdictions.[23]
- The
Court of Appeals was concerned in L Albert & Son with an appeal from
a judgment in an action for damages by a buyer against a seller for breach of a
contract for the sale of goods
constituted by late delivery of certain machines,
referred to as "Refiners", for use in the buyer's rubber production operation.
The Court of Appeals held that, without needing to prove that timely delivery
would have contributed to the buyer making a profit
from the rubber production
operation, the buyer was entitled to recover expenditure it had incurred in
laying a foundation for the
machines.
- Chief
Judge Learned Hand
said:[24]
"Normally a promisee's damages for breach of contract are the value of the
promised performance, less his outlay, which includes,
not only what he must pay
to the promisor, but any expenses necessary to prepare for the performance; and
in the case at bar the
cost of the foundation was such an expense. The sum which
would restore the Buyer to the position it would have been in, had the
Seller
performed, would therefore be the prospective net earnings of the 'Refiners'
while they were used (together with any value
they might have as scrap after
they were discarded), less their price –$25,500 – together with
$3,000, the cost of installing
them."
He continued:
"The Buyer did not indeed prove the net earnings of the 'Refiners' or their
scrap value; but it asserts that it is nonetheless entitled
to recover the cost
of the foundation upon the theory that what it expended in reliance upon the
Seller's performance was a recoverable
loss. In cases where the venture would
have proved profitable to the promisee, there is no reason why he should not
recover his expenses.
On the other hand, on those occasions in which the
performance would not have covered the promisee's outlay, such a result imposes
the risk of the promisee's contract upon the promisor. We cannot agree that the
promisor's default in performance should under this
guise make him an insurer of
the promisee's venture; yet it does not follow that the breach should not throw
upon him the duty of
showing that the value of the performance would in fact
have been less than the promisee's outlay. It is often very hard to learn
what
the value of the performance would have been; and it is a common expedient, and
a just one, in such situations to put the peril
of the answer upon that party
who by his wrong has made the issue relevant to the rights of the other."
He concluded:
"On principle therefore the proper solution would seem to be that the promisee
may recover his outlay in preparation for the performance,
subject to the
privilege of the promisor to reduce it by as much as he can show that the
promisee would have lost, if the contract
had been performed."
- Whether
affording such an opportunity or "privilege" is properly regarded as imposing a
legal onus on the defendant perhaps matters
little. The defendant bears a legal
onus of proving that the expenditure, which the plaintiff in fact incurred and
which was in fact
wasted in the event of non-performance, would still have been
wasted in the counterfactual of the contract having been performed
in the sense
that the claim of the plaintiff will prevail if the defendant does not so
prove.
Precedent
- The
foregoing explanation of legal principle is consistent with unanimous reasoning
in each of McRae v Commonwealth Disposals
Commission,[25] Carr v
J A Berriman Pty
Ltd,[26] and TC
Industrial Plant Pty Ltd v Robert's Queensland Pty
Ltd.[27]
- McRae
concerned an action for damages for breach of a contract for the sale of a
stranded oil tanker of indeterminate size and value. The
plaintiffs were the
putative buyers and intended salvagers of the tanker. The first defendant was
the Commonwealth Disposals Commission.
The breach of contract found was
constituted by breach by the Commission of a promise that such a tanker existed
at or near a specified
location.[28] Dixon and
Fullagar JJ (with whom McTiernan J concurred)
observed:[29]
"The practical substance of the case lies in these three factors – (1) the
Commission promised that there was a tanker at or
near to the specified place;
(2) in reliance on that promise the plaintiffs expended considerable sums of
money; (3) there was in
fact no tanker at or anywhere near to the specified
place. In the waste of their considerable expenditure seems to lie the real and
understandable grievance of the plaintiffs, and the ultimate question in the
case (apart from any question of quantum) is whether
the plaintiffs can recover
the amount of this wasted expenditure or any part of it as damages for breach of
the Commission's contract
that there was a tanker in existence."
- The
wasted expenditure which the plaintiffs had incurred and were held to be
entitled to recover comprised the cost of fitting out
a salvage expedition and
proceeding to the place where no tanker was to be
found.[30] Having concluded
that the wasted expenditure was within the reasonable contemplation of the
parties at the time of entering into
the contract of sale and so was not too
remote,[31] Dixon and
Fullagar JJ turned to address an argument of the Commission to the effect
that the plaintiffs had failed to discharge their
onus of proving that their
expenditure had been wasted given that the tanker might still have been found to
have been incapable of
profitable salvage even if it had existed at or near the
specified location.[32] The
denouement was as
follows:[33]
"The argument is far from being negligible. But it is really, we think,
fallacious. If we regard the case as a simple and normal
case of breach by
non-delivery, the plaintiffs have no starting-point. The burden of proof is on
them, and they cannot establish
that they have suffered any damage unless they
can show that a tanker delivered in performance of the contract would have had
some
value, and this they cannot show. But when the contract alleged is a
contract that there was a tanker in a particular place, and
the breach assigned
is that there was no tanker there, and the damages claimed are measured by
expenditure incurred on the faith
of the promise that there was a tanker in that
place, the plaintiffs are in a very different position. They have now a
starting-point.
They can say: (1) this expense was incurred; (2) it was incurred
because you promised us that there was a tanker; (3) the fact that
there was no
tanker made it certain that this expense would be wasted. The plaintiffs have in
this way a starting-point. They make
a prima-facie case. The fact that the
expense was wasted flowed prima facie from the fact that there was no tanker;
and the first fact is damage, and
the second fact is breach of contract.
The burden is now thrown on the Commission of establishing that, if there had
been a tanker, the expense incurred would equally have
been wasted. This, of
course, the Commission cannot establish. The fact is that the impossibility of
assessing damages on the basis of a comparison
between what was promised and
what was delivered arises not because what was promised was valueless but
because it is impossible
to value a non-existent thing. It is the breach of
contract itself which makes it impossible even to undertake an assessment on
that
basis. It is not impossible, however, to undertake an assessment on another
basis, and, in so far as the Commission's breach of contract
itself reduces the
possibility of an accurate assessment, it is not for the Commission to
complain."
- Three
points in this reasoning need to be highlighted. The first is that the
expenditure which the plaintiffs proved in fact to have
been incurred and in
fact to have been wasted by reason of non-performance of the contract was said
itself to constitute compensable
damage. The second is that proof by the
plaintiffs of that compensable damage was said, as in L Albert & Son,
to shift to the Commission the onus of establishing that the expenditure would
still have been wasted had the contract been performed.
The third is that no
part of the reasoning depended on any assumption or presumption that the
plaintiffs would at least have recovered
their expenditure had the contract been
performed. To the contrary, the prospect of successful salvage was accepted to
have been
uncertain even if a tanker had existed at or near the contractually
specified location.[34]
- J
A Berriman and TC Industrial Plant both illustrate the proposition
that a plaintiff is entitled to frame a claim for damages for breach of contract
to include a claim
for wasted expenditure distinctly from and in addition to any
claim the plaintiff might make for loss of profit up to the ceiling
set by the
principle in Robinson v Harman.
- J
A Berriman relevantly concerned an action by a builder for breach of a
construction contract constituted by delay in making a site ready for
construction to commence. Fullagar J (with whom Dixon CJ, Williams,
Webb and Kitto JJ concurred) referred to the builder's damages
having been
assessed "under three heads": "loss of profit on the contract"; "expenditure
incurred and wasted in 'keeping a team of
men together in anticipation of being
able to start work on the job'"; and an amount for which the builder was liable
to a subcontractor.[35] As to
the second of those identified heads of damage, his Honour remarked that
"[e]xpenditure so incurred and wasted would be recoverable
by way of damages,
and the amount awarded under this head was not
challenged".[36]
- TC
Industrial Plant concerned an action by a buyer against a seller for breach
of a contract for the sale of a stone crushing machine constituted by
breach of
an implied condition that the machine would be fit for the purpose of supplying
crushed aggregate to fulfil a contract
with the Commonwealth. The primary judge
awarded damages in the sum of (1) the "expenditure and liabilities incurred by
the plaintiff
in the course of and for the purposes of carrying out its contract
with the Commonwealth less the amounts paid to it by the Commonwealth
under that
contract" and (2) the estimated profits which the plaintiff would have made had
it been able to carry out its contract
with the Commonwealth and a further
contract.[37] Kitto, Windeyer
and Owen JJ rejected an argument of the seller that "the plaintiff could
not recover under both the heads of damage
upon which the [primary] judge based
his award but was bound to elect whether it would pursue its claim for
expenditure uselessly
incurred as a result of the defendants' breaches of
contract or, in the alternative, its claim to recover for the loss of the
profits
it would have earned had the crusher been fit for the purpose for which
both defendants knew it was
required".[38] Their Honours
said:[39]
"To sum the matter up, the seller (in effect) promised the buyer that the
machine was such that upon the buyer laying out £X
in acquiring and
installing the machine he would be able to get £X + Y by working it. For
breach of the promise the buyer, having
laid out his £X, may recover, if he
chooses, what the machine would have been worth to him if it had been as
promised (presumptively
£X) minus the actual value of the machine.
Alternatively he may recover £X+Y".
What was said to be "perfectly clear" was that "the plaintiff could not have
damages assessed on the one basis plus damages assessed
on the other
basis".[40]
- Turning
now to Amann
Aviation,[41] to say that
any explanation of the principle governing the recoverability of wasted
expenditure is wholly consistent with the reasoning
of the majority
(Mason CJ and Dawson J, Brennan J, and Gaudron J)
would be impossible given the notorious difficulty of extracting a ratio
decidendi from the various reasons for judgment in that
case.[42] The most that can
properly be said is that the explanation I have given can be seen to be
concordant with the core dispositive reasoning
of Mason CJ and Dawson J.
- Amann
Aviation concerned an action by a private contractor against the
Commonwealth for damages for repudiation of a contract to provide aerial coastal
surveillance services for a specified period subject to the prospect of renewal
and to the possibility of early termination for
cause.[43] Without needing to
prove that it would have profited from the contract, the plaintiff was held to
be entitled to recover damages
in the amount of the expenditure it had incurred
in reliance on an expectation of the Commonwealth performing the
contract.[44] The critical
aspects of the joint reasons for judgment of Mason CJ and Dawson J for
the present purposes are the following.
- Mason CJ
and Dawson J were clear in emphasising that the principle in Robinson v
Harman provides the framework for determining the category or categories of
compensable damage which a plaintiff might be found to have
sustained by reason
of a defendant's non-performance of the contract and the ultimate measure of
compensatory damages to which a
plaintiff might be found to be entitled. So much
is encompassed within the generality of their statement that "the expressions
'expectation
damages', 'damages for loss of profits', 'reliance damages' and
'damages for wasted expenditure' are simply manifestations of the
central
principle enunciated in Robinson v Harman rather than discrete and truly
alternative measures of damages which a party not in breach may elect to
claim".[45] That the
principle sets a ceiling on compensatory damages was made clear by them in
emphasising that "[t]he corollary of the principle
in Robinson v Harman
is that a plaintiff is not entitled, by the award of damages upon breach, to be
placed in a superior position to that which he or
she would have been in had the
contract been
performed".[46] TC
Industrial Plant was said by them to illustrate those
propositions.[47]
- Mason CJ
and Dawson J were also clear in stating, with specific reference to L
Albert & Son and McRae, that "a plaintiff has a prima facie case
for recovery of wasted expenditure once it is established that the expense was
incurred
in reliance on the promise of the party in breach, there being a
failure of performance by that
party"[48] and that
establishment by a plaintiff of a prima facie case for recovery of wasted
expenditure shifts the onus to the defendant "to
establish that such expenditure
would not have been recouped even if the contract had been fully
performed".[49]
- Their
Honours recognised that the recovery of damages for wasted expenditure under a
contract from which no net profit would have
been realised not only places the
plaintiff in the position the plaintiff would have been in had the contract been
fully performed
but also restores the plaintiff to the position the plaintiff
would have been in had the plaintiff not entered into the
contract.[50] Distancing
themselves from the view of the recovery of damages for wasted expenditure
vindicating a "reliance interest" in the sense
defined by Fuller and
Perdue,[51] they noted that
"[i]n this particular situation it will be noted that there is a coincidence,
but no more than a coincidence, between
the measure of damages recoverable both
in contract and in
tort".[52]
- With
reference to TC Industrial Plant, Mason CJ and Dawson J
rejected the notion that a plaintiff has an election, in the sense of an
unconstrained choice, as to whether
to frame its claim for damages as one for
the recovery of wasted
expenditure.[53] The gist of
their explanation was that how a plaintiff frames its claim for damages within
the framework set by the principle in
Robinson v Harman can be expected
to turn on the nature of the contract (which might or might not have been
entered into with a view to direct or immediate
profit) and on the plaintiff's
appraisal of the practical exigencies of proving and quantifying categories of
damage that might potentially
be available to be
claimed.[54]
- True
it is that their Honours said that in a case of damages assessed by reference to
wasted expenditure "the law assumes that a
plaintiff would at least have
recovered his or her expenditure had the contract been fully performed" and
observed that the approach
taken in L Albert & Son and McRae
"amounts to the erection of a presumption that a party would not enter into a
contract in which its costs were not
recoverable".[55] And true it
is that their Honours observed that the plaintiff in Amann Aviation faced
"difficulties" establishing "what its profits (if any) would have been had the
Commonwealth not repudiated the
contract".[56] But the point
to which these observations ultimately led was that the case was one "in which,
it being natural and appropriate for
[the plaintiff] to sue to recover its
wasted expenditure by way of reliance damages, the onus rested on the
Commonwealth of establishing
that the reliance expenditure would have been
wasted even if the contract had been
performed".[57]
- The
reasoning of Mason CJ and Dawson J cannot be taken to impose, as a
condition of a plaintiff succeeding on a claim for damages
for wasted
expenditure, that the plaintiff must establish a factual basis for assuming or
presuming that the plaintiff would have
recouped the expenditure had the
contract been performed. Nor can that reasoning be taken to impose, as a
condition of a plaintiff
succeeding on a claim for damages for wasted
expenditure, that the plaintiff must demonstrate that it meets some objectively
demonstrated
threshold of difficulty of proving loss of profit.
- The
reasons for judgment of Mason CJ and Dawson J are in those latter two
respects to be contrasted with those of the other two members
of the majority:
Brennan J and
Gaudron J.[58]
Brennan J and Gaudron J each saw the approach taken in L Albert
& Son and McRae as directed to the establishment and
quantification of damage constituted by loss of the contractually expected
benefit or gain to
which the wasted expenditure was directed and each saw the
approach as involving a reversal of the onus of proof of that damage.
They
differed, however, as to the justification for that reversal of the onus of
proof.
- Brennan J
explained the sufficient and necessary justification for the reversal of the
onus of proof as being that "the breach of
the contract itself makes it
impossible to undertake an assessment on the ordinary basis" in the sense that
it "is the defendant's
repudiation or breach which denies, prevents or precludes
the existence of circumstances which would have determined the value of
the
plaintiff's contractual
benefits".[59] His Honour
would accordingly have restricted application of the approach to a case in which
non-performance by the defendant was
demonstrated to have that practical
effect.[60]
- Gaudron J,
in contrast, saw the reversal of the onus of proof as a reversal only of an
evidentiary onus. Her Honour saw the justification
for that reversal of
evidentiary onus as lying in an assumption that the loss occasioned by
repudiation or breach of contract is
no less than the expenditure that has been
wasted, an assumption which might or might not be justified on the facts of a
particular
case.[61] Her
Honour said that "[a]n assumption to that effect is no more than the recognition
of the ordinary expectations of the world of
commerce that the value of a
contract will be no less than the cost of its
performance".[62]
- For
reasons I have given in explaining my understanding of the underlying legal
principle, I consider that the assessment of damages
according to the approach
taken in L Albert & Son and McRae is directed to the
establishment and quantification of a distinct category of damage constituted by
wasted expenditure and I do not
consider that the approach needs other
justification or is otherwise restricted. The reasons of Brennan J and of
Gaudron J express
competing justifications for the approach, each of which
would entail a concomitant restriction. Neither of those competing approaches
is
compelled by the doctrine of precedent.
- The
appellant draws attention to the observation by Bell, Keane and Nettle JJ
in Berry v CCL Secure Pty
Ltd[63] to the effect
that Amann Aviation could be seen as an illustration of the general
principle that a wrongdoer should suffer such uncertainty of proof as might
result
from its wrongful conduct. The observation was made with specific
reference to the reasoning of Brennan J and unquestionably reflects
his
Honour's justification for the approach taken in L Albert & Son
and McRae. However, the appellant overstates the significance of
the observation in seeking to treat it as an authoritative distillation of
the
reasoning underlying the holding in Amann Aviation. No issue concerning
the recovery of wasted expenditure arose for consideration in
Berry.
Application
- The
essential facts of the present case are as stark as they are uncomplicated. The
appellant entered into a contract with the respondent
under which the appellant
promised to take all reasonable action to apply for and register a plan of
subdivision and to grant the
respondent a 30-year lease of land. Having obtained
a licence to enter upon the land in the interim, the respondent proceeded to
spend $3.7 million constructing a commercial building on the land. The appellant
repudiated the contract, leaving the investment
in the building stranded.
- Those
facts are alone sufficient to establish the prima facie entitlement of the
respondent to recover in damages for breach of contract
the $3.7 million it had
spent which was wasted because of the repudiation of the contract. The appellant
failed to discharge its
onus of establishing that the respondent would have
wasted the expenditure even if the contract had been
performed.
Disposition
- For
these reasons, I agree that the appeal should be dismissed.
- GORDON J.
The appellant, Cessnock City Council ("the Council"), entered into an agreement
for lease with the respondent, 123 259 932
Pty Ltd, formerly Cutty Sark Holdings
Pty Ltd ("Cutty Sark"), for a 30-year lease over part of Cessnock
Airport, to operate from the day after the registration date of the plan of
subdivision
of the land ("the Plan"). Under the agreement for lease, the Council
promised to take all reasonable action to apply for and register
the Plan by 30
September 2011 ("the Sunset Date"), and in the meantime granted Cutty Sark a
licence to occupy the proposed Lot 104.
- While
in occupation of Lot 104, Cutty Sark built an aircraft hangar, at a cost of over
$3.6 million, from which it intended to operate
a business conducting joy
flights and advanced aerobatic training for pilots. In breach of the agreement
for lease, the Council did not take reasonable action to register
the Plan. Consequently, the Plan was not registered, either by the Sunset
Date
or at any later time, and the proposed 30-year lease was not granted. Cutty
Sark sued the Council for breach of contract, seeking
"reliance damages" –
namely, damages for losses suffered as a consequence of relying upon the
Council's contractual promise
which was breached. In this appeal, Cutty Sark
sought to recover the expense of constructing the hangar.
- The
primary judge held that Cutty Sark was not entitled to reliance damages, on the
grounds that the "presumption of recoupment"
did not arise and was, in any
event, rebutted, and awarded Cutty Sark nominal damages only. The Court of
Appeal overturned the primary
judge's decision and awarded Cutty Sark
$6,154,459.40 (inclusive of interest).
- The
detail of the relevant background is set out in the reasons of Edelman, Steward,
Gleeson and Beech-Jones JJ. For the reasons
that follow, I agree that the appeal
should be dismissed. I prefer to express the applicable principles in the
following terms.
Damages for breach of contract
- The
general rule at common law is "that where a party sustains a loss by reason of a
breach of contract, [they are], so far as money
can do it, to be placed in the
same situation, with respect to damages, as if the contract had been
performed".[64] The corollary
is that a plaintiff is not entitled, by an award of damages, to be placed in a
superior position to that which they
would have been in had the contract been
performed.[65] This
compensatory rule is fundamental to the assessment of contract damages; its
status as the "ruling principle" has been repeatedly
confirmed by this
Court.[66] And, of course,
the plaintiff bears "the legal burden of establishing the existence and
amount of the loss or damage" suffered by
reason of a breach of
contract.[67]
- The
measure of damages for breach of contract is calculated by reference to the
value of the promised performance, sometimes referred
to as
"expectation loss"[68]
or "expectation damages".[69]
"Losses directly incurred, as well as gains prevented", may be a legitimate
basis for compensation.[70]
Losses directly incurred include expenditures reasonably incurred in preparation
for performance or in part performance of the contract
(where such expenditure
is not otherwise reimbursed), such expenditures being "in anticipation of the
advantage that will come to
[the injured party] from completed
performance".[71] Gains or
advantages prevented are, of course, loss of
profits.[72] Damages for lost
profits are any amount by which gross receipts would have exceeded expenses
reasonably incurred.[73]
There can be no double recovery. Where a plaintiff establishes a loss of
profits, that calculation necessarily accommodates the expenditures
reasonably
incurred.
- It
is sometimes impossible,[74]
impossible with any
certainty,[75] or
difficult[76] to establish
the value of the promised or lost performance. In such cases, a plaintiff is not
left remediless or confined to nominal
damages. A plaintiff may seek to
establish, and recover, the losses directly
incurred[77] –
sometimes referred to as "reliance damages" – being the expenditure
reasonably incurred in anticipation of, or reliance
on, the promise of another
party to the contract that was wasted as a consequence of the breach by the
wrongdoer. That expenditure
is made in anticipation of the advantage that will
come to the injured party from completed performance, consistent with the
rationale
that ordinarily performance of a contract "results in advantage to
both parties over and above that with which they part in the course
of its
performance".[78] In some
cases, not inconsistent with that rationale, recovery of reasonable expenditure
(the directly incurred costs) has been assessed
by reference to a presumption or
"the presumption of
recoupment".[79]
- Damages
for wasted expenditure are not a separate measure or category of expectation
damages but a method of calculating damages
consistent with the compensatory
principle that a party is entitled to damages equivalent to the amount of money
required to put
them in the position they would have been in had the breach not
been committed or, put another way, in the position they would have
been in had
the contract been
performed.[80] As was said in
this Court more than 30 years ago: "the expressions 'expectation damages',
'damages for loss of profits', 'reliance
damages' and 'damages for wasted
expenditure' are simply manifestations of the central principle enunciated in
Robinson v Harman rather than discrete and truly alternative measures of
damages which a party not in breach may elect to
claim".[81] No question
of election arises.[82] That
is, this is not a plaintiff choosing between competing
remedies.[83]
- The
value of damages for wasted expenditure is the quantum of the relevant
expenditure, less any retained benefit accruing to the
plaintiff from the
expenditure.[84] The
plaintiff must establish that, but for the promise, they would not have spent
the money. The plaintiff is not worse off just
because they spent money. The
"wasted" expenditure must be linked to the breach of the contractual promise.
That is, the plaintiff
will recoup the expenditure reasonably incurred in
reliance on the defendant's promise that was wasted as a consequence of the
defendant's
breach and their failure to perform the
contract.[85]
Expenditure which would have been made anyway is not
recoverable.[86]
- There
is no distinction to be drawn between incidental and essential
expenditure.[87] The
remoteness limit is sufficient. As the Court of Appeal held, there is no
principled basis for confining the notion of expenditure
incurred
"in reliance on the defendant's contractual promise" to expenditure
required by the contract or required to enable the plaintiff
to perform their
contractual obligations. The notion that one would incur expenses only if it
were reasonable to suppose that they
would at least be recouped applies equally
to moneys expended in reliance on the promised performance as to those expended
in performing
or preparing to perform the contract.
- The
references in The Commonwealth v Amann Aviation Pty Ltd to
expenditure in preparation for or in performance of a contract do not confine
the award.[88] While such a
description sufficed to capture the relevant expenditure in Amann
Aviation, it would not capture the kind of expenditure held to be
recoverable, for example, in McRae v Commonwealth Disposals
Commission.[89] That
expenditure was not required by the contract or incurred in performance of, or
in preparing to perform, any contractual obligation.
The plaintiffs' only
contractual obligation was to pay the purchase price; they were not obliged to
salvage the tanker.[90] The
expenditure was incurred so that the plaintiffs could acquire and exploit the
property they acquired under the contract –
the (non‑existent)
tanker – or, put differently, so that they could derive benefit from the
contract.
- However,
not all wasted expenses are recoverable. There are necessarily some limits. As
earlier noted, the expenditure must be reasonable.
Reasonableness applies
to the nature and extent of the expenditure, not to the reasonableness of the
reliance on the promised
performance.[91]
Reasonable expenditure extends to expenditure that might naturally be
incurred in preparing for, performing, or exploiting the benefit
of the
contract, or that is or ought to have been contemplated by the defendant. In
other words, it is assessed by considering whether
the expenditure was in the
contemplation of the parties. It is not a form of
insurance.[92]
- The
wrongdoer, however, can seek to establish that the plaintiff should not recover
the wasted expenditure by reference to type and
amount of expenditure
(it not being reasonable on one or both of the bases just identified) as
well as adducing evidence of what
would have happened, recognising that the
latter may be difficult if not, in some cases, impossible. That is,
"[i]t will still be
open to a defendant ... to argue that, notwithstanding
the fact that it is impossible to assess what profits, if any, the plaintiff
would have made had the contract been fully performed, the expenditure claimed
by a plaintiff would nevertheless not have been recovered
even if" the defendant
had performed their
obligations.[93]
Put another way, it is open to the wrongdoer to prove that the plaintiff's
expenditure was, on the balance of probabilities, wasted
anyway. It is just
and fair that the wrongdoer, who caused the difficulty in proof, should bear the
onus of showing that the party
not in breach would have made a loss on the
contract.[94] As Chief
Judge Learned Hand said, "it is a common expedient, and a just one ... to put
the peril of the answer upon that party who
by [their] wrong has made the issue
relevant to the rights of the
other".[95] That is, where
the wrongdoer's breach has rendered assessment of damages on the basis of lost
profits impossible or very difficult,
principles of justice and fairness dictate
that it should be for the wrongful party to prove that the plaintiff would not
at least
have recovered their expenditure had the contract been fully performed
or, put another way, would have made a loss on the
contract.[96]
- The
creation of rules the application of which depends upon what findings of fact
can be made about what benefit or benefits performance
of the contract would
have realised to the plaintiff is unhelpful. It is unhelpful because the
determinative question will always
be what sum will put the plaintiff in the
position the plaintiff would have been in had the contract been performed. That
assessment
must be made in light of all relevant evidence adduced in the
particular matter. If, as here, all that is known is that: the plaintiff
outlaid money in the expectation
of performance by the defendant; the defendant
did not perform; the plaintiff has not shown that they would have made a profit
over
and above the expenditure; and the defendant has not shown that the
plaintiff would have made a loss if the contract had been performed,
then the
expenditure may be recovered.
- Damages
for wasted expenditure are not awarded on the basis that their award facilitates
proof of damage. There is no relaxation
of proof. The trial judge reaches a
concluded view on the quantum of damages based on findings that the plaintiff
did make outlays
in reliance on the defendant's promise that were wasted as a
consequence of the defendant's breach and non-performance, the plaintiff
did not
show that they would have made a profit and the defendant did not show that the
plaintiff would have made a loss, because
predicting the outcome of the
performance of the contract is "impossible", "impossible with any certainty" or
"difficult" in the
manner described
above.[97] Other than proof
of those facts, the trial judge does not undertake a forensic assessment of
the gravity of the wrongdoer's conduct.
Nor does the trial judge assess the
extent of the uncertainty that results from the breach and then use that
assessment as the basis for adjusting the burden placed on the
wrongdoer to
adduce evidence to show that the plaintiff would have made a loss. The need for
the defendant to show that the plaintiff
would have made a loss is not
proportionate to the extent of the uncertainty caused by the defendant. The
trial judge's task remains,
as it always has been, to decide what the evidence
shows will be the sum that will put the plaintiff in the position that they
would
have been in had the contract been performed. Put in different terms, if
the trial judge makes the findings described, those findings
show that awarding
the amount wasted will so far as the evidence reveals put the plaintiff
in that position.
- Finally,
aleatory contracts,[98] and
contracts of chance,[99] are
not contracts to which this method of calculation might apply. In those cases,
the uncertainty of gain or loss is inherent in
the nature of the contract; the
uncertainty cannot be said to have been caused by the breach of contract by the
repudiating party.
EDELMAN, STEWARD, GLEESON AND
BEECH-JONES JJ.
Introduction
- It
is long-established orthodoxy that damages for consequential loss for a breach
of contract are awarded only to place the plaintiff
in the same situation as if
the contract had been performed. The issue on this appeal is the method of proof
for a plaintiff to establish
the position that they would have been in if the
contract had been performed, where the plaintiff has incurred expenditure in
anticipation
of, or reliance on, the performance of a defendant's contractual
obligation and the defendant's breach of that obligation has the
effect that the
expenditure is wasted.
- As
will be explained in these reasons, that issue should be addressed as follows.
The legal onus to prove loss arising from a breach
of contract rests on the
plaintiff as the party seeking to recover damages. However, where a breach of
contract has resulted in (namely,
caused or increased) uncertainty about the
position that the plaintiff would have been in if the contract had been
performed, then
the discharge of the plaintiff's legal burden of proof will be
facilitated by assuming (or inferring) in their favour that, had the
contract
been performed, then the plaintiff would have recovered the expenditure
they reasonably incurred in anticipation of, or
reliance on, the performance of
the contract. The strength of this assumption or inference, and thus the weight
of the burden placed
on the party in breach to adduce evidence to rebut the
inference in whole or in part, will depend on the extent of the uncertainty
that
results from the breach. Expressed in this way, this facilitation principle is
tied to its rationale, namely the uncertainty
in proof of loss occasioned to the
plaintiff by the defendant's breach.
- The
appellant, Cessnock City Council ("the Council"), is the registered proprietor
of land on which the Cessnock Airport is located.
Against a background where the
Council had hoped to develop the airport and accompanying land, the Council
entered an agreement with
the respondent corporation to lease a prospective lot
at the airport to the respondent. The grant of the lease required subdivision
of
part of the Council's land. So a condition of the agreement for lease was that
the Council would take all reasonable action to
apply for and obtain
registration of the plan of subdivision by 30 September 2011. As
events transpired, that action required the
Council to spend around
$1.3 million. Not wishing to incur that cost, the Council breached the
condition and repudiated the agreement
for lease. The respondent never obtained
a lease.
- Prior
to the Council's repudiation, and in anticipation of, or reliance on, the
agreement for lease, the respondent spent almost
$3.7 million constructing
an "iconic" hangar on the land. But the respondent was not successful in
conducting businesses on the site
of the proposed lease. The respondent's
businesses failed. Following the Council's repudiation, the agreement for lease
was treated
as terminated and the Council acquired the hangar for $1. It is
common ground that by this time, at the latest, the respondent's
expenditure was
wasted, in the sense that the respondent could not recoup any of the
expenditure.
- The
respondent faced great difficulty in proving the consequential loss that it
suffered by reference to the position that it would
have been in if the Council
had performed its contractual obligations. The respondent's difficulties of
proof arose from multiple
uncertainties: if the Council had obtained
registration of the plan of subdivision, would the Council have further
developed the
airport and accompanying land? How soon would that development
have occurred? If development occurred, how much more business would
have been
attracted to the airport precinct? How would the respondent have responded to
any increase in business and operations at
the airport?
- Faced
with these potentially insurmountable uncertainties, the respondent relied upon
the principle described above that facilitated
its proof of loss by treating its
wasted expenditure as "prima facie" evidence of the amount that it would have
recouped or as the
"presumed" amount that would have been recouped. The primary
judge in the Supreme Court of New South Wales rejected the application
of that
principle to the circumstances of this case and awarded the respondent nominal
damages of $1. The Court of Appeal overturned
the primary judge's decision,
applied the principle, and awarded damages to the respondent of almost
$3.7 million.
- In
this Court, there was dispute about the basis for, and the nature and operation
of, the principle that the Court of Appeal applied
to facilitate the
respondent's proof of its loss. Consistently with the manner in which the trial
and the appeal to the Court of
Appeal had been run, the appeal to this Court was
brought on an all-or-nothing basis. The Council did not argue that the
respondent
would have recovered some lesser amount of its wasted expenditure.
And the respondent did not argue that it was entitled to a lesser
measure of
damages representing merely the reasonable cost of the action of obtaining
registration of the plan of subdivision to
which the respondent was
entitled.[100]
- Although
there was some disagreement between the parties about the effect of the decision
in The Commonwealth v Amann Aviation Pty
Ltd,[101] the
respondent's reliance on the principle that permits facilitation of its proof of
the position that it would have been in if the
contract had been performed is
broadly consistent with the reasoning of Mason CJ and Dawson J, as
well as Deane J, who spoke of the
principle as a "presumption" in favour of
the plaintiff, with Brennan J, who spoke of it as a "reversal of the onus",
and with Toohey
J and Gaudron J, who spoke of it as placing an
"evidentiary onus" on a defendant. The description "facilitation principle"
emphasises
that the principle is not rigid. All the circumstances must be
considered and the strength with which the principle applies to facilitate
a
plaintiff's proof by treating reasonably incurred, but wasted, expenditure as
likely to be recouped will depend upon the extent
of uncertainty caused or
increased by the defendant's breach. In this case, there was considerable
uncertainty as a result of the
Council's breach. The principle was correctly
applied by the Court of Appeal. The appeal should be dismissed with
costs.
Background
The Council awards a tender for development of the airport
- The
appellant is a local council which owns land on which the Cessnock Airport is
located. The Cessnock local government area, as
described by the Council, is
"within relatively easy driving distance from Sydney, Newcastle and the Coast"
and includes the Hunter
Valley wine growing area, "Australia's oldest wine
region and one of the most famous". The wine industry employed 2,500 people and
the region recorded 737,240 visitors in 1994.
- In
1998, the Council requested expressions of interest for the development and
management of the airport. The Council explained in
the request that the airport
was located in the "rapidly developing Vineyards area of the Lower Hunter
Valley" and that it was one
of only two airports in the lower Hunter Valley. The
Council said that it considered the airport to have "significant potential to
accommodate expanded operations for light RPT/Commuter, charter, general
aviation and sports aviation traffic".
- The
request for expressions of interest contained a "Cessnock Aerodrome Development
Plan". In that development plan, the Council
explained that among its proposals
was a lengthened runway to accommodate significantly larger, long-range
aircraft, an upgrade of
terminal facilities for regular passenger and charter
services, and subdivision of some of the airport land into lots for lease or
sale, to be used for air-related activity. The Council observed that "the number
of major projects before it" meant that it would
not be appropriate for the
Council to fully fund the airport development from its own resources. The
Council said that it may be
possible for the development to be funded from a
combination of sources: sale of excess land, sale of land within the airport
environment
for air-related activity, or attaching private investor
funding.
- In
November 1998, Aviation & Leisure Corporation Pty Ltd ("ALC"), a
company unrelated to the respondent, submitted a response
to the Council's call
for expressions of interest. ALC sought "to coordinate the development of
Cessnock Aerodrome in conjunction
with various parties", including the Council.
ALC observed that there were "great potential economic benefits from an upgrade
of
Cessnock Aerodrome which will facilitate increased visitor numbers to the
region".
- A
key aspect of ALC's development strategy was "[a]dd[ing] non aviation activities
to available land to help pay for the infrastructure
costs to upgrade the
runway, navaids and terminal". Additional services proposed by ALC included the
provision of accommodation,
entertainment, hospitality and retail. ALC
emphasised that it "[was] ready and keen to move this project to completion very
quickly"
and estimated the cost of the project as greater than
$3.8 million. However, ALC also noted that "[t]he viability of the project
will depend on adding a mix of non aviation activities to improve cash flows on
top of existing activities which should also be expanded".
- On
2 June 1999, the Council awarded ALC preferred tender status. Earlier,
the Council had invited ALC to submit a tender for its
management and
development of the airport. In its tender presentation to the Council, ALC
reiterated that it wished to proceed with
the project as soon as possible. ALC
identified the airport as a "prime piece of real estate" with "opportunities to
introduce to
Australia ... private hangars and 'Aerotel houses'", describing
those concepts (referred to by the courts below as "hangar homes")
as popular in
the United States of America but virtually unknown in Australia.
- ALC
also proposed "an aircraft display hangar ultimately attached to the terminal to
house a vintage aircraft through glass sides
to the terminal and parking areas".
With respect to hangarage, ALC identified opportunities for all of the
following: (i) large maintenance
hangars as already exist;
(ii) smaller "strip" hangars for individual aircraft; (iii) "USA
style" Aerotel Units combining accommodation
with aircraft and car parking; and
(iv) larger USA style houses combining accommodation with aircraft and car
parking. ALC identified
the "financial imperative to allow sufficient
development of the total site to achieve an overall profitability". With respect
to
the Council's contribution to development, ALC suggested that "the Council
should consider an ongoing input as long as its cash contribution
can be seen to
be reducing each year".
- ALC's
proposal was attractive to the Council because it had been represented as a way
to produce an income stream to help the Council
pay for the development of the
airport, of which registration of the plan of subdivision was the first
step.
The process of development begins
- In
July 2002, the Council resolved that parts of the airport would be leased
to ALC with a view to the future development of the
airport. In
December 2003, the Council, in its capacity as a developer and a registered
proprietor, lodged a development application
for the consolidation of the
airport land into two lots and the subsequent subdivision of Lot 2 into 25
further lots, one of which
(proposed Lot 104) was the subject of the later
agreement for lease to the respondent.
- In
March 2004, the Council entered a three-year lease and management agreement
with ALC. The lease provided that if the plan of subdivision
was registered by
30 June 2011, the Council would grant a 25-year lease to ALC upon
expiry of the initial lease. The initial term
of the lease to ALC was
subsequently extended by agreement, with the extension reflecting the time
required to register the plan
of subdivision.
- In
July 2004, the Council adopted a development control plan for the
airport.[102] The
development control plan and the development itself had purposes that included:
permitting development to capitalise on the advantages
of the airport site and
its strategic location; facilitating environmentally responsible development to
maximise the economic benefits
to the Cessnock region; and encouraging
appropriate ancillary development.
- As
repeated in later Council documents, the development control plan identified the
airport's location as one of its developmental
advantages. The plan identified
zone 1 of the airport as the hangar and development area, which included
currently vacant land proposed
to be used for additional hangars and related
development and for the residential accommodation units, or hangar homes,
associated
with private hangars. An appendix contained specific guidelines for
aircraft storage and maintenance hangar buildings and the plan
contemplated
production of detailed design guidelines for the private hangar and apartment
accommodation as well as development of
a motel site. Zone 3, the
"[t]erminal area", was identified as including an area proposed for additional
airport related development,
including airport and tourist related shops.
Zone 4 was identified as the "[a]ssociated land uses" area "to be developed
for tourist
related purposes complimentary [sic] to the airport".
- On
17 November 2004, the Council, acting in its capacity as an approving
authority, approved the development application that it
had made in its capacity
as developer and registered proprietor of the airport. One condition imposed by
the Council, condition 23,
was that the proposed lots be "connected to
Hunter Water Corporation's reticulated sewerage system". Although the
consolidation of
the airport land into two lots was registered, the plan of
subdivision of Lot 2 into 25 further lots (including proposed Lot 104)
was never registered by the Council.
The respondent enters an
agreement for lease
- Mr Johnston,
who became the principal of the respondent, was a property developer with an
interest in aircraft. In April 2004, Mr
Johnston and his business
partner had met with the Corporate and Community Services Manager for the
Council to discuss a suitable
site for a hangar in which to house aircraft owned
by Mr Johnston or entities related to him. Mr Johnston and his
business partner
thought that the hangar could also incorporate an aviation
museum and an entertainment venue for corporate events. Around July 2004,
Mr Johnston obtained a copy of the Council's development control plan.
- In
April 2005, a solicitor acting on behalf of Mr Johnston submitted a
development application for a proposed hangar on Lot 104 of
the Council's
proposed subdivision. The application provided that the site would be in
operation 24 hours a day, seven days a week.
The estimated cost of the work
was $560,000. Development consent was granted on 28 July 2006.
- Between
August 2005 and April 2007, the solicitors for the Council and the
solicitor for Mr Johnston negotiated the terms of an agreement
for lease by
which the Council promised to grant a 30-year lease of proposed Lot 104
from the day after the registration of the plan
of subdivision. The parties to
the agreement for lease were the Council (as proposed lessor) and the respondent
(as proposed lessee).
The respondent was a corporation which Mr Johnston
incorporated on 27 December 2006 as Cutty Sark Holdings Pty Ltd. The
agreement
for lease was executed by the Council on 26 July 2007,
following its execution by the respondent.
- The
agreement for lease contained extensive provisions in relation to works to be
conducted by the respondent. The respondent was
given a licence, for an
increasing annual fee which started at $29,000, to enter the area of proposed
Lot 104 for the permitted use
of the land as an aircraft hangar. The work
contemplated by the agreement for lease included the construction of a hangar
which the
Council was aware would cost around $1.8 million and would be
designed by a renowned architect, Peter Stutchbury. The hangar was
described by
the primary judge as
"iconic".[103]
Clause 16.8 of the proposed lease that was annexed to the agreement for
lease provided that, on the expiry or termination of the
lease, the hangar would
be transferred to the Council unencumbered for $1.
- The
proposed lease to the respondent of prospective Lot 104 was subject to
registration of the plan of subdivision. By cl 4.2(a)(2)
of the agreement
for lease, the Council promised to take all reasonable action to apply for and
obtain registration of the plan of
subdivision by a "Sunset Date" of
30 September 2011. If the plan of subdivision was not approved and
registered by the Sunset Date,
then each party had a power to terminate the
agreement.
The respondent builds the hangar and conducts
businesses from it
- From
May 2007, after the Council's grant of development consent for the hangar on 28
July 2006 and very shortly before the execution
of the agreement for lease by
the Council, the respondent began construction of the hangar on proposed
Lot 104. Services were connected
to the hangar in March 2009.
- At
various times between July 2009 and June 2011, the respondent operated
three businesses from the hangar. The first business was
an adventure flight
business which the respondent operated between July and November 2009. The
second business was an aircraft museum
which the respondent operated between
September 2009 and February 2010. The third business was a corporate
venue hire business which
the respondent operated between August 2009 and
June 2011. In the financial year 2009/2010, the respondent made a loss of
$52,185.06
(with a depreciation cost for buildings of $42,292.29 and interest of
$88,038.85 on borrowings to build the hangar). In the financial
year 2010/2011,
the respondent made a loss of $13,909.94 (apparently not accounting for
depreciation and interest).
- By
the Sunset Date, and without development of the airport, the three businesses
plainly were not profitable. Mr Johnston gave evidence
that the businesses
were not sustainable because without the subdivision and development of the
airport it was difficult to attract
business. He said that with his "tenure" (a
lease of Lot 104 following subdivision) he "would probably say I think I
can make it
work. But Council would have had to develop the airport that was
also promised."
The Council chooses not to fulfil the
subdivision condition
- From
the time that the Council granted itself the development consent on
17 November 2004, the Council engaged consultants to produce
feasibility reports and to obtain quotations for the work involved in fulfilling
the Council's conditions in the development consent,
including
condition 23, which required the proposed lots to be connected to Hunter
Water Corporation's reticulated sewerage system.
The Council gave the
consultants a budget for compliance with the development consent of
$789,000.
- On
1 February 2010, the consultants informed the Council that they
estimated a further $1,317,764 was required to comply with the
development
consent. Within the Council, a bid was placed to the Council's Infrastructure
Strategy Section for allocation of $1,317,800
to the "Hunter Valley Airport
Development Consent". It was expected that this amount would eventually be
offset by income from the
airport development. In 2010 the Council's financial
position included approximately $79 million expenditure on public works, an
operational position (excluding capital income) of $3,292,000 and unrestricted
cash and investments of $1,634,000. But the discretionary
bid was refused.
- On
29 June 2011, one day before the expiry of ALC's lease and management
agreement, the General Manager of the Council informed ALC
that the Council
"won't be proceeding with the subdivision of the land at the airport" because
the Council had "no intention of spending
about a million dollars fixing the
sewerage". On 1 December 2011, the Council terminated its agreements
with ALC.
- On
13 September 2011, shortly before the Sunset Date of
30 September 2011 in the agreement for lease between the Council and
the
respondent, the General Manager of the Council wrote to the solicitor for
the respondent saying that the Council had "been unable
to achieve the
registration of the plan of subdivision within the timeframe anticipated in the
agreement for lease". The Council
offered the respondent a 25-year exclusive
licence on the same terms as the proposed lease or a series of leases for
successive terms
of five years or fewer.
- On
20 December 2011, the solicitor for the respondent declined the
Council's offer. The solicitor observed that the respondent had
spent over
$2.7 million on the hangar venue. The solicitor added that the respondent
"would not have entered into the Agreement for
Lease if there had not been the
assurance the subdivision would proceed and allow a 30 year lease to be
granted". He emphasised that
the respondent entered the agreement "hoping his
building would be able to contribute to the Cessnock business and tourism
development"
and that the respondent was "committed to endeavouring to find new
uses of the building".
The respondent is deregistered and the
Council acquires the hangar
- On
22 December 2011, the respondent made its last payment of licence
fees, being an amount of $14,408, for occupation of proposed
Lot 104 under
the agreement for lease. In mid-2012, the respondent ceased occupation of
proposed Lot 104 and the hangar. In September
2013, the respondent
disconnected power to the hangar as it could not pay the cost of the
electricity. In September 2015, the respondent
was deregistered by the
Australian Securities and Investments Commission ("ASIC") for the non-payment of
fees.
- Following
the deregistration of the respondent, the Council engaged in communications with
ASIC about matters including the termination
of the agreement for lease and the
effect of cl 16.8 of the proposed lease with the respondent, which
permitted all improvements
on proposed Lot 104 to become the property of
the Council upon payment of $1 following determination of the lease (which was
not
granted). On 11 May 2016, ASIC accepted $1 from the Council in
exchange for transfer of the hangar to the Council. On
6 December
2016, the Council entered a lease agreement for the hangar
with a new tenant.
The Council continues to explore development
of the airport
- The
Council took no subsequent action toward subdivision of the airport or to fulfil
the sewerage and water infrastructure requirement
in condition 23 of the
development consent. Nevertheless, the Council remained enthusiastic about the
prospects for development of
the airport. On 15 August 2012, the
Council resolved to endorse a nomination of the airport as a Major
Infrastructure Project for
the purpose of seeking funding from the Hunter
Infrastructure and Investment Fund. The Council resolution followed the
recommendation
of a report by its Strategic Asset Planning Manager. The report
identified the purpose of the Cessnock Aerodrome Terminal project
as the
provision of "terminal space, offices and hangar space for businesses looking to
establish and expand at Cessnock Airport".
- The
development proposed in the report provided "for a series of modular
offices/shop-fronts around the perimeter ... for businesses
operating at the
Aerodrome ... as well as a lounge area for customers". The remainder of the
hangar space was to "be retained for
leasing as aircraft hangar space or any
other business opportunities [that complied with the relevant guidelines]". The
report described
the project as "an opportunity ... to acquire a
revenue-generating asset".
- Notably,
the project endorsed in the report involved the acquisition and refurbishment of
the hangar constructed by the respondent.
The report observed that in 2012 the
Council had "received around twelve requests for both hangar space and office
space from businesses
looking to establish or expand at [the airport] and, at
present, Council is unable to satisfy this demand". The report described
the
grant funding as "an opportunity for Council to meet, in the short-term, this
demand from businesses" as well as providing "an
ongoing revenue stream for
Council" and "bring[ing] an iconic building into public ownership". These
matters were repeated by the
Council in its application for funding, but the
application was ultimately unsuccessful.
- The
Council continued to explore development of the airport, whilst recognising the
need for sewerage and water infrastructure to
attract investment and expand
business activity at the airport. In January 2014, the Council adopted the
Cessnock Airport Strategic
Plan, which focused upon the location of the airport
as key to its development potential, identifying its unique value proposition
as
its status as the "Gateway to the Hunter Valley". The Strategic Plan noted the
"limited" future of competitor airports and the
"capacity for future development
on the site". The Strategic Plan noted that "[s]ignificant infrastructure
investment could be funded
from grants or loans".
- There
is no evidence that the Council seriously pursued the possibility of a loan to
fund development of the airport. But on 14 August
2014, the Council
submitted an Expression of Interest as part of the Restart NSW "Resources for
Regions 2014-2015" round of funding,
seeking approximately $6.95 million.
The project for which funding was sought was not merely the acquisition and
refurbishment of
the hangar constructed by the respondent. It was an upgrade of
the entire airport precinct "to realise the community's vision of
[the airport]
being a well-planned and serviced facility that attracts
environmentally-responsible economic development opportunities
to the Cessnock
region". The funding application identified "large tracts of land" on the
airport site as available for development,
noting the absence of sewerage and
water connection as having "drastically impeded investment as well as inhibiting
the expansion
of existing businesses". The Council sought a "one-off cash
injection" which it planned to supplement with its own contribution of
almost
$300,000. The timeframe for project delivery was forecast to be within
two years.
- In
2020, the Council's updated Strategic Plan proposed a Precinct Masterplan for
the development of the airport which divided the
airport into five precincts.
Precinct 2 included additional private hangars along the length of the
runway, a historical museum area,
and extension of the runway provided external
funding was available. Precinct 3 was designated as including area for
commercial business
opportunities, including accommodation hangars. The updated
Strategic Plan noted that the airport would benefit from "[i]mproved
infrastructure to the western side as funding becomes available". Hangar homes
were identified as a potential business opportunity.
- The
updated Strategic Plan revealed that the Council was reluctant to "[u]ndertake
significant capital works to attract business"
on the basis that "[t]here is no
guarantee that this would work [to generate additional business], and is likely
to only add to the
ongoing maintenance costs in future years". The Council was
similarly cautious regarding proposals to enter into some form of joint
arrangement, management or corporatisation of the airport. The Council
considered "specific improvements to maximise income" as the
"most appropriate
option" for management of the airport and observed that there are "a number of
business opportunities waiting to
be developed for this site, [which] should be
acted upon". The updated Strategic Plan concluded that "[t]here appears to be
significant
interest in the Airport generally and this should capitalised [sic].
Marketing of hangar land, hangar space, and other business opportunities
should
be a priority."
The respondent commences these
proceedings
- On
5 June 2017, the respondent was reinstated by an order of the Supreme
Court of South Australia. In September 2017, the respondent
commenced
proceedings in the Supreme Court of New South Wales principally alleging that
the Council had breached the agreement for
lease and seeking recovery of damages
based on the respondent's wasted expenditure in construction of the
hangar.[104] Subject to
some dispute about quantum of various construction costs, the case was litigated
on an all-or-nothing basis. At no stage
did the Council attempt to argue an
alternative case that the respondent would have recouped only part of its
expenditure.
The decisions of the primary judge and Court of
Appeal
The decision of the primary judge
- The
primary judge (Adamson J) held that the Council had breached
cl 4.2(a)(2) of the agreement for lease, which had required the
Council to
take all reasonable action to apply for and obtain registration of the plan of
subdivision by the Sunset Date of 30 September
2011. The Council
breached this obligation by failing to commit funds to connect the proposed lots
to sewerage by the Sunset Date
of 30 September 2011. That breach was the
effective cause of the non-registration of the plan of subdivision by the Sunset
Date and
the failure of the proposed lease to come into effect. The primary
judge also rejected the Council's submission that the agreement
for lease had
excluded the Council's liability for damages.
- As
to the extent and quantification of the respondent's claim for damages based on
its wasted expenditure, the primary judge held
that a plaintiff could only
recover damages based on wasted expenditure, without the usual proof that the
expenditure would have
been recouped, if the nature of the breach rendered it
"impossible" to assess damages on that usual
basis.[105] Further, the
primary judge held that the Council was not contractually bound to develop the
airport and the risk of no development
was borne by the respondent, so no
presumption of loss could arise in favour of the respondent consequent upon the
Council's failure
to develop the airport.
- Nevertheless,
the primary judge concluded that even if it could be "presumed" that the
respondent would have recouped its expenditure,
the Council had rebutted that
"presumption". The primary judge essentially relied upon two matters in
reasoning that the Council
had rebutted any "presumption" that the respondent's
wasted expenditure would have been recouped. First, the primary judge held that
there was "little demand" for particular lots and hangar homes at the airport
and that "there was little interest beyond the plaintiff's,
in the further
development of the
airport".[106] Secondly,
the primary judge placed considerable emphasis on the unprofitable nature of the
respondent's businesses, holding that
the respondent may have been better off
without its obligations to pay licence fees under the agreement for lease
because the surrounds
of proposed Lot 104 might not have been developed and
the respondent had shown itself unable to conduct its businesses
profitably.[107] As for the
possibility of a lack of development of the airport, the primary judge found
that although it was not impossible for the
Council to have paid
$1.3 million to connect the proposed lots to sewerage, the Council was in
"a difficult financial position" and
was barely able to fulfil its public
functions, with limited capacity to service any substantial
loan.[108]
- The
primary judge also held that, in any event, the respondent's wasted expenditure
consequent upon the Council's breach was too
remote to be recovered as damages.
The primary judge relied upon factual matters for this conclusion including: the
uncertainty of
registration of the plan of subdivision; that the Council and the
respondent had contemplated that no lease might be granted; and
that the hangar
would eventually be transferred to the Council for
$1.[109]
- Ultimately,
the primary judge awarded the respondent nominal damages of $1 for the Council's
breach of the agreement for lease.
The decision of the Court of
Appeal
- The
respondent successfully appealed to the Court of Appeal (Brereton JA;
Macfarlan and Mitchelmore JJA agreeing). In the Court of
Appeal, the
Council did not contest the primary judge's finding of breach. The Court of
Appeal held that the failure by the Council
to take reasonable action to procure
registration of the plan of subdivision, and the Council's statements that it
did not intend
to do so, amounted to a continuing repudiatory breach which was
accepted by the respondent when it vacated the premises, thereby
terminating the
agreement for
lease.[110]
- The
Court of Appeal held that there was a "presumption", not confined to cases of
"impossibility" of proof by a plaintiff, that wasted
expenditure caused by a
defendant's breach of contract could be recovered, including all wasted
expenditure reasonably incurred in
anticipation of, or reliance on, the
performance of the defendant's contractual promise, not merely expenditure that
was incurred
pursuant to a contractual obligation, or required to perform the
contract.[111] The absence
of any obligation upon the Council to develop the airport, and the risk that it
might not be developed, was only relevant
to the "presumption" to the extent
that it may show that it was not reasonable for the respondent to rely upon the
obligation that
was breached in incurring expenditure to construct the
hangar.[112]
- The
Court of Appeal held that the respondent could rely on the "presumption" because
the respondent's expenditure of $3,697,234.41
on construction of the hangar had
been wasted in anticipation of, or reliance on, the performance of the promise
by the Council that
it would take all reasonable action to apply for and obtain
registration of the plan of subdivision by the Sunset Date of
30 September
2011.[113]
- As
to whether the "presumption" was rebutted, the respondent successfully
challenged the primary judge's finding that there was little
demand for
particular lots and hangar homes at the airport and little interest in the
further development of the airport. As Brereton
JA explained, the evidence
had
revealed:[114]
"a significant possibility of expansion and development of the airport, with
Council documents over the decade from 2011–2020
consistently referring to
the increased demand for hangarage and the Council's ambitions for development
of the airport; and had
the Plan been registered, there would still remain [in
2022] another 19 years until 2041 for that to occur".
- As
to whether the damage was too remote to be recoverable, the Court of Appeal held
that it ought to have been plain to both parties
at the time the contract was
made that a failure by the Council to perform its obligation under
cl 4.2(a)(2) would result in the
respondent wasting its expenditure in the
construction of the hangar. That damage was therefore considered to fall within
the second
limb of Hadley v
Baxendale,[115] and the
factual matters relied upon by the primary judge did not make the damage too
remote.[116]
- It
may be that the question of remoteness of damage is better analysed by reference
to the foreseeability of the respondent's lost
potential revenue rather than the
foreseeability of its wasted expenditure. The wasted expenditure, in the
language used by the Court
of Appeal, is relevant only to "enliven the
presumption" that the respondent would have made revenue of at least that
amount.[117] On that basis,
the prospect of a loss of future potential revenue would plainly be within the
knowledge that the parties would be
taken to have had at the time of entering
into the contract, sufficient for the general principle in Hadley v Baxendale
to apply.[118] Perhaps
for that reason, the only issue upon which the Council sought, and obtained,
special leave from this Court concerned whether
it could be accepted that the
respondent had established that, but for the Council's repudiation, it would
have obtained revenue
in an amount sufficient to recoup its
expenditure.
The issue in this Court
- On
appeal to this Court, there was no dispute that the Council repudiated the
agreement for lease. The grounds of appeal in this
Court were confined to
whether the Court of Appeal erred in concluding that "a presumption arose that
the respondent would at least
have recouped its wasted expenditure if the
contract between the [Council] and the respondent had been performed" and that
"the presumption
was not rebutted in the circumstances of this
case".
Damages for consequential loss arising from a breach of
contract
The Australian and English positions
- From
the early nineteenth century, with the rise of the will theory of contract law
and the objective approach to
agreement,[119] English law
recognised that the basis for the remedial response of damages for a breach of
contract was that damages were to be assessed
objectively by reference to lost
expectations.[120] Although
the assessment of damages was generally a matter for a jury in the early
nineteenth century, juries were guided by judges
as to "a general premise that a
party whose contract had been breached was entitled to be placed in the position
[they] would have
been in had the contract been
performed".[121] In 1846,
Pollock CB remarked that although questions of damages were for the jury,
"there are certain established rules according
to which they ought to find; and
here there is a clear rule—that the amount which would have been received
if the contract
had been kept, is the measure of damages if the contract is
broken".[122]
- Nearly
two centuries later, it is now well established that there is only one measure
of consequential losses for a breach of contract.
As many decisions of this
Court have held,[123] that
is the measure that provides a sum of money that places the plaintiff "in the
same situation ... as if the contract had been
performed".[124] This
description of damages for breach of contract necessarily requires the rejection
of any notion that recovery of contract damages
for consequential losses could
aim to put the innocent party in the position they would have been in if there
had been no contract
at all. There will be cases where the impossibility of a
precise calculation of damages, and the "once and for ever" nature of
damages,[125] might mean
that an award of damages could later be discovered to have overcompensated a
plaintiff by providing the plaintiff with
more than they would have received if
the contract had been performed. But an award of damages for a breach of
contract should not
permit a court knowingly to allow a plaintiff to avoid a bad
bargain by being put in the position they would have been in if the
contract had
not existed.[126]
- In
Australian and English law, therefore, it is not sufficient for recovery of
consequential loss suffered by a breach of contract
that: (i) the plaintiff
spent money in anticipation of, or reliance on, performance of a defendant's
contractual obligation; and
(ii) that money was wasted or partly wasted
after taking account of any benefit obtained by the plaintiff from the
expenditure. These
two matters are not enough because if the money would never
have been recovered on performance of the contract without any breach
of
contract, then the plaintiff has no consequential loss. It must also be shown
that (iii) the money was wasted because of the breach of contract. In
other words, the plaintiff would have recovered the money if that obligation had
not been breached. The
issue in this case concerns the manner of proof in
relation to (iii).
- The
approach described above explains this Court's rejection of the notion that
"reliance" losses and "expectation" losses are alternative
measures of damages
between which a plaintiff can
elect.[127] Although labels
such as "reliance loss" and "expectation loss" can be
unhelpful,[128] when
"expectation loss" is used to describe the measure of consequential loss
suffered by a plaintiff—by comparing the plaintiff's
position after breach
with the position they would have been in if the contract had been
performed—then it is the only measure
of consequential loss. Hence, any
award of contract damages that is based on expenditure in anticipation of, or
reliance on, performance
of a contract has been described as a "'proxy'
for",[129] or "species
of",[130] recovery of
expectation loss: "the idea that protection of the reliance interest is an
alternative measure of damages is a
myth".[131] The reliance by
a plaintiff upon a contract is merely part of an alternative way of proving the
plaintiff's loss, that is, the position
that they would have been in if the
contract had been performed.
- In
summary, this understanding of consequential loss for breach of contract has the
following effects:
- When
calculating the consequential loss suffered by a plaintiff due to a defendant's
breach of contract, the goal, in general terms,
is to put the plaintiff in same
the position as if the contract had been performed.
- The
calculation of a plaintiff's consequential loss will permit the plaintiff to
recover expenditure reasonably incurred in anticipation
of, or reliance on, the
performance of the contractual obligation that was breached but only to the
extent that the expenditure would
have been recovered but cannot now be
recovered ("wasted expenditure"). Of course, the plaintiff can also recover any
additional
profit that would have been obtained from the contract but, in this
event, the plaintiff would simply focus on the total profits
that would have
been made, with the wasted expenditure merely being an expense in the production
of those profits.
- In
assessing the loss that can be recovered, that loss which is due to unreasonable
or improvident actions of the plaintiff is generally
disregarded by application
of the rules of mitigation of loss. And that loss which is too remote is
disregarded by application of
the rules of remoteness of loss.
- None
of these propositions is controversial. It is also uncontroversial that the onus
of proof in relation to (3) lies on the defendant,
at least in relation to
mitigation of loss.[132]
This appeal is ultimately concerned with the requirements for proof of the
measure of consequential loss and the availability of
a method based upon
recovery of wasted expenditure in (2).
The position in the United
States
- Considerable
submissions were made on this appeal about the legal position in the United
States, particularly due to the importance
of the 1949 decision in
L Albert & Son v Armstrong Rubber
Co,[133] which was a
significant feature in the reasoning of the majority Justices in The
Commonwealth v Amann Aviation Pty
Ltd,[134] discussed
below. At the time that the decision in L Albert & Son v Armstrong Rubber
Co was delivered, the position in the United States as set out in the
Restatement (First) of
Contracts[135] was
broadly similar to the summary
above.[136] The rules of
damages in the Restatement (First) of Contracts were generally concerned
with the principle of putting "the injured party in as good a position as that
in which [they] would have
been put by full performance of the
contract".[137] And
although recovery of wasted expenditure was confined to expenditure "in
performance of the contract or in necessary preparation
therefor" and was capped
by the amount of the contract
price,[138] the recovery of
wasted expenditure was recognised as part of an award of damages with the
onus upon the defendant to prove that performance of the contract would not have
led to recoupment of some or all of that
expenditure for the following
reason:[139]
"Frequently it is very difficult, and at times it is impossible, to prove the
cost of completion and the amount of profit that would
have resulted from full
performance. It is in these cases that the rule of the present Section is
essential to the plaintiff's case.
Since in the usual case [the plaintiff] is
entitled to expenditure plus profits, [the plaintiff's] inability to prove
profits should
not deprive [the plaintiff] of [the plaintiff's] right to the
proved expenditure, so far as this expenditure was provident and reasonable
and
is not already compensated for in usable materials on hand."
- The
position in the United States has substantially changed and is now very
different from Australian and English law. The Restatement (Second) of
Contracts[140]
recognises different "interests of a promisee", including an "expectation
interest" and a "reliance
interest".[141]
Corresponding with those interests are two different "types" of damages for
consequential loss following a breach of contract. The
first is "damages based
on ... expectation interest", which give the injured party "a sum of money that
will, to the extent possible",
put that party in the same position as they would
have been in "had the contract been
performed".[142] The
second, which is an "alternative to the measure of damages" based on the
expectation interest, is damages based on the "reliance
interest", including
"expenditures made in preparation for performance or in performance, less any
loss that the party in breach
can prove with reasonable certainty the injured
party would have suffered had the contract been
performed".[143]
- The
justification in the Restatement (Second) of Contracts for the existence
of the alternative "reliance" measure of damages for a breach of contract is the
"reliance interest" that the promisee
is said to have in the contract. The
language and justification of a "reliance interest" was taken directly by the
Restatement (Second) of Contracts from a highly influential two-part
article by Fuller and
Perdue.[144] In the first
part of their article, Fuller and Perdue said that "the 'normal' rule of
contract damages" seemed to be "a queer kind
of 'compensation'". They thought
that one of the "principal purposes" of the award of contract damages was to put
the plaintiff "in
as good a position as [they were] in before the promise was
made".[145]
- In
seeking to put the promisee in the position they were in before the contract had
been made, Fuller and Perdue argued that "the
promisee who has actually relied
on the promise ... certainly presents a more pressing case for relief than the
promisee who merely
demands satisfaction for [their] disappointment in not
getting what was
promised".[146] The usual
damages based on the "expectation interest" were, on Fuller and Perdue's
approach, a proxy for a plaintiff's reliance
loss.[147] Indeed, they
recognised that, in principle, their approach might have the effect that a
plaintiff could recover more than the loss
that the plaintiff would have
incurred if the defendant had performed the
contract.[148]
- The
justification in the Restatement (Second) of Contracts for the recovery
of wasted expenditure as consequential loss for a breach of contract thus now
rests upon a rationale that has been
rejected in this
country.[149] Rather than
compensating the plaintiff with a sum of money that places the plaintiff in the
same position as if the contract had
been performed, the rationale is to place
the plaintiff in the same position as if the contract had never existed, even
though the
breach of contract did not cause the plaintiff to enter the contract
or incur the expenditure. By contrast, the Australian approach
of placing the
plaintiff in the same position as if the contract had been performed treats the
essence of contract law as
performance.[150]
Onuses
and methods of proof of consequential loss
The legal onus and a principle of facilitation of proof
- The
legal onus to prove loss arising from a breach of contract falls upon the
plaintiff.[151] Whilst this
legal onus is not frequently stated, the reason for the infrequency may simply
be that "the rule is beyond
doubt".[152] But although
the plaintiff bears that legal onus, in some circumstances the common law
facilitates its discharge. For instance, as
explained above, a defendant has the
burden of establishing that a plaintiff's loss was unreasonable in the sense
required by the
rules concerning mitigation of loss. So too, in a principle
deriving from the law of torts, a plaintiff is assisted in proof by reasonable
inferences where a defendant's breach has resulted in difficulties or
impossibilities of proof of loss or damage. This principle
of assistance in
proof, or "facilitation principle", lies at the heart of this appeal.
- The
precise description of this principle of facilitation of proof by a plaintiff
has varied in the cases, although the substance
of the principle is generally
the same. In some Australian judgments the principle has been described as
giving rise to a defendant's
"evidentiary
onus"[153] (although that
expression can be used to mean different
things[154]). In some
Australian judgments the principle has been described as giving rise to a "prima
facie inference"[155] or
prima facie case for the
plaintiff.[156] In other
Australian judgments, including the decisions of the primary judge and the Court
of Appeal in this case, the principle has
been referred to as a
"presumption".[157] The
reference to "presumption", which is used in a variety of different senses in
law,[158] is best avoided
in this context because it has been associated with a different rationale for
the facilitation of proof by an assumption
of fact, namely that in the ordinary
course of commercial dealings a party will expect at least to recoup their
expenses.[159] As explained
below, that proposed rationale for the principle should not be accepted.
- Whatever
the description of the principle, its essence is that it facilitates the
discharge of the plaintiff's legal onus of proof
of loss in circumstances where
the defendant's wrongdoing has resulted in uncertainty regarding the quantum of
loss. This facilitation
principle operates where uncertainty arises from the
defendant's breach and is capable of coexisting with other principles concerning
facilitation of proof that might assist either the plaintiff or the defendant,
such as the principle in Blatch v
Archer[160] that
"all evidence is to be weighed according to the proof which it was in the power
of one side to have produced, and in the power
of the other to have
contradicted".
(1) The law of torts
- The
facilitation principle was most famously stated in the context of a tort in
Armory v
Delamirie.[161] In that
case, the defendant wrongfully deprived the plaintiff of the plaintiff's
possessory title to a jewel which had been set in
a socket in a ring. Since the
defendant refused to produce the jewel, it was impossible for the plaintiff to
prove the value of the
jewel. Evidence was given of the value of the best jewels
that would fit in the socket. Pratt CJ directed the jury that in the
absence
of production of the jewel the jury should "presume the strongest"
against the defendant and award the plaintiff the market value
of the best
jewels.
- Two
centuries later, the facilitation principle for assessment of damages in the law
of torts was explained by the Supreme Court
of the United States in Story
Parchment Co v Paterson Parchment Paper
Co[162] as applying
"[w]here the tort itself is of such a nature as to preclude the ascertainment of
the amount of damages with certainty[;]
it would be a perversion of fundamental
principles of justice to deny all relief to the injured person, and thereby
relieve the wrongdoer
from making any amend for [their] acts". As so explained,
the facilitation principle is not confined to circumstances where it is
impossible to assess damages, or to intentional acts of a
defendant,[163] but has
been applied in particular categories of case where the wrongdoing of the
defendant has resulted in uncertainty that has
made the assessment more
difficult. In those particular categories of case, the risk of uncertainty that
results from the acts of
the wrongdoer should be thrown on the wrongdoer rather
than the injured party.
- In
other contexts, in this Court the facilitation principle has been described as
one which permits inferences to be drawn in favour
of a plaintiff where the
wrongdoing of the other party "made quantification
difficult".[164] Naturally,
however, the greater the difficulty in proof that results from the defendant's
wrongdoing, the stronger the inference
the court will be prepared to draw
against the wrongdoer.
(2) Breach of contract
- In
Wilson v Northampton and Banbury Junction Railway
Co,[165] the Lord
Chancellor (with whom James and Mellish LJJ agreed) explained that the same
principle that permits inferences to be drawn
against a tortfeasor applies also
to permit inferences to be drawn against a party whose breach of contract has
resulted in uncertainty
for the purpose of assessing damages. The Lord
Chancellor said that "the principle is to be reasonably applied according to the
circumstances
of each
case".[166]
- One
circumstance in which the principle has been applied is where a plaintiff has
expended money in anticipation of, or reliance on,
the performance of a
contractual obligation and the defendant's breach of that obligation has made it
difficult or impossible for
the plaintiff to prove that any reasonably incurred
expenditure would be recouped. An early recognition of the principle was the
decision of Chief Judge Learned Hand in the Second Circuit of the United States
Court of Appeals in L Albert & Son v Armstrong Rubber
Co.[167] That case was
decided prior to the general recognition by United States courts of an
independent "reliance interest" in a contract
itself.
- One
issue in L Albert & Son v Armstrong Rubber Co was the assessment
of damages for a breach of contract by a seller of four machines who delivered
two of the machines at a time so
late as to justify the buyer's refusal to
accept all four machines. The buyer did not claim for any alleged loss of
profits from
the use of the machines but instead successfully claimed damages
based on alleged wasted expenditure of $3,000 that was spent building
a
foundation for the machines.
- In
upholding that part of the buyer's argument, Chief Judge Learned
Hand commenced his analysis by recognising the usual rule for
damages for
breach of contract: "Normally a promisee's damages for breach of contract are
the value of the promised performance,
less [their] outlay, which includes ...
any expenses necessary to prepare for the
performance".[168] The
principle in Story Parchment Co v Paterson Parchment Paper Co was then
applied: "[i]t is often very hard to learn what the value of the performance
would have been; and it is a common expedient,
and a just one, in such
situations to put the peril of the answer upon that party who by [their] wrong
has made the issue relevant
to the rights of the
other".[169] Nevertheless,
it was said that the promisee's prima facie right to recover their "outlay in
preparation for the performance" is subject
to "the privilege of the promisor to
reduce [recovery] by as much as [they] can show that the promisee would have
lost, if the contract
had been
performed".[170]
- The
same issue arose before this Court in an appeal heard a little over a year after
the decision in L Albert & Son v Armstrong Rubber Co. In this
Court, in McRae v Commonwealth Disposals
Commission,[171] the
same approach was broadly taken in relation to damages for breach of contract in
the context of a contract for the sale of an
oil tanker. In that case, the
Commonwealth Disposals Commission, contracting on behalf of the
Commonwealth—which was ultimately
the party held
liable[172]—had
promised the plaintiffs that there would be a tanker located at a specific place
known as Jourmaund Reef. The plaintiffs
paid £285 to secure the contract
and spent approximately £3,000 searching for the oil tanker. There was no
tanker at that
place. The Commission was in breach of its contractual promise
that the oil tanker existed. The difficulty in assessing damages for
that breach
of contract was that it was "quite impossible to place any value on what the
Commission purported to
sell".[173] Dixon and
Fullagar JJ (with whose conclusion McTiernan J concurred) said that
following proof of the wasted expense due to the breach
of contract the
plaintiffs had a "prima-facie case". They said that "[t]he burden is now thrown
on the Commission of establishing
that, if there had been a tanker, the expense
incurred would equally have been
wasted":[174]
"It is the breach of contract itself which makes it impossible even to undertake
an assessment on that basis [of valuing a non-existent
tanker]. It is not
impossible, however, to undertake an assessment on another basis, and, in so far
as the Commission's breach of
contract itself reduces the possibility of an
accurate assessment, it is not for the Commission to complain."
- The
reference by Dixon and Fullagar JJ to a "prima-facie case" describes the
facilitation of the discharge of the plaintiff's legal
onus of proof rather than
a positive shift of a legal onus of proof to the
defendant.[175]
Dixon CJ, Webb, Fullagar and Taylor JJ later said of a plaintiff's
"prima facie case" in the context of the doctrine of res ipsa loquitur
that the prima facie case would succeed "unless [alternative] facts are proved
... In this sense, and in this sense alone, the defendant
may, perhaps, be said,
to carry an onus".[176] As
Gleeson CJ and McHugh J said of the same doctrine, "the principle is
not a distinct, substantive rule of law, but an application
of an inferential
reasoning process [in which] the plaintiff bears the onus of proof ... even when
the principle is
applicable".[177]
- In
summary, the facilitation of the plaintiff's proof arises in cases where the
defendant's breach of an obligation results in uncertainty
and difficulty of
proof of loss for the plaintiff, who has incurred expenditure in anticipation
of, or reliance on, the performance
of the obligation that was breached. The
facilitation of proof that reasonably incurred expenditure would have been
recovered has
been described by Leggatt J as an example of courts doing the
"best they can not to allow difficulty of estimation to deprive the
claimant of
a remedy, particularly where that difficulty is itself the result of the
defendant's
wrongdoing".[178] In
applying the principle "reasonably ... according to the circumstances of each
case",[179] the plaintiff
is given an evidential "benefit of any relevant doubt" that expenditure would be
recouped to the extent that it was
reasonable, with the practical effect of
giving the plaintiff "a fair wind" to establish
loss.[180] The strength of
the wind will depend upon the extent of the uncertainty resulting from the
breach by the
defendant.[181] And all of
the circumstances, including any evidence led by the defendant, must be
considered. The plaintiff is given a "fair wind"
but not a "free
ride".[182]
- The
nature of the decision in McRae v Commonwealth Disposals Commission as
one that is concerned with issues of proof, rather than the recognition of a
separate head of damages, is confirmed by the decision
of this Court in TC
Industrial Plant Pty Ltd v Robert's Queensland Pty
Ltd.[183] In that case,
a stone crushing machine was purchased for use in the performance of a contract
that the buyer had entered with the
Commonwealth. The buyer was awarded damages
when the machine was unfit for the purpose for which it was supplied and the
contract
with the Commonwealth could not be completed. The damages award
included: (i) a sum of £15,889 for wasted expenditure incurred
in
performing work under the contract with the Commonwealth less amounts paid to
the buyer by the Commonwealth under that contract,
and (ii) £12,000
for additional loss of profits on that and another contract. The seller argued
that the buyer could not accumulate
both amounts. This Court rejected that
argument but emphasised that no question of election arose because both amounts
were aspects
of a single measure of damages: the wasted expenditure claimed was
not separate from the claim for lost profits. A plaintiff, "having
expended
£X which he would have got back together with £Y profit" had the
contract been performed, can recover "£X
+ Y; and it makes no difference if
you prefer to say that he can recover £X under the name of cost plus
£Y under the name
of [additional]
profit".[184]
The facilitation principle in Amann Aviation
- The
leading decision on the application of these principles is the decision of this
Court in The Commonwealth v Amann Aviation Pty
Ltd.[185] It is not
easy to identify a ratio decidendi at any level of specificity from the six
different sets of reasons in that case. Nevertheless,
as explained below, the
decision broadly conformed with the principles discussed above.
- Amann
Aviation entered a contract with the Commonwealth to conduct aerial coastal
surveillance of Australia's northern coastline.
The contract term was three
years. There was a strong prospect that the Commonwealth would renew the
contract at the expiry of the
three years because, by that time, Amann Aviation
"would be fully equipped with the cost of its aircraft written down. It would be
very difficult for a competitor to match this
advantage."[186] At trial
in the Federal Court, and on appeal to the Full Court of the Federal Court, it
was held that the Commonwealth repudiated
the contract six months after entry.
One basis upon which Amann Aviation put its claim was to recover its wasted
expenditure. In
anticipation of, or reliance on, the performance of the
Commonwealth's contractual obligations, Amann Aviation had spent considerable
sums in reasonable pre-operational expenditure, in acquiring and fitting out
aircraft (which had a resale value of far less than
the amount spent), in
termination payments and on a security deposit.
- The
primary judge held that Amann Aviation would have made a profit on the contract,
without renewal, of $820,000 but that, since
there was a 50 per cent chance that
the Commonwealth would lawfully have terminated the contract, the damages were
limited to $410,000.
The Full Court of the Federal Court, however, held that
Amann Aviation was entitled to have its damages assessed on the basis of
its
wasted expenditure, which the Commonwealth failed to prove was expenditure that
would not have been recouped. A majority of the
Full Court refused to discount
the damages for what it assessed to be a 20 per cent chance that the contract
would have been lawfully
terminated before conclusion. The total awarded, before
interest, was $5,475,184.
- In
this Court, the appeal by the Commonwealth was dismissed by a majority of
Mason CJ and Dawson J, Brennan J, and Gaudron J. In
dissent,
each of Deane J, Toohey J, and McHugh J would have awarded a
lesser amount to Amann Aviation. Deane J and Toohey J would
have
allowed (different) discounts from the award to reflect the possibility that the
Commonwealth might lawfully have terminated
the contract. McHugh J would
have made an award based on expected profit rather than wasted expenditure.
- In
the majority, although the detail of reasoning was not common to all judges,
there were certain strands of commonality. Each member
of the majority accepted
that the general rule at common law was that damages for breach of contract aim
to put the innocent party
in the same position as if the contract had been
performed.[187] Each member
of the majority rejected the notion that "reliance damages" were an alternative
to the general rule, or a measure which
the plaintiff could elect to
claim.[188] Hence, as
Mason CJ and Dawson J observed, the decisions in the United States
concerning "reliance damages" needed to be treated with
"some
reserve".[189]
- Each
member of the majority relied upon the uncertainty resulting from the acts of a
wrongdoer as a reason in favour of the facilitation
of the discharge of the
plaintiff's legal onus of proving
loss.[190] That
facilitation took the form of treating the loss as equivalent to the amount of
wasted expenditure incurred in anticipation of,
or reliance on, the performance
of the obligation that was
breached.[191] Consistently
with the principles described above, their Honours described this facilitation
of proof of recovery of expenditure reasonably
incurred as a "just
result"[192] or "just and
fair"[193] or
proper.[194]
- Each
member of the majority justified their approach by reference to the reasoning in
L Albert & Son v Armstrong Rubber
Co,[195] with
Mason CJ and Dawson J, and Brennan J, quoting from Chief Judge
Learned Hand to the effect that in situations of uncertainty
resulting from
wrongful acts "it is a common expedient, and a just one ... to put the peril of
the answer upon that party who by
[their] wrong has made the issue relevant to
the rights of the
other".[196] And each
member of the majority refused to discount the damages award to account for the
possibility of a lawful termination because
that possibility was "unlikely to
occur"[197] or because even
the 20 per cent possibility of termination did not preclude a conclusion that
Amann Aviation could have recouped
its
expenditure.[198]
- Beyond
these matters, there were differences in the reasoning of the majority judges.
For instance, there was some terminological
dispute about the proper description
of the legal rule that facilitates proof of the plaintiff's loss. Mason CJ
and Dawson J considered
the rule to be one that placed the onus of proof on
the defendant.[199]
Brennan J also spoke of the "reversal of the
onus"[200] although his
Honour referred also to the plaintiff establishing a "prima facie
case".[201] Although the
difference on this point is primarily terminological, if the language of "onus"
is to be used then the better description
is that of Gaudron J, who treated
the legal onus of proving loss as borne throughout by the plaintiff, but
described the facilitation
principle as one which is concerned with a "practical
or evidentiary
onus".[202]
- Another
difference is that Mason CJ and Dawson J and Gaudron J, but not
Brennan J, relied upon an additional reason for facilitating
the
plaintiff's legal onus of proving loss by treating the loss as equivalent to the
amount of wasted expenditure. The additional
reason was that "[i]n the ordinary
course of commercial dealings" a party will expect at least to recoup
expenditure.[203]
Mason CJ and Dawson J described this as a "presumption that a party
would not enter into a contract in which its costs were not
recoverable".[204] That
reasoning is unnecessary to support the facilitation principle and it cannot be
accepted.
- It
is not uncommon in the ordinary course of commercial dealings that a party might
make what, in hindsight, turns out to be a bad
bargain, so that the party does
not recoup the expenditure made in anticipation of, or reliance on, the
performance by the other
party of their contractual obligations. The general,
and sometimes unrealistic, expectation of parties to commercial contracts that
their expenditure will be recouped is not a basis to facilitate the discharge of
that party's legal onus of proving that the expectation
was well founded at the
time of breach of contract. Of course, as Brennan J observed, the facts of
a particular case might be sufficient
for an inference that the contractual
performance of the defendant would lead the plaintiff to recoup their
expenditure.[205] But these
facts, and this inference, are for the plaintiff to establish; there is no
presumption of fact.
- In
Berry v CCL Secure Pty
Ltd,[206] Bell, Keane
and Nettle JJ synthesised the commonalities in the reasoning of the
judgments of the majority in Amann Aviation in similar terms. Their
Honours described the legal burden of proving loss as resting with the plaintiff
but recognised that an "inference"
(leading to an "evidentiary burden") could
arise from the wrongdoer's conduct, consistently with the "principle
encapsulated in Armory v
Delamirie[207]". Their
Honours recognised that the principle was applied in Amann Aviation due
to the uncertainties in Amann Aviation's proof of its loss resulting from the
repudiation of the contract by the Commonwealth.
They endorsed Brennan J's
reasoning that it was "just" that the shift in evidentiary burden meant that the
"Commonwealth should bear
the ultimate onus of proving at least a prospect that
Amann's returns under the contract would not have been sufficient to recoup
that
expenditure". The greater the likelihood of non-recoupment proved by the
Commonwealth, the greater would be the reduction in
the plaintiff's
damages.
An equivalent principle in English law
- An
equivalent to the facilitation principle has been recognised in English law,
where the principle is described as a "fair wind"
for
plaintiffs.[208] For
instance, in what was later described as a "masterly
judgment",[209] in Omak
Maritime Ltd v Mamola Challenger Shipping
Co[210] Teare J
explained: damages based upon wasted expenditure were an illustration of "the
fundamental principle in Robinson v Harman" so that there was only one
principle "governing the law of damages for breach of
contract";[211] the
language of "election" is not appropriate in that it is not a choice between
inconsistent remedies;[212]
and "the practical impossibility of proving loss of
profit"[213] due to the
defendant's breach should require the defendant to bear an onus to establish
that wasted expenditure would not have been
recovered.[214] And in
Yam Seng Pte Ltd v International Trade Corporation
Ltd,[215]
Leggatt J reiterated these points and added, in an eloquent summary of what
we have described as the facilitation principle, that
in instances of wasted
expenditure by a
plaintiff:[216]
"[T]he attempt to estimate what benefit the claimant has lost as a result of the
defendant's breach of contract or other wrong can
sometimes involve considerable
uncertainty ... The court is aided in this task by what may be called the
principle of reasonable
assumptions – namely, that it is fair to resolve
uncertainties about what would have happened but for the defendant's wrongdoing
by making reasonable assumptions which err if anything on the side of generosity
to the claimant where it is the defendant's wrongdoing
which has created those
uncertainties."
- These
principles from these two decisions were referred to with approval by the Court
of Appeal of England and Wales in Soteria Insurance Ltd v IBM United Kingdom
Ltd.[217] That
case concerned the interpretation of an exclusion clause and consideration of
whether a claim for loss based on wasted expenditure
was a claim for
"consequential losses" (and thus irrecoverable under the exclusion clause),
which was defined as a separate exclusion
from "loss of profit", or whether the
claim was for "direct loss" (and thus recoverable), which was defined to include
"the reasonable,
incremental costs of procuring substantially similar
replacement or alternative[] services or
systems".[218] One issue
was whether financing costs and payments to third party suppliers fell
within recoverable "direct loss[es]" rather than irrecoverable "consequential
losses" within the meaning of the exclusion clause.
- However,
in the course of reasoning concerning this question of interpretation of the
exclusion clause, Coulson LJ, with whom Phillips
LJ and
Zacaroli J agreed, also said: "[c]laims for wasted expenditure are an
entirely different animal" from claims for loss of profit;
claims for wasted
expenditure were "different types of
loss";[219] and the
plaintiff has a "choice" and can elect between claims for wasted expenditure and
loss of profits.[220] In
light of the approval by Coulson LJ of the reasoning described above from
Omak Maritime Ltd and Yam Seng Pte Ltd, we do not understand
Coulson LJ to have endorsed the adoption of a principle akin to that which
operates in the United States, where
recovery of reliance expenditure is a
separate type of loss that does not aim to place the plaintiff in the same
position as if the
contract had been performed. Otherwise, we note that in
Soteria Insurance Ltd v IBM United Kingdom Ltd Coulson LJ
characterised the wasted expenditure as "easily-ascertainable" rather than
"speculative and uncertain", and therefore
found that it fell within the
contractual description of a "direct loss" rather than a "consequential
loss[]".[221] A petition
for leave to appeal to the Supreme Court was refused on the basis that the
application did not raise an arguable point
of law of general public importance.
The Council's challenges to the facilitation principle and its
scope
- The
Council challenged the existence and scope of the facilitation principle in four
ways. The Council submitted: (i) the facilitation
principle is inconsistent
with the legal rules concerning loss of a chance; (ii) any recognition of
the facilitation principle should
not apply to speculative contracts;
(iii) any recognition of the facilitation principle should apply only to
"essential" reliance;
and (iv) any recognition of the facilitation principle
should require the contract breaker only to establish a prospect of
non-recoupment
of wasted expenditure. None of these submissions should be
accepted.
(i) The facilitation principle is consistent with legal
rules concerning loss of a chance
- The
Council disputed any application of the facilitation principle to speculative
contracts, submitting that the principle was inconsistent
with the legal rules
concerning damages for loss of a chance. The Council submitted that a claim for
damages based upon loss of a
chance requires a plaintiff to prove that there was
"a substantial prospect of a beneficial
outcome"[222] and that this
condition would be undermined if a plaintiff could rely upon the facilitation
principle to, in the Council's words,
"throw the burden of uncertainty that is
inherent in speculative contracts onto defendants".
- The
Council's submission conflates two different types of loss. In cases where the
plaintiff's claim is for wasted expenditure, the
plaintiff's loss is an outcome
that did not occur: recovery of the expenditure under the contract. In cases
where the plaintiff's
claim is for loss of a chance, the plaintiff's loss is a
valuable opportunity of which it was deprived, not the
outcome.[223] If the
defendant's breach of contract results in uncertainty for the plaintiff's proof
of either type of loss then the facilitation
principle can operate in each
case.[224] In relation to a
claim for a lost chance, it has been said that the uncertainty resulting from
the defendant's breach permits the
plaintiff to prove the existence of the
valuable opportunity merely by showing "a real (more than negligible)
possibility" of that
opportunity.[225] The
quantification of that valuable opportunity will depend on informed
estimation.
(ii) The facilitation principle can apply to
speculative contracts
- In
Amann Aviation, Mason CJ and Dawson J said that one
circumstance in which it would not be appropriate to apply the facilitation
principle in favour
of the plaintiff was in the case of a pure aleatory contract
"for the reason that inherent in the entry into such a contract is the
contingency that not even the slightest expenditure will be recovered, let alone
the securing of any net
profit".[226] The Council
sought to expand this circumstance so that the facilitation principle would not
apply to any contract for a speculative
venture. The Council defined the
relevant class of speculative contracts as those where speculation as to the
future is inherent
in the bargain.
- If
the Council's submission were correct then there would be little, if any, scope
for the facilitation principle, since the very
circumstances in which it usually
operates are those in which the defendant breaches a contract the consequences
of which involved
speculation as to the future, thus making it difficult or
impossible for the plaintiff to prove their loss. Amann Aviation itself
involved a speculative contract in the sense that Amann Aviation could only have
speculated about the possibility of renewal
of its contract after three years in
circumstances where, if the contract had not been renewed, Amann Aviation would
not have recouped
its pre-operational expenditure spent acquiring and fitting
out aircraft.[227]
- As
already noted, it is unsound to make the operation of the facilitation principle
depend on the subjective intentions of the parties
as to whether the expenditure
would be recouped under the contract. Similarly, whilst there might be doubt
about the scope of a category
of "purely aleatory"
contracts,[228] it is
unsound to attempt to identify such categories of contracts as ones to which the
principle does not apply. Many contracts involve
risk and are in some sense
speculative. It does not assist to attempt to characterise those contracts as
"purely aleatory" or not.
The critical issue is the extent to which the breach
causes or increases uncertainty in the innocent party's proof of loss. For
example,
where the defendant's contractual breach is a failure to obtain
insurance against a known event then, in the ordinary course, that
breach will
not have caused or increased any uncertainty for the plaintiff in proving loss.
If the event occurred, and thus the risk
to be insured against materialised,
then the plaintiff can recover as though the insurance had been obtained. If the
event did not
occur and the risk did not materialise then the plaintiff has not
suffered any consequential loss. On those scenarios no question
arises of the
innocent party recovering wasted expenditure, such as the premium; the breach
did not cause or increase the uncertainty
of proof and the facilitation
principle has no role to play.
(iii) The facilitation principle
is not confined to "essential" reliance
- The
Council sought to rely upon a distinction drawn by Fuller and Perdue between two
different types of reliance interest that could
be protected. The Council argued
that if the respondent were to be facilitated in any aspect of its onus of proof
this should only
be in relation to "essential reliance", being partial contract
performance or necessary preparations for performance. By contrast,
the Council
argued, "incidental reliance", being any other reliance which follows naturally
and foreseeably from the
contract,[229] should not
be the subject of any facilitation of the plaintiff's onus.
- The
concepts of essential reliance and incidental reliance were developed by Fuller
and Perdue in the course of their proposed development
of the law in the United
States. As explained above, their approach is very different from that adopted
in Australian and English
law. Moreover, a distinction between essential
reliance and incidental reliance is difficult and elusive. Even Fuller and
Perdue's
suggested rule concerning reliance damages included both types of
reliance, with the authors acknowledging that the cases they referred
to had not
limited relief to essential
reliance.[230] Similarly,
the Restatement (Second) of
Contracts[231] permits
recovery of wasted expenditure based on "'incidental' reliance", giving the
example of a purchaser of a retail store who,
after incurring expenditure on
inventory, suffers a loss on the resale of that inventory following the seller's
repudiation of the
contract for sale of the store.
- The
Council correctly observed that, in L Albert & Son v Armstrong
Rubber Co,[232] the
$3,000 of expenditure that had been wasted on building a foundation for the
machines was described as a case of what Fuller and
Perdue had described as
"essential reliance". But Chief Judge Learned Hand did not decide that case on
the basis of a "reliance interest"
and did not suggest that the result would be
different if the $3,000 had been "incidental reliance".
- The
decision in L Albert & Son v Armstrong Rubber Co also
illustrates why, as a matter of principle, it is difficult to justify the
different treatment of wasted expenditure that is
reasonably incurred as a
necessary preparation for performance of an extant contract and wasted
expenditure to the extent that it
is incurred reasonably in anticipation of a
contract. There is no justification in principle for treating the wasted
expenditure
differently depending upon whether, as the Council submitted on this
appeal, the $3,000 had been reasonably spent on foundations
for the machines in
order to accept delivery or whether the $3,000 had been reasonably spent on
foundations for the machines to operate
efficiently. In both cases, it should be
sufficient that the expenditure was wasted as a result of the defendant's breach
of contract
and the defendant did not overcome the uncertainty resulting from
its breach of contract to reduce the award of damages by establishing
that some
or all of the expenditure would not have been recovered.
(iv) The
facilitation principle can apply despite evidence of a prospect of
non-recoupment
- The
Council submitted that any facilitation of the plaintiff's onus of proof could
put no more than an evidentiary onus upon a defendant
to show that there was a
"prospect" that the plaintiff would not recoup its wasted expenditure. Once that
prospect of non-recoupment
was established, it was submitted, the plaintiff
could not recover anything without proof that the loss would positively have
occurred.
It is hard to see how such an approach could be consistent with
principle or with the outcome of Amann Aviation, which was not challenged
on this appeal.
- If
the force of the facilitation principle could be spent by a slight evidentiary
onus being cast upon defendants to show nothing
more than a prospect of
non-recoupment, then plaintiffs will generally bear the difficult or impossible
task of overcoming the uncertainty
caused by the defendant's wrongdoing. That is
not consistent with the foundations of the facilitation principle. Indeed, in
Amann Aviation, the majority held that even a 20 per cent chance that
Amann Aviation's contract would have been lawfully terminated before its expiry
after three years was not sufficient to reduce the award of damages based
on wasted expenditure, although their Honours did refer also to the significant
likelihood of renewal
of the contract and the reasoning of Brennan J
expressly relied upon the significant prospect that the contract would have been
renewed
after the three
years.[233] The prospect of
termination of the contract was not, in all the circumstances, sufficient to
establish a prospect that the expenditure
would not be recovered.
-
The Council submitted that support for the slight evidentiary onus could be
found in the reasons of Bell, Keane and Nettle JJ in
Berry v CCL Secure
Pty Ltd,[234] where
their Honours said that the evidentiary onus upon the Commonwealth was to prove
"at least a prospect that Amann's returns under
the contract would not have been
sufficient to recoup that expenditure". But, in that statement, their Honours
were not saying anything
more than that the minimum necessary to reduce a
plaintiff's damages based on wasted expenditure is to show ("at least") a
prospect
that the returns under the contract would not have been sufficient to
recoup "any part of the expenditure [the plaintiff] had
incurred".[235] In other
words, if the Commonwealth in Amann Aviation had proved that there was a
ten per cent prospect that the returns would not have been sufficient to recoup
the wasted expenditure,
then damages based on wasted expenditure should have
been reduced by ten per cent.
- In
summary, the facilitation principle arises in cases where the defendant's breach
of an obligation results in uncertainty and difficulty
of proof of loss for the
plaintiff, who has incurred expenditure in anticipation of, or reliance on, the
performance of the obligation
that was breached. The facilitation of the
plaintiff's proof by an assumption that the plaintiff has suffered loss in the
amount
of reasonable expenditure is neither a blunt rule nor able to be bluntly
dismissed in every case by a slight evidentiary onus. The
strength with which
the principle applies will depend upon the extent of uncertainty resulting from
the defendant's breach. And the
extent to which evidence from a defendant can
reduce or eliminate the loss represented by a plaintiff's wasted expenditure
will depend
upon the extent to which that evidence establishes a likelihood of
non-recoupment.
The respondent's wasted expenditure established
its loss
The reasonable expenditure on the hangar was wasted in anticipation of, or
reliance on, performance of the obligation breached
- The
Council did not challenge the conclusion of the Court of Appeal that, in
expending money to construct the hangar, the respondent
relied upon the Council
performing cl 4.2(a)(2) of the agreement for lease by taking all reasonable
action to apply for and obtain
registration of the plan of subdivision by the
Sunset Date of 30 September 2011. That registration would have
resulted in a lease
to the respondent of proposed Lot 104. Mr Johnston
had consistently referred to his desire for "bankable tenure", by which he meant
a lengthy leasehold interest against which he could borrow, or which he could
sell.[236]
- Further,
although the Council referred in oral submissions to the dramatic increase in
the cost of construction of the hangar beyond
the initial estimate, there was no
ground of appeal in this Court that asserted that the quantum of damages should
be reduced because
(i) the cost of approximately $3.7 million for the
"iconic" hangar was unreasonable or improvident or (ii) the wasted
expenditure
should be confined to the initial estimate of the cost of a hangar
of $560,000, identified in Mr Johnston's April 2005 development
application. The absence of any such ground was likely informed by the fact that
the agreement for lease, executed by the Council
on 26 July 2007,
required the consent of the Council for works performed by the respondent and
made specific reference to the erection
of a hangar, the cost of which was known
by the parties at that time to be much more than the initial estimate.
- Prior
to the Council's grant of development consent for the hangar on
28 July 2006, Mr Johnston had told the relevant Council officer
that he would be spending "between 2 to 3 million on a Peter Stutchbury
building" and that he needed a "decent tenure" for that reason.
As
Brereton JA concluded, there is no doubt that both the Council and the
respondent "had in contemplation the expensive and iconic
hangar which was
ultimately
constructed".[237] Indeed,
prior to the execution of the agreement for lease, the solicitor for the
respondent had written to the solicitors for the
Council saying:
"It is noted that the Plans for the Hangar have been prepared by an
award-winning architect, the design is of a very high standard
and the iconic
hangar once completed will be [a] very worthwhile visual and working hangar
situated on this very important part of
Cessnock Airport.
It can be appreciated that our client could have submitted a Development
Application for a more modest building which would cost
approximately one half
of the cost to build the hangar as approved and which would make the proposed
business to be run from the
building more economically viable. However our
client decided that the hangar as designed and consented to by Council is a much
more
appealing building for the future of the airport and a worthwhile addition
to the tourist landscape for the airport and the adjoining
Pokolbin area."
- The
consequence of the Council's repudiation was that the respondent never obtained
the leasehold tenure that it had required to
exploit its investment of nearly
$3.7 million in the construction of the hangar. The conclusion of the Court
of Appeal, unchallenged
in this Court, was that it was reasonable for the
respondent to reject the Council's inferior offer of a 25-year licence or five
consecutive leases of five years, an offer made in circumstances where "any
prospect of a more conducive commercial environment was
precluded".[238]
- The
respondent's expenditure was wasted and there was no prospect of recoupment, at
the very latest, when the Council acquired the
hangar for $1. The respondent's
expenditure had been incurred in anticipation of, or reliance on, the
performance by the Council
of its obligation to take all reasonable action to
apply for and obtain registration of the plan of subdivision by
30 September 2011,
so that the respondent could obtain a lease of
proposed Lot 104.
The uncertainties for proof of loss
resulting from the Council's breach
- On
appeal to the Court of Appeal, and also to this Court, there was rightly no
challenge to the primary judge's finding that the
consequences of the breach by
the Council were that the plan of subdivision, and therefore the lots in the
subdivision (including
proposed Lot 104), was not registered, and therefore
that the respondent did not become entitled to a 30-year lease of proposed
Lot
104. The Council's breach, and these consequences of it, resulted in
three significant areas of uncertainty for the respondent in
seeking to prove
that it would have recouped its wasted expenditure.
- First,
although there is a ready inference that can be drawn that the Council would
have engaged in substantial development if funds
were available, there is
uncertainty about whether funding for development of the airport might have been
obtained in the event that
the Council complied with its contractual obligation
and had the subdivision registered. Possibilities for funding were from the
Council's own funds, or from grants, loans or equity funding.
- As
to funding from the Council's own funds or use of the Council's funds for a
loan, the primary judge found that it was possible
for the Council to have paid
$1.3 million to fulfil condition 23 and connect the proposed lots to
Hunter Water Corporation's reticulated
sewerage system, but her Honour also
found that the Council was in a difficult financial
position.[239]
Nevertheless, the Council may have been amenable to using some of its funds to
develop the airport, or to service loans for development,
if it had already
expended $1.3 million to connect the sewerage system and registered the
plan of subdivision. The Council's financial
position in 2010 included
approximately $79 million expenditure on public works, an operational
position (excluding capital income)
of $3,292,000 and unrestricted cash and
investments of $1,634,000.
- It
was also uncertain whether equity investment could have been attracted or if any
grant applications would have had more success
if the Council had made an
initial $1.3 million commitment to the development by connecting the
proposed lots to Hunter Water Corporation's
reticulated sewerage system.
- The
uncertainty regarding which funding possibilities would eventuate, if any, was a
result of the Council's breach of contract in
failing to commit the
$1.3 million in funds to connect the proposed lots to the sewerage system.
None of these possibilities for
funding development of the airport could be said
to be remote or fanciful. The connection of proposed lots to the sewerage system
and registration of the plan of subdivision would have significantly improved
the prospects of development of the airport. In the
Council's
14 August 2014 Expression of Interest for funding from Restart NSW
Resources for Regions, under a section titled "Economic
Assessment: Benefits",
the Council identified "large tracts of land" on the airport site as "available
for development for aviation
and related business investment". The explanation
provided for the lack of development was the absence of sewerage and water
connections
on that part of the site, "which has drastically impeded investment
as well as inhibiting the expansion of existing businesses".
The Council
explained:
"The connection of sewer will enable additional land to be available for
development (as it will no longer be required for on-site
sewage management
systems), while the connection of water will unlock proposed development areas
on the western side of the airport
and it will allow existing aviation-related
businesses to expand due to the removal of the restriction on the size of
hangars due
to fire safety codes. This will result in phased revenues from
additional aviation-related developments of up to $275,000 per annum."
- Secondly,
a further area of significant uncertainty resulting from the Council's breach
concerned the extent of increased potential
demand for the respondent's
businesses and use of the "iconic" hangar. Again, however, it is not remote or
fanciful to suggest that
there would have been a substantial increase in demand
for allotments at that location following registration of the plan of
subdivision.
This possibility would flow from an increase in demand that would
come with any development. But even without development of the
airport as
contemplated in the Council's documents, there was already an excess of demand
for hangarage which the Council could not
satisfy. The uncertainty resulting
from the Council's breach concerns the extent to which that demand might have
been satisfied,
and the manner in which it would have been managed, once
subdivision occurred.
- The
demand for hangar space at the airport substantially increased between 2012 and
2014. As noted above, in 2012 the Council had
received around 12 requests for
both hangar space and office space from businesses looking to establish or
expand at the airport,
which it was unable to meet. By the time of the Council's
14 August 2014 Expression of Interest for funding from Restart NSW
Resources
for Regions, the 12 requests received in 2012 had become three
requests per week, an increase of 1,200 per cent, with the Council
observing
that it "is unable to meet demand turning away around 3 aviation inquiries per
week for hangar space".
- Thirdly,
and finally, another area of uncertainty concerned the manner in which the
respondent would have operated its businesses
in circumstances where it held a
leasehold interest in one lot within a 25-lot subdivision in a potentially
developed airport precinct
with potential increased demand for its businesses.
In part, this uncertainty concerned attributes and business techniques of
Mr
Johnston, rather than uncertainty derived from the Council's breach of
contract. For instance, the Council relied upon findings by
the primary judge
that Mr Johnston was a "risk-taker" who "did not concern himself with
detail or with documents" and who was, "at
heart, a speculator, who would see
what angle he could obtain to sell an asset or an opportunity and move on to
other things".[240]
- But
even this third area of uncertainty still derived in part from the Council's
breach of contract. But for the breach of contract
by the Council,
Mr Johnston would have had a leasehold interest over proposed Lot 104
and the airport may have been developed with
a potential increase in business,
depending upon the nature and extent of the development and the management of
demand for hangar
space. The business decisions and risks that Mr Johnston
took for the respondent would have been informed by his lease over proposed
Lot 104 and any accompanying increase in demand for the respondent's
businesses and/or hangar that flowed from development of the
airport.
With the facilitation of the respondent's proof, loss was
established
- The
uncertainties that arose from the Council's breach of contract made proof of the
respondent's loss very difficult. Without any
facilitation of the respondent's
legal onus of proof to establish that its expenditure on construction of the
hangar would have been
recouped, the respondent would have been required to lead
evidence as to the prospect that, having spent $1.3 million to fulfil the
sewerage and water infrastructure requirement in condition 23, the Council
would have obtained or used funds to develop the airport,
in a manner that would
have resulted in a sufficient increase in demand, and within a period of time
during which the respondent's
businesses could be sustained. Large uncertainties
and speculation would be involved.
- In
the absence of further evidence concerning these uncertainties, the facilitation
principle treats the respondent as having established
its loss in the amount of
its reasonable expenditure on the hangar, incurred in anticipation of, or
reliance on, the performance
of the Council's obligation that was breached. The
extent of the uncertainty that resulted from the Council's breach was such as
to
require the Council to lead substantial evidence as to these matters of
uncertainty to establish that some or all of the respondent's
wasted expenditure
would not have been recouped.
- It
is a notable feature of this litigation that the Council ran no alternative case
that the respondent would have recouped part,
but not all, of its expenditure.
As senior counsel for the Council expressed the point in oral submissions, the
Council's argument
was that "no recoupment is more likely than any recoupment".
The Council did not lead any evidence to dispute the inference from
its own
documents that, with the subdivision and the connection of the proposed lots to
Hunter Water Corporation's reticulated sewerage
system, the development of the
airport was seen as highly desirable. Nor, apart from evidence as to its
finances, did the Council
lead any evidence to establish that funding for
development from a loan would have been prohibitively expensive or that equity
investment
was unlikely to be attracted, especially in the event that the
Council had incurred the expenditure necessary to have the subdivision
registered. The Council led no evidence concerning how demand for products or
services at the airport might have been affected by
development, including any
time lags in increased demand. The Council did not even call any witness who
worked for the Council at
the time when the agreement for lease was negotiated
and executed or at any time until very shortly before the Sunset Date.
- It
may be that the limited evidence upon which the Council relied could have
assisted to establish a likelihood that the respondent
would not have recouped
part of its expenditure. But the case, as developed, concerned only the binary
question of whether or not
it was more likely that the respondent would not
recoup any of its expenditure at all. With the benefit of the application of the
facilitation principle, the Court of Appeal was correct to conclude that the
respondent established that it would have recouped its
expenditure.
Conclusion
- The
appeal should be dismissed with costs.
- JAGOT J.
No good can come from a circumstance in which a local government body takes
action to foster the development of its area
without also being willing and able
to fund the action it has contractually promised to undertake. In this case, the
hazard inherent
in that circumstance has come to pass in the form of the
respondent's claim for damages against the appellant, Cessnock City Council
("the Council"), for breach of contract.
- The
damages the respondent claimed were for its wasted expenditure in constructing
an aircraft hangar at the Cessnock Airport, being
land owned by the Council, in
connection with an agreement for lease between the Council as lessor and the
respondent as lessee under
which the Council promised to "take all reasonable
action to apply for and obtain" registration of a plan of subdivision of the
Cessnock
Airport by the "Sunset Date", being 30 September 2011. The Council
no longer disputes that it breached the agreement for lease by
not undertaking
the works necessary to obtain registration of the plan of subdivision, but
contends that the Court of Appeal of the
Supreme Court of New South Wales
(Brereton JA, Macfarlan and Mitchelmore JJA agreeing) erred in
awarding the respondent damages on
account of such wasted expenditure in the
amount of $6,154,459.40 (representing the cost of constructing the hangar of
$3,697,234.41
and interest).
- The
Court of Appeal did not err in applying to this case the principle that where a
party expends money in reliance on the contractual
promise of another party, and
that other party breaches or repudiates the contract by not performing that
promise, a presumption
of fact arises that the expenditure is "wasted" by reason
of the other party's breach or repudiation. Because such expenditure is
presumptively characterised as "wasted" by reason of the other party's breach or
repudiation, that expenditure is properly recoverable
as loss suffered by the
party who has expended the money consistent with the principle in Robinson v
Harman: "where a party sustains a loss by reason of a breach of contract,
[that party] is, so far as money can do it, to be placed in the
same situation,
with respect to damages, as if the contract had been
performed".[241]
- The
relevant controls to maintain the operation of this presumption within the
limits of the Robinson v Harman principle, the effect of which is that no
plaintiff may be placed in a better position than they would have been in had
the contract
been performed, are that: (a) the claimed wasted expenditure
must have been incurred in reliance on, but is not required to have
been
incurred in performance of, the contract; (b) the claimed wasted
expenditure must not be too remote under the rule in Hadley v Baxendale,
which confines recovery to the loss that "may fairly and reasonably be
considered either arising naturally, ie, according to the
usual course of
things, from such breach of contract itself, or such as may reasonably be
supposed to have been in the contemplation
of both parties, at the time they
made the contract, as the probable result of the breach of
it";[242] (c) the
claimed wasted expenditure must not exceed the amount of the expenditure in
performance of or reliance on the contract; and
(d) once the presumption is
engaged, the party in breach can rebut the presumption in whole or part by
proving that the claimed wasted
expenditure is not "wasted" because, had it
performed the contractual promise, "the expense incurred would equally have been
wasted"
by the other party in whole or
part.[243]
- Further,
a claim for wasted expenditure does not exclude a claim for lost profits
resulting from a breach of contract but in such
a case no "double recovery" is
permitted; recovery of lost profits which can be proved to have been suffered
over and above the claimed
wasted expenditure must account for the capital
outlay which the wasted expenditure represents, an expenditure necessary to earn
the claimed lost profits (over and above the amount of the claimed wasted
expenditure).[244]
- Given
the reasoning in McRae v Commonwealth Disposals
Commission[245] and
TC Industrial Plant Pty Ltd v Robert's Queensland Pty
Ltd,[246] from which
these principles emerge with clarity, no greater complexity than this should be
sown into or permitted to invade this
field.
- This
approach to the engagement of the presumption and the controls on its operation
also represents an appropriately robust and
practical approach to the assessment
of damages for contractual breach based on considerations of fairness and
justice.[247] The aptness
of such an approach is exposed by the facts and principled resolution of the
present case.
The critical facts
- Given
the other reasons for judgment, the facts may be identified in summary form.
Most of these facts do no more than expose the
wisdom of the common law's
robustly pragmatic approach to damages for breach of contract, including by
recognising that wasted expenditure
is a compensable head of loss.
- From
late 1998 onwards, the Council considered that the development of the Cessnock
Airport would bring substantial benefits to the
Cessnock local government area.
To that end, the Council: (a) obtained a consultant's report, the "Cessnock
Aerodrome Development
Plan"; (b) issued an expression of interest for the
development and management of the Cessnock Airport; (c) negotiated with the
preferred
tenderer, ultimately entering into an agreement for lease and a
management agreement with the preferred tenderer, Aviation &
Leisure
Corporation Pty Ltd ("ALC"), in March 2004; and (d) lodged with itself a
development application proposing to consolidate
the various lots comprising the
Cessnock Airport into two lots and then to subdivide the new lot 2 into 25 lots,
most of which would
be located to the west of the existing runway and a few of
which would be located to the east of the existing runway including a
proposed
Lot 104.
- The
Council granted itself a development consent for the proposed consolidation and
subdivision subject to conditions on 17 November
2004. The conditions, in
effect, required the subdivided lots to be serviced to the satisfaction of all
relevant authorities. Condition
23 required that the lots be connected to the
existing reticulated sewerage system. The Council commenced this development by
carrying
out physical works on the land, the effect of which was to ensure that
the development consent did not lapse (which it otherwise
would have done had
the development not been commenced within five years of the operative date of
the development consent, which
was 18 November 2004).
- Commencement
of a development the subject of a development consent to prevent the lapse of
the consent is one thing. Complying with
all conditions of a development consent
as required so that a plan of subdivision can be registered to create new lots
is another.
- The
Council obtained registration of the plan of consolidation of the Cessnock
Airport into two lots as contemplated by the development
consent. The Council
also did other things. The Council: (a) adopted a development control plan
for the Cessnock Airport, Development
Control Plan No 53 – Cessnock
Aerodrome ("DCP 53"), setting out its vision and requirements for the
development of the Cessnock
Airport in July 2004; (b) negotiated with the
principal of the respondent, Mr James Johnston, a property developer with an
interest
in aircraft, about an agreement for lease of land within the Cessnock
Airport on which Mr Johnston proposed to construct a hangar
for aircraft used in
an aviation adventure flight business; (c) granted a development consent
for "New Aircraft Hanger [sic] for
Joy Flights and Advanced Flight/Aerobic
Training incorporating an Aviation Museum" on part of the Cessnock Airport in
July 2006;
(d) permitted Mr Johnston to construct the hangar on part of the
Cessnock Airport commencing in the latter part of 2006; (e) executed
an
agreement for lease with the respondent in July 2007; and (f) in partial
compliance with the conditions of the development consent
for the subdivision,
caused works to be carried out so that the land on which the hangar was located
was connected to utility services,
including works for disposal of wastewater
via an extension of the existing reticulated sewerage system.
- The
relevant effects of key provisions of the agreement for lease between the
Council and the respondent were that: (a) the land
to be leased to the
respondent was to be Lot 104, being a lot to be created by registration of the
plan of subdivision the subject
of the grant of development consent by the
Council to itself in November 2004; (b) the commencement date of the lease
was to be the
day after, relevantly, registration of that plan of subdivision;
(c) the Council's obligation to enter into the lease was conditional
on
registration of the plan of subdivision and, by cl 4.2(a)(2), the Council
was required to "take all reasonable action to apply
for and obtain"
registration of the plan of subdivision on or before the Sunset Date, being
30 September 2011; and (d) if the plan
of subdivision was not
registered on or before the Sunset Date, being 30 September 2011, either
party could "rescind" the agreement
for lease by notice and, if so rescinded,
neither party could make a claim for damages against the other.
- For
its part, in or around mid-2009, the respondent substantially completed
construction of the hangar on what was to be Lot 104
if the plan of
subdivision were to be registered. As noted, in constructing the hangar, the
respondent spent $3,697,234.41. From
July to November 2009, the respondent
conducted an adventure flight business from the hangar. The respondent ceased
operating that
business in November 2009 because it was not profitable to
continue. From around September 2009 until February 2010, the respondent
used
the hangar as an aircraft museum, but that business was also unprofitable and
ceased as a result. Between August 2009 and May
2011, the respondent used the
hangar for corporate events, but this business became "completely unsustainable"
in or around June
2011, and therefore ceased. In this context, it is to be
recalled that the Sunset Date by which the plan of subdivision was to be
registered was 30 September 2011.
- In
the meantime, in February 2010, the Council's consultant for the subdivision
works advised the Council that a further $1,317,764
would be required to be
spent by the Council to comply with the conditions enabling registration of the
plan of subdivision, including
connecting the proposed lots on the western side
to the existing reticulated sewerage system as required by condition 23. After
it
received the consultant's estimate, the Council tried to get internal
approval from the Council's Infrastructure Strategy Section
for the allocation
of $1,317,800 to enable such compliance and, thereby, registration of the plan
of subdivision. The Council failed
to secure that allocation.
- At
some time before 29 June 2011 (and, as discussed below, it should be
inferred that it was well before that date), the Council
must have decided that
it was not willing to pay the $1,317,764 necessary to comply with the conditions
of the development consent
to enable registration of the plan of subdivision.
This is apparent from the fact that on 29 June 2011 the Council's General
Manager
told a representative of ALC that "[w]e won't be proceeding with the
subdivision of the land at the Airport. Council has no intention
of spending
about a million dollars fixing the sewerage. We don't have the money and won't
be doing it."
- On
13 September 2011, the Council also wrote to the respondent's legal
representative saying that the "Council has been unable to
achieve the
registration of the plan of subdivision within the timeframe anticipated in the
Agreement for Lease despite taking all
reasonable action to enable that
registration including: obtaining the subdivision approval, construction of
landscape buffers and
arboreal mounding, provision of concrete access crossings,
construction of an intersection dust abatement seal and partial construction
of
a sewer carrier main", and offering to grant to the respondent an exclusive
licence for a term of 25 years or a number of successive
leases for five
years or less.[248]
- Although
the Council asserted that it had taken all reasonable action to apply for and
obtain registration of the plan of subdivision
by the Sunset Date of
30 September 2011, that assertion was self‑serving. Nothing in the
terms of the agreement for lease made
the Council's financial position, or
willingness or unwillingness to incur debt or otherwise fund the works necessary
to comply with
the conditions of the development consent in the ordinary course,
relevant to the reasonableness or unreasonableness of its conduct.
Absent any
circumstance that could be said to engage the doctrine of frustration (and no
such circumstance existed), any consideration
of the Council's financial
position is misplaced. The Council had bound itself to take all reasonable
action to apply for and obtain
registration of the plan of subdivision by the
Sunset Date of 30 September 2011. Having so bound itself, it could not
avoid that
obligation by crying poor.
- The
Council's notice to the respondent's legal representative on 13 September
2011 constituted a repudiation of the Council's obligations
under the agreement
for lease. After further failed negotiations between the respondent and the
Council, the respondent vacated proposed
Lot 104 in mid‑2012. The
Council terminated the agreement for lease in September 2015, a termination
which the primary judge
found valid and against which the respondent did not
appeal. Brereton JA's analysis of these circumstances (Macfarlan and
Mitchelmore
JJA agreeing) is correct. Brereton JA
said:[249]
"Although it may be doubted whether, having repudiated its essential and
fundamental obligation under the Agreement, the Council
was entitled to
terminate for breach by [the respondent], this holding was not challenged on
appeal. ... By refusing to take reasonable
action to procure registration of the
Plan and stating that it did not intend to do so, the Council plainly engaged in
repudiatory
conduct; and there was a continuing repudiatory breach so long as
the Council failed to take the reasonable steps required to procure
registration. In vacating the premises, [the respondent] had accepted the
repudiation and thereby terminated the Agreement. ... But
if that be incorrect,
and the absence of a formal acceptance of the repudiation meant that the
contract remained on foot with the
theoretical possibility that the Council
might yet, albeit belatedly, remedy its breach by taking steps to procure
registration of
the Plan, it put it beyond its capacity to do so when it
terminated in 2015".
Other relevant aspects of the evidence
-
In its call for expressions of interest in 1998, the Council said that the
"Cessnock Aerodrome is strategically located in the rapidly
developing Vineyards
area of the Lower Hunter Valley" and had "failed to achieve its full potential",
but that "[o]pportunities are
now arising for more productive use of the
aerodrome's assets". The call for expressions of interest referred to the
consultant's
report, the Cessnock Aerodrome Development Plan, which recommended
in favour of "significant upgrading and expansion of Cessnock
Aerodrome" on
eight bases, including that the "Aerodrome is Strategically located in the mid
Hunter and is at the prime 'Gateway'
to the Vineyards District", tourism and
demand for pilot training is increasing, and there "is significant potential in
the site
for air‑related industry development (Western side) and some
potential for tourism development (Eastern side)".
- In
DCP 53, published in 2004, the Council said that "[t]he proposals for
expansion of the airport and associated facilities are based
on a realistic
balance between the potential for growth in aircraft movements over a range of
categories against the cost of development
and maintenance of facilities, and
the need to complement those activities which make the Vineyards District a
unique and important
part of the City of Cessnock".
- In
August 2012, the Council endorsed the nomination of the development of the
Cessnock Airport as a priority project for funding
under the Hunter
Infrastructure and Investment Fund. The report to the Council recommending in
favour of the nomination recorded
that the "Council took back management of the
aerodrome in December 2011", amongst other things, to "[p]romote economic and
tourism
development across the local government area" and to "[p]rovide a
sustainable revenue stream". The report said that "[t]his year
Council has
received around twelve requests for both hangar space and office space from
businesses looking to establish or expand
at Cessnock Airport and, at present,
Council is unable to satisfy this demand" and "grant funding is an opportunity
for Council to
meet, in the short‑term, this demand from businesses
wishing to establish within the local government area (economic benefit);
provide an ongoing revenue stream for Council; and bring an iconic building into
public ownership (social benefit)". The "iconic
building", as disclosed in the
nomination as submitted, is the hangar the respondent constructed. According to
a subsequent application
the Council made for funding, "[w]ith the expansion of
Bankstown Airport being opposed by Bankstown City Council, there are strong
prospects for Cessnock Airport to become the base for aviation‑related
businesses looking to expand". The proposal was to acquire
the hangar, to fit
out part of the hangar with modular office space for "businesses operating at
the Aerodrome (such as helicopter
flights, jet rides, vintage flights, etc)" and
to lease the remainder as hangar space or for other business opportunities. The
funding
sought for this project was $2,000,000.
- In
2014, the Council applied for grant funding for a "significant infrastructure
upgrade of Cessnock Airport to realise the community's
vision of it being a
well‑planned and serviced facility that attracts
environmentally‑responsible economic development
opportunities to the
Cessnock region". The Council sought nearly $7,000,000 in funding. The
application identified that the "Cessnock
Airport is a centrally‑located
general aviation airport ... currently being utilised for adventure, scenic and
charter flights
(including mining fly‑in fly‑out charters),
ballooning, recreational flying, flying school operations and aircraft
maintenance",
but was lacking in the infrastructure and facilities to enable it
to be used as a passenger transport or freight hub. The application
also said
this:
"On the western side of the airport there are large tracts of land available for
development for aviation and related business investment,
however, there is
no connection of sewer or water on this part of the site, which has drastically
impeded investment as well as inhibiting
the expansion of existing
businesses." (emphasis added)
- These
"large tracts of land" on the western side of the Cessnock Airport are the
location of the majority of the 25 lots proposed
to be created and fully
serviced in accordance with the development consent for the subdivision the
Council granted to itself in
November 2004.
- The
application also said that the "Cessnock Airport offers a major opportunity to
meet the economic, employment, social and sustainability
needs of all the
communities and their residents across the [local government area] and become a
key community asset. It is ideally
situated and investment ready."
- The
Council released another version of the Cessnock Airport Strategic Plan (first
released in 2014 and thereafter amended) in February
2020. This Strategic Plan
described the Cessnock Airport as a "vibrant hub and an integral component to
the Hunter community", the
success of which was "in the fact it already has a
point of difference in the market place due to its central location to the
vineyards
of the Hunter Valley and the current varied user base, and this should
be developed". The Strategic Plan said that "[w]ater, sewerage
and power is
available to the eastern side of the Airport. The western side water is via
tanks, and sewerage is treated through individual
on site sewerage management
systems." This reflects the fact that the Council completed only part of the
works required by the development
consent for the subdivision. The Strategic
Plan also said that a "Precinct Masterplan will aid in attracting future
development".
Again, Masterplans were required to be completed under
condition 20 of the development consent for the subdivision. According to
the Strategic Plan, the "Cessnock Airport has excellent opportunities to
capitalise on developing networks with other airports both
within the Hunter
Region and other adjoining regions, including metropolitan Sydney". The
Strategic Plan said that "[c]onsideration
to a centralised waste water system on
the western side may also be an option instead of connection to 'mains'". It
should be inferred
that this option was raised due to the fact that the
connection of the western side of the Cessnock Airport to the existing
reticulated
system, as required by condition 23 of the development consent
before the plan of subdivision could be registered, had been estimated
in 2010
to cost the best part of $1,317,764.
- An
affidavit of Teressa Chadwick, the Governance and Council Support Coordinator,
who worked at the Council from October 2017 onwards,
attaches documents,
including documents from the Council's consultant overseeing compliance with the
conditions of the development
consent for the subdivision. The affidavit
attaches numerous documents from the consultant from 2005 to 2008. Between 2009
and 2010,
a few documents are attached from the consultant. In 2011, no
documents are attached from the consultant. The documents are described
as
including: (a) a contract entered into in January 2007 with a contractor
for the construction of sewer mains at the Cessnock Airport,
with invoices and
progress claims by the contractor being provided in April and May 2007, and
January, February and March 2008; and
(b) a quotation for the preparation
of a Masterplan for the Cessnock Airport in August 2007, and further proposals
for the preparation
of the Masterplan by consultants in April and June 2008.
From May 2009, the main communications from the consultant overseeing compliance
with the conditions of the development consent for the subdivision comprised
status reports rather than invoices, and other documents
associated with
progressing the works required to comply with the conditions of the development
consent.
- The
Council called no evidence to suggest that any inference that would otherwise be
drawn from the documentary record should not
be drawn. The inferences that
should be drawn are that: (a) at least until sometime in 2008, the Council
was committed to ensuring
that the conditions of the development consent for the
subdivision were satisfied; (b) by no later than early 2009, the cost of
those
works caused the Council to reconsider its willingness to ensure that it
continued to take all reasonable action required to comply
with those conditions
and, thereby, obtain registration of the plan of subdivision; and (c) from
no later than early 2009 onwards,
the Council was manifestly not continuing to
progress all or at least most of the works required to comply with the
conditions of
the development consent for the subdivision.
The
required comparison
- The
position if the Council had performed its obligations under the agreement for
lease must be compared with the actual position
by reason of the Council's
failure to perform its obligations under the agreement for lease. This will
enable assessment of the Council's
argument that, if the presumption of
recoupment did arise (contrary to its case), it rebutted the presumption.
- The
Council's obligation was to take all reasonable action to apply for and obtain
registration of the plan of subdivision by the
Sunset Date of 30 September
2011. To comply with that obligation the Council would have had to satisfy all
conditions of the development
consent required to be satisfied before
registration of the plan of subdivision and, thereafter, apply for registration
of the plan
of subdivision. It may be accepted that, once the Council had done
these things, it could do no more to obtain registration of the
plan of
subdivision other than promptly dealing with any inquiries or requisitions from
the registering authority.
- It
is apparent, therefore, that to enable registration of the plan of subdivision
by the Sunset Date of 30 September 2011 the Council
would have had to
ensure compliance with the conditions of the development consent well before the
Sunset Date of 30 September 2011.
Had it done so and obtained registration
of the plan of subdivision by the Sunset Date of 30 September 2011 then, by
satisfying the
conditions of the development consent, all 25 proposed lots would
have been fully serviced. That is, all required kerbs, gutters,
footpaths,
driveways, roads, landscaping, street lighting, and drainage works would have
been completed. In addition, all connections
of each lot to energy services,
water services, telecommunications services, and the reticulated sewerage system
would have been
made available to each proposed lot. Further, all required
cross‑easements, other easements, rights of carriageway, and dedication
of
land for public road purposes would have formed part of the application for
approval of the plan of subdivision, ensuring legal
access and provision of all
services to and from all lots in the subdivision. Moreover, as required by
condition 20, the Council
would have prepared and approved the Masterplans
as required by DCP 53. Finally, had these works been completed in
sufficient time
to enable the plan of subdivision to be registered by the Sunset
Date of 30 September 2011, the respondent's hangar would have been
located
on a legal lot in a registered subdivision comprising that lot and 24 other
legal lots, each lot capable of separate long‑term
lease by the Council
and development by a third party, on the basis of approved Masterplans for the
overall development of the Cessnock
Airport, DCP 53 contemplating that
development.
- The
actual position as at the Sunset Date of 30 September 2011, by reason of
the Council's failure to perform its obligations under
the agreement for lease,
was that only some of the works required by the development consent for
subdivision had been satisfied.
In particular, the Council had not complied with
condition 23, requiring the connection of all lots to the existing reticulated
sewerage
system. Accordingly, none of the 25 lots had been created. Nor had any
of the rights (for example, cross‑easements, other easements,
rights of
carriageway, and dedication of land for public road purposes) which would have
been created by approval of the plan of
subdivision. None of the proposed lots
were capable of being the subject of the grant of a lease exceeding five
years.[250] The hangar
continued to exist on a large parcel that included proposed Lot 104, but
neither proposed Lot 104 nor any of the other
24 proposed lots existed.
- Two
further points should be made in this comparative exercise. First, the
respondent commenced its business operations from the
hangar on proposed
Lot 104 once it had been connected to services as the development consent
required, but the time during which
it conducted those business operations (from
July 2009 to June 2011) coincided with the period by and within which the
Council manifestly
was not proceeding to complete the works required for the
plan of subdivision to be registered and within which the Council positively
decided that it would not be doing so. Second, at least in its application to
obtain grant funding in 2015, the Council considered
that the lack of connection
of the western side of the Cessnock Airport to the existing reticulated sewerage
system "has drastically
impeded investment as well as inhibiting the expansion
of existing businesses", that being the main development area for hangars
and
hangar homes identified in DCP 53, which, to enable secure tenure to be
granted, would have required registration of the plan
of subdivision.
The Council's case
- The
essence of the Council's case, as relevant to this appeal, was that the
respondent had to prove that the money it spent on building
the hangar was
"wasted" in the sense that, had the Council performed its legal obligations
under the agreement for lease, the respondent
would have recouped at least that
amount of money over the term of the lease. Putting it another way, the
Council's case was that
the respondent had not proved that it was in any
different position from that in which it would have been had the Council
performed
its legal obligations under the agreement for lease, with the asserted
consequence that the respondent suffered no loss by reason
of the Council's
breach of contract. According to this argument, the respondent's business
proposals for the hangar were inherently
speculative and, even if the Council
had taken all reasonable action to apply for and obtain registration of the plan
of subdivision
by the Sunset Date of 30 September 2011, the respondent's
businesses would have failed by no later than June 2011 in any event (as
they
did in fact fail).
- This
argument also involved the proposition that the businesses the respondent
operated from the hangar between July 2009 and June
2011 could never have been
profitable without the development of the Cessnock Airport otherwise proceeding,
the Council never guaranteed
that such development would have occurred either by
the Sunset Date of 30 September 2011 or at all, and such development
depended
on the actions of third parties and therefore was outside of the
Council's control. By reason of these matters, the Council contended
that either
the presumption did not arise at all in this case or that, if the presumption
arose, it had been rebutted.
McRae
- In
McRae, Dixon and Fullagar JJ explained the principles that should be
applied in a case of claimed wasted expenditure by distinguishing
between:
(a) a fallacious conception of that case as one of non‑delivery of a
contracted‑for item (an oil tanker capable
of salvage) which meant that
the plaintiffs' expenditure on seeking to salvage the non‑existent tanker
could not be "wasted"
in the sense necessary to constitute recoverable loss; and
(b) the correct conception of the case as one in which "the contract
alleged
is a contract that there was a tanker in a particular place, and the
breach assigned is that there was no tanker there, and the damages
claimed are
measured by expenditure incurred on the faith of the promise that there was a
tanker in that place".[251]
On that correct basis, Dixon and Fullagar JJ said
that:[252]
"[The plaintiffs] have now a starting‑point. They can say: (1) this
expense was incurred; (2) it was incurred because you promised
us that there was
a tanker; (3) the fact that there was no tanker made it certain that this
expense would be wasted. The plaintiffs
have in this way a starting‑point.
They make a prima‑facie case. The fact that the expense was wasted flowed
prima facie
from the fact that there was no tanker; and the first fact is
damage, and the second fact is breach of contract. The burden is now
thrown on
the Commission of establishing that, if there had been a tanker, the expense
incurred would equally have been wasted. This,
of course, the Commission cannot
establish. The fact is that the impossibility of assessing damages on the basis
of a comparison
between what was promised and what was delivered arises not
because what was promised was valueless but because it is impossible
to value a
non‑existent thing. It is the breach of contract itself which makes it
impossible even to undertake an assessment
on that basis. It is not impossible,
however, to undertake an assessment on another basis, and, in so far as the
Commission's breach
of contract itself reduces the possibility of an accurate
assessment, it is not for the Commission to complain."
- Their
Honours were not saying that the plaintiffs had to prove that it was impossible
to assess damages on the usual basis of returns
had the contract been performed
before the plaintiffs could recover their loss. They were recognising wasted
expenditure as a category
of recoverable loss and saying only that it hardly
befitted the party in breach to complain about the fact that the plaintiffs
could
not prove their loss on the usual basis. They also were not saying that
the contract had to be within some special class before expenditure
in reliance
on (not mere performance of) the contract would be characterised as "wasted" by
reason of the non‑performance of
the contractual promise.
Amann Aviation
- It
may be accepted that the reasoning in The Commonwealth v Amann Aviation Pty
Ltd[253] is not as
straightforward as that of Dixon and Fullagar JJ in McRae. But that
is no reason to elevate every or any nuance of the Court's reasoning processes
to the level of principle.
- Mason CJ
and Dawson J concluded that "a plaintiff has a prima facie case for
recovery of wasted expenditure once it is established
that the expense was
incurred in reliance on the promise of the party in breach, there being a
failure of performance by that party",
it being "just and fair that the
repudiating party should bear the onus of showing that the party not in breach
would have made a
loss on the
contract".[254] As they put
it, "it was a case in which, it being natural and appropriate for Amann to sue
to recover its wasted expenditure by way
of reliance damages, the onus rested on
the Commonwealth of establishing that the reliance expenditure would have been
wasted even
if the contract had been
performed".[255] This
accords precisely with the reasoning in McRae, the only difference being
their Honours' observation that, unlike McRae, "it was not impossible, as
a matter of theory, for Amann to establish what its profits (if any) would have
been had the Commonwealth
not repudiated the
contract".[256] Again, the
point is not that the Commonwealth's breach had to make it impossible or even
difficult for Amann to prove loss other
than on the basis of wasted expenditure.
It is simply that it is hardly for the party in breach to complain about that
impossibility
or difficulty.
- The
exception to the presumption which Mason CJ and Dawson J contemplated,
of "a purely aleatory contract" where "inherent in the
entry into such a
contract is the contingency that not even the slightest expenditure will be
recovered, let alone the securing of
any net
profit",[257] should not be
permitted to be expanded beyond its strict terms. An aleatory contract is one in
which the required performance depends
entirely on a mere chance event, such as
a life insurance contract. The agreement for lease between the Council and the
respondent
was not of this kind. There is no principled basis available to
expand the exception to the presumption which Mason CJ and Dawson
J
contemplated.
- Brennan J
accepted that "the amount which a plaintiff has reasonably expended in reliance
on the defendant's promise and which is
wasted by reason of the defendant's
breach of his promise is a proper subject of damages for breach of
contract"[258] and that
while the onus of proof of loss was on the plaintiff a "sufficient and necessary
justification for shifting the onus to
the party in breach in the assessment of
damages for wasted expenditure incurred in reliance on the defendant's promise
before rescission
for breach is that the breach of the contract itself makes it
impossible to undertake an assessment on the ordinary
basis".[259] This
conception of the justification for the presumption or prima facie case of
recoupment also does not make impossibility of an
assessment of loss on the
ordinary basis a prerequisite to the engagement of the presumption or prima
facie case of recoupment.
- Deane J,
quoting an observation of Cooke J, observed that "[i]t has been truly said
that the assessment of damages in contract and
tort is 'a pragmatic
subject ... [which] does not lend itself to hard‑and‑fast
rules'".[260] Reflecting
that pragmatism, his Honour said that "[i]n a case where a plaintiff has
incurred expenditure either in procuring the
contract or in its performance but
it is impossible or difficult to establish the value of any benefits which the
plaintiff would
have derived from performance by the defendant, considerations
of justice dictate that the plaintiff may rely on a presumption that
the value
of those benefits would have been at least equal to the total detriment which
has been or would have been sustained by
the plaintiff in doing whatever was
reasonably necessary to procure and perform the
contract".[261]
Deane J continued, saying that "[w]here that presumption is operative, it
enables the recovery by a plaintiff of what are commonly
referred to as
'reliance damages', that is to say, damages equivalent to the wasted expenditure
which has been reasonably incurred
in reliance upon the assumption that the
contractual promises of the defendant would be honoured" but that the
"presumption will
be rebutted if it be self‑evident or established that
the plaintiff would have derived no financial or other benefit from performance
of the contract or that any financial or other benefit which would have been
derived from future performance would not have been
sufficient in value to
counterbalance the past
expenditure".[262] This
reasoning is not readily reconcilable with McRae and involves the
contradiction of, on the one hand, requiring the assessment of damages on the
usual basis (returns from the performance
of the contract) to be impossible or
difficult and, on the other hand, imposing an onus on the party in breach to
disprove the impossible
or difficult.
- Toohey
J considered that the principle in Robinson v
Harman[263] –
that damages for breach of contract are to place the party who has sustained
loss, so far as money can do so, in the same
position as if the contract had
been performed – accorded with the concept of reliance damages provided
that such damages did
not exceed the wasted
expenditure.[264]
Toohey J accepted that "if the plaintiff would not have recouped [their]
outlay in any event, [they are] not entitled to reliance
damages".[265] His Honour
reiterated that "the primary rule is that it is for the plaintiff to establish
the damages to which [they are]
entitled",[266] but this
was "not to say that, in some instances, damage may not be inferred or
presumed".[267] His Honour
resolved the question of onus on the basis that "[t]here is, in effect, an
evidentiary onus on the defendant to show that
receipts would not have equalled
outlay by the plaintiff, though ultimately the aim is to determine what loss has
occurred on the
basis of all available evidence. It may be assumed, in the
absence of evidence to the contrary, that the plaintiff would have recovered
[their] costs."[268]
- Gaudron J
identified that "[t]he present case is one in which the uncertainties are such
that it is not possible to make any reliable
estimate of the value of Amann's
contractual rights. Thus, it is one in which the assessment of damages might
properly be approached
having regard to Amann's wasted
expenditure."[269]
Gaudron J said that "[o]nce it is appreciated that damages assessed by
reference to wasted expenditure are awarded to compensate
for the loss of
contractual rights or for loss of profits, it is apparent that what is involved
is an assumption that the loss is
no less than that which has been outlaid and
wasted by reason of repudiation or
breach".[270]
Gaudron J rejected the notion that the party in breach was subject to a
legal onus, but said that "[t]he assumption which underlies
the award of damages
by reference to wasted expenditure, like all assumptions, is one which, once
made, will ordinarily be maintained
unless displaced by evidence pointing to the
contrary. In a practical sense that may mean that the assumption will often be
made
and maintained unless the defendant proves
otherwise."[271] As a
"starting‑point", the assumption had to "give way if there is evidence to
the contrary".[272]
Further, "the circumstances may be such as to preclude any assumption to that
effect. Thus, the assumption will not be made if it
appears that receipts would
have been less than the amount of the wasted
expenditure."[273]
- McHugh J
did not accept that McRae was based on a principle "that proof of
expenditure gives rise to a prima facie inference that it will be recouped by
the carrying
out of the contract", that decision being "satisfactorily based on
the broad principle of justice that, if the breach of the defendant
has made it
impossible to ascertain whether or not the plaintiff would have made a profit
from the performance of the contract, it
is only fair that the defendant should
reimburse the plaintiff for expenditure which it has wasted as the result of the
breach".[274] Accordingly,
his Honour considered that once the plaintiff had proved that it was impossible
to assess the outcome of performance
of the contract, the plaintiff "is entitled
to be compensated for all expenditure wasted in reasonable reliance on the
defendant's
promise to perform its side of the
contract".[275] This
approach, like that of Deane J, may also elevate the impossibility of
ascertaining damages on the usual basis to a precondition
to the engagement of
the presumption, contrary to McRae.
Post-Amann
Aviation
- In
Berry v CCL Secure Pty
Ltd,[276] in explaining
Amann Aviation, Bell, Keane and Nettle JJ said
that:[277]
"While a claimant bears the legal burden of establishing the amount of its loss
or damage, the nature and circumstances of the wrongdoer's
conduct may support
an inference or presumption that shifts the evidentiary burden ... One
relevant modern application of that principle
is reflected in this Court's
decision in Amann Aviation".
- While
their Honours referred to Brennan J as having explained that, in the
circumstances of that case, "it was just that the Commonwealth
should bear the
ultimate onus of proving at least a prospect that Amann's returns under the
contract would not have been sufficient
to recoup that
expenditure",[278] their
Honours should not be understood as suggesting that a party in breach in such a
case will discharge its onus merely by proving
a "prospect" of
non‑recoupment had the contract been performed. There was no need for
their Honours to consider the presumption
on the facts of that
case,[279] and it is clear
from the reasoning in Amann Aviation that the mere prospect of
non‑recoupment was not sufficient to defeat Amann's claim for recoupment
of wasted expenditure.
- The
approach of Dixon and Fullagar JJ in McRae accords with that of
Mason CJ and Dawson J in Amann Aviation. That approach has the
advantage of embodying the robust practicality, informed by considerations of
fairness and justice, that the
common law takes to the assessment of damages for
contractual breach. That approach should be applied as indeed the Court of
Appeal
did.[280]
The
presumption
- The
applicable principles, if engaged, do not permit the Council's attempts to
elevate what are truly matters of the sufficiency
of proof – namely, for
the party in breach to rebut the presumption by discharging the legal onus on it
in a particular case
– to the status of preconditions to the engagement of
the presumption. Accordingly, leaving aside purely aleatory contracts
(where the
presumption may not arise at all), the strength of the presumption does not vary
depending on the nature of the particular
contract or the allocation of risks
under it. The presumption is the presumption. It is a presumption that
expenditure in reliance
on the other party's performance of the contract is
wasted expenditure and, therefore, is a recoverable category of loss if the
contract
is not performed by reason of that other party's breach. What may vary
is the evidence necessary to rebut the presumption having
regard to the nature
of the particular contract or the allocation of risks under it. Similarly,
considerations such as the nature
and degree of the expenditure and its
relationship (essential or incidental) to the contract, the expected source of
recoupment of
the expenditure (from the contract breaker or otherwise), the
degree of speculation inherent in the contract or expenditure, and
the actual
conditions referable to the contract leading up to the breach – all of
which were called in aid by the Council to
support its case – do not
determine whether the presumption is engaged or not. Nor do such considerations
determine the strength
of the presumption. But they may be relevant to the
question of the remoteness of damage, the reasonableness of the expenditure,
and
the evidence sufficient to rebut the presumption by discharge of the legal onus
of the party in breach.
Application of McRae and Amann
Aviation to the present case
- No
party challenged the correctness of McRae or Amann Aviation in
this appeal.
- The
respondent spent the $3,697,234.41 constructing the hangar. There can be no
proper suggestion in this appeal that this expenditure
was unreasonable. The
respondent constructed the hangar relying on the Council's contractual promise
to take all reasonable action
to apply for and obtain registration of the plan
of subdivision by the Sunset Date of 30 September 2011. While that
contractual promise
did not guarantee registration of the plan of subdivision,
it did guarantee that the Council would do everything reasonable to enable
such
registration. Those actions included satisfying the conditions of the
development consent for the subdivision. The loss in the
form of the wasted
expenditure is within the second limb of the rule in Hadley v
Baxendale,[281] namely
such loss as may reasonably be supposed to have been in the contemplation of
both parties at the time they made the contract
as being the probable result of
the breach. The Council has not proved that the respondent would not have
recouped the cost of constructing
the hangar if the Council had fulfilled its
contractual promise.
- One
problem with the Council's arguments that it rebutted the presumption is that
they fail to recognise the difference between:
(a) on the one hand,
operating the businesses the respondent operated from the hangar between July
2009 and June 2011 in circumstances
where the Council was manifestly working
towards completing all works required by the development consent to enable
registration
of the plan of subdivision and obtaining approvals for the
Masterplans required by DCP 53; and (b) on the other hand, operating
those
businesses in circumstances where those works had manifestly stalled due
to lack of the commitment of funds by the Council to complete
those works.
Another problem with the Council's arguments that it rebutted the presumption is
that, as is apparent from the Council's
own documents referred to above,
everything the Council said and did from 1998 in relation to the development of
the Cessnock Airport
is irreconcilable with those arguments.
- It
is also not to the point that the profitability of the respondent's businesses
being conducted from the hangar always depended
on the patronage not of the
Council but of others. It is obvious that the patronage of others was going to
be heavily dependent on
the Council fulfilling its contractual obligation to
take all reasonable action to obtain registration of the plan of subdivision
by
the Sunset Date of 30 September 2011. The Council did not guarantee that
others would take up the development potential of the
other lots to be created
by the subdivision. But it did guarantee to take all reasonable action to create
those lots by the Sunset
Date of 30 September 2011. And, in guaranteeing
that, it also guaranteed to satisfy the conditions of the development consent.
Had
it done so, those proposed lots would have been fully serviced and
immediately available for development. That hypothesised circumstance
bears no
resemblance to the reality of the respondent's business operations from the
hangar between July 2009 and June 2011, in which
development could not occur on
the western side of the Cessnock Airport because the Council was unwilling to
spend the money required
to service that land in accordance with the development
consent for the subdivision.
- Further,
it is not correct to say, as the Council contended, that the respondent's
success depends on matters where the key evidence
lay with the respondent,
namely as to what businesses it would have sought to conduct and how it would
have sought to finance them
if the Council had fulfilled its contractual
promise. The respondent conducted businesses from the hangar, but they failed in
the
actual situation of the Council not having fulfilled its contractual
promise. Accordingly, the "disastrous performance" of the respondent's
businesses up to breach, as the Council described it, proves nothing. It is
quite unrealistic to infer that the failure of the respondent's
businesses in
the actual situation in which it found itself between 2009 and 2011 would have
been the same had the Council not repudiated
the contract. It is one thing to
accept that the repudiation did not occur until 13 September 2011, when the
Council wrote to the
respondent. It is another to assume or infer that the
respondent's businesses would have been in the same circumstances between 2009
and 2011 irrespective of that repudiation.
- The
Court of Appeal was correct to conclude that "the fact that there was no promise
to develop the airport does not mean that the
potentiality of its development is
irrelevant when considering whether the Council had shown that [the respondent]
would not recoup
its expenditure", as "it is permissible to have regard also to
potential benefits that might have accrued to the plaintiff, although
they are
not contractual entitlements, if they may reasonably be supposed to have been in
the contemplation of the parties" when
they entered into the
contract.[282] The Court of
Appeal was also correct to conclude that "[p]roof of losses in the early stages
of a business or enterprise that was
to run for many years does not establish
that, over the term of the Lease, [the respondent] would not have earnt
sufficient revenue
to recoup its
costs".[283] This is
particularly so in the circumstances identified above, namely that the
respondent's businesses were operating in an environment
not comparable to the
environment in which they would have been operating had the Council fulfilled
its contractual promise. Accordingly,
the Council did not discharge the onus of
proving that the expenditure on the hangar would have been wasted irrespective
of its repudiation
of the contract. Therefore, the presumption of recoupment was
not rebutted.
- For
these reasons, the appeal should be dismissed with costs.
[1] 123 259 932 Pty Ltd v Cessnock
City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 487-488 [73].
[2] (1854) 9 Exch 341 [156 ER
145].
[3] 123 259 932 Pty Ltd v Cessnock
City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 513 [146].
[4] Including, most recently,
Winterton, "Reassessing 'Reliance Damages': The High Court Appeal in Cessnock
City Council v 123 259 932 Pty Ltd" (2024) 46 Sydney Law Review
(advance).
[5] Tabcorp Holdings Ltd v Bowen
Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272 at 286 [13].
[6] [1848] EngR 135; (1848) 1 Exch 850 at 855
[154 ER 363 at 365].
[7] Haines v Bendall [1991] HCA 15; (1991) 172
CLR 60 at 63.
[8] Baltic Shipping Co v Dillon
[1993] HCA 4; (1993) 176 CLR 344 at 367. See also Paciocco v Australia & New Zealand
Banking Group Ltd [2016] HCA 28; (2016) 258 CLR 525 at 616 [283].
[9] Seddon and Bigwood, Cheshire
& Fifoot Law of Contract, 12th Aust ed (2023) at 1223 [23.2].
[10] Clark v Macourt [2013] HCA 56; (2013)
253 CLR 1 at 11 [26].
[11] See Kramer, The Law of
Contract Damages (2014) at 482; Barnett, Damages for Breach of
Contract, 2nd ed (2022) at 81 [3-007].
[12] [1884] USSC 74; (1884) 110 US 338 at 344.
Insofar as United States v Behan [1884] USSC 74; (1884) 110 US 338 at 345-347 can be read
to suggest that a defaulting party is "estopped" from asserting that the value
of performance
would not have equalled the expenditure towards performance, it
must be read in light of L Albert & Son v Armstrong Rubber Co (1949)
178 F 2d 182 at 189.
[13] [1910] NSWStRp 13; (1910) 10 SR (NSW) 220 at
227-230, 231, 234-236.
[14] [1884] USSC 74; (1884) 110 US 338 at 345.
[15] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082.
Permission to appeal was refused by the Supreme Court of the United Kingdom.
[16] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082 at
1095 [40], 1103-1104 [69]-[73].
[17] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082 at
1104 [73]. See also at 1105-1106 [84].
[18] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 54.
[19] See Owen, "Some Aspects of the
Recovery of Reliance Damages in the Law of Contract" (1984) 4 Oxford Journal
of Legal Studies 393 at 396. See also Chitty on Contracts, 35th ed
(2023), vol 1 at 2238 [30-025] and Seddon and Bigwood, Cheshire & Fifoot
Law of Contract, 12th Aust ed (2023) at 1235 [23.11].
[20] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 79. See Burrows, "Damages for Breach of Contract: Expectation Limiting Status
Quo" (1984) 100 Law Quarterly Review 27 at 28-30.
[21] (1949) 178 F 2d 182.
[22] [1991] HCA 54; (1991) 174 CLR 64 at 86-87,
105-106, 126, 138-139, 154, 156.
[23] See Bowlay Logging Ltd v
Domtar Ltd (1978) 87 DLR (3d) 325 at 334 (Supreme Court of British
Columbia); Ti Leaf Productions Ltd v Baikie [2001] NZCA 303; (2001) 7 NZBLC 103,464 at
103,471 [33]; Mega Yield International Holdings Ltd v Fonfair Co Ltd
[2014] HKCA 466 at [58]; Soteria Insurance Ltd v IBM United Kingdom Ltd
[2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082 at 1097 [45].
[24] (1949) 178 F 2d 182 at 189.
[25] [1951] HCA 79; (1951) 84 CLR 377.
[26] [1953] HCA 31; (1953) 89 CLR 327.
[27] [1963] HCA 57; (1963) 180 CLR 130.
[28] [1951] HCA 79; (1951) 84 CLR 377 at
410-411.
[29] [1951] HCA 79; (1951) 84 CLR 377 at 412.
[30] [1951] HCA 79; (1951) 84 CLR 377 at 413, 415,
417-418.
[31] [1951] HCA 79; (1951) 84 CLR 377 at 413.
[32] [1951] HCA 79; (1951) 84 CLR 377 at
413-414.
[33] [1951] HCA 79; (1951) 84 CLR 377 at 414
(emphasis added).
[34] [1951] HCA 79; (1951) 84 CLR 377 at 414. See
The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 89.
[35] [1953] HCA 31; (1953) 89 CLR 327 at 352.
[36] [1953] HCA 31; (1953) 89 CLR 327 at 352.
[37] [1963] HCA 57; (1963) 180 CLR 130 at 136.
[38] [1963] HCA 57; (1963) 180 CLR 130 at 138.
[39] [1963] HCA 57; (1963) 180 CLR 130 at 141.
[40] [1963] HCA 57; (1963) 180 CLR 130 at 141.
[41] [1991] HCA 54; (1991) 174 CLR 64.
[42] See Treitel, "Damages for
Breach of Contract in the High Court of Australia" (1992) 108 Law Quarterly
Review 226; Lücke, "The So-Called Reliance Interest in the High Court"
(1994) 6 Corporate & Business Law Journal 117.
[43] [1991] HCA 54; (1991) 174 CLR 64 at 72-74.
[44] [1991] HCA 54; (1991) 174 CLR 64 at 97-98,
115, 157-158.
[45] [1991] HCA 54; (1991) 174 CLR 64 at 82.
[46] [1991] HCA 54; (1991) 174 CLR 64 at 82.
[47] [1991] HCA 54; (1991) 174 CLR 64 at 85.
[48] [1991] HCA 54; (1991) 174 CLR 64 at 89.
[49] [1991] HCA 54; (1991) 174 CLR 64 at 82,
86-87.
[50] [1991] HCA 54; (1991) 174 CLR 64 at 85-86.
[51] [1991] HCA 54; (1991) 174 CLR 64 at 82-83.
[52] [1991] HCA 54; (1991) 174 CLR 64 at 86.
[53] [1991] HCA 54; (1991) 174 CLR 64 at 85.
[54] [1991] HCA 54; (1991) 174 CLR 64 at 85.
[55] [1991] HCA 54; (1991) 174 CLR 64 at 86-87
(emphasis omitted).
[56] [1991] HCA 54; (1991) 174 CLR 64 at 89.
[57] [1991] HCA 54; (1991) 174 CLR 64 at 90.
[58] [1991] HCA 54; (1991) 174 CLR 64 at 104-108,
155-157.
[59] [1991] HCA 54; (1991) 174 CLR 64 at
106-107.
[60] [1991] HCA 54; (1991) 174 CLR 64 at
104-108.
[61] [1991] HCA 54; (1991) 174 CLR 64 at 157.
[62] [1991] HCA 54; (1991) 174 CLR 64 at 156.
[63] [2020] HCA 27; (2020) 271 CLR 151 at 169-170
[29].
[64] Robinson v Harman [1848] EngR 135; (1848)
1 Ex 850 at 855 [154 ER 363 at 365]. See also Wenham v Ella [1972] HCA 43; (1972) 127
CLR 454 at 471; Burns v MAN Automotive (Aust) Pty Ltd (1986) 161 CLR 653
at 667, 672; The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174
CLR 64 at 80, 98, 161; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
[2009] HCA 8; (2009) 236 CLR 272 at 286 [13]; Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1 at 6
[7], 11 [26], 19 [60], 30 [106].
[65] Haines v Bendall [1991] HCA 15; (1991)
172 CLR 60 at 63; Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 82, 136,
155, 163; Clark [2013] HCA 56; (2013) 253 CLR 1 at 11 [27], 19 [60].
[66] Tabcorp Holdings [2009] HCA 8; (2009)
236 CLR 272 at 286 [13]. See also Johnson v Perez [1988] HCA 64; (1988) 166 CLR 351 at
355, 386; Haines [1991] HCA 15; (1991) 172 CLR 60 at 63; Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 98, 116, 161; Clark [2013] HCA 56; (2013) 253 CLR 1 at 6 [7], 11 [26], 19
[60], 32 [111].
[67] Berry v CCL Secure Pty
Ltd [2020] HCA 27; (2020) 271 CLR 151 at 168 [28], citing Amann Aviation [1991] HCA 54; (1991) 174
CLR 64 at 80, 88, 99, 118, 137. See also Clark [2013] HCA 56; (2013) 253 CLR 1 at
11 [27].
[68] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 80-81, 98-99, 117, 134-135, 148, 161; Tabcorp Holdings
[2009] HCA 8; (2009) 236 CLR 272 at 286 [13]. See also L Albert & Son v Armstrong
Rubber Co (1949) 178 F 2d 182 at 189; Omak Maritime Ltd v Mamola
Challenger Shipping Co [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 50 [15].
[69] Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 80-82, 137, 161.
[70] Holt v United
Security Life Insurance & Trust Co (1909) 72 A 301 at 306. See also
Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 99.
[71] Holt (1909) 72 A 301 at
306.
[72] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 99.
[73] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 81.
[74] Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 81, 85-86, 89, 105‑106, 126, 130-131, 137. See
also McRae v Commonwealth Disposals Commission [1951] HCA 79; (1951) 84 CLR 377 at 411,
414.
[75] Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 83, 89, 137. See, eg, L Albert (1949)
178 F 2d 182 at 189-190; Anglia Television Ltd v Reed [1972] 1
QB 60; Omak Maritime Ltd [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 53-54 [33]- [34];
Yam Seng Pte Ltd v International Trade Corporation Ltd [2013] EWHC 111; [2013] 1 Lloyd's
Rep 526 at 553 [188]- [189].
[76] Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 89, 126; L Albert (1949) 178 F 2d 182 at 189.
See also Omak Maritime Ltd [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 51 [22].
[77] McRae [1951] HCA 79; (1951) 84 CLR 377
at 414-415; Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 86, 89, 106-108, 126-127,
154. See also L Albert (1949) 178 F 2d 182 at 189.
[78] Holt (1909) 72 A 301 at
306. See also Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 89.
[79] See Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 87-90, 126; Berry [2020] HCA 27; (2020) 271 CLR 151 at 169
[29].
[80] See, eg, Amann
Aviation [1991] HCA 54; (1991) 174 CLR 64 at 82, 108, 134, 162-163. See also
TC Industrial Plant Pty Ltd v Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180
CLR 130 at 142; Omak Maritime Ltd [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 55
[42]; Yam Seng [2013] EWHC 111; [2013] 1 Lloyd's Rep 526 at 552 [186].
cf American Law Institute, Restatement (Second) of Contracts (1981),
§344, §347, §348.
[81] Amann Aviation
[1991] HCA 54; (1991) 174 CLR 64 at 82, 108, 134, 162-163.
[82] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 85, 108, 136-137, 155, 162.
[83] cf United Australia Ltd v
Barclays Bank Ltd [1941] AC 1 at 18‑19; Sargent v ASL
Developments Ltd [1974] HCA 40; (1974) 131 CLR 634 at 641-642.
[84] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 79, 127-128.
[85] McRae [1951] HCA 79; (1951) 84 CLR 377
at 412-413; Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 84, 86, 88-89, 104-105,
106, 107, 127, 129, 139-140, 154, 158, 161, 166-167. See also Anglia
Television Ltd [1972] 1 QB 60 at 63.
[86] See, eg, McRae [1951] HCA 79; (1951) 84
CLR 377 at 416.
[87] See, eg, McRae [1951] HCA 79; (1951) 84
CLR 377 at 412-413; Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at
86, 88, 89, 104-106, 107, 127, 129, 139, 140, 154, 158. cf Fuller and Perdue,
"The Reliance Interest in Contract Damages: 1" (1936)
46 Yale Law Journal
52 at 73-74, 78, 79.
[88] See, eg[1991] HCA 54; , (1991) 174 CLR 64 at
126, 135.
[89] [1951] HCA 79; (1951) 84 CLR 377.
[90] McRae [1951] HCA 79; (1951) 84 CLR 377
at 381-382, 414-415.
[91] McRae [1951] HCA 79; (1951) 84 CLR 377
at 413.
[92] L Albert (1949) 178 F 2d
182 at 189.
[93] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 86.
[94] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 89, 105-108, 156. See also Omak Maritime Ltd [2010] EWHC 2026; [2011] 1
Lloyd's Rep 47 at 51 [22], 52-53 [33], 55 [47]; Yam Seng [2013] EWHC 111; [2013]
1 Lloyd's Rep 526 at 553 [188].
[95] L Albert (1949) 178 F 2d
182 at 189.
[96] McRae [1951] HCA 79; (1951) 84 CLR 377
at 412; Amann Aviation [1991] HCA 54; (1991) 174 CLR 64 at 86, 89, 105-108, 154, 157.
See also Omak Maritime Ltd [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 51 [22], 52-53
[33], 55 [47]; Yam Seng [2013] EWHC 111; [2013] 1 Lloyd's Rep 526 at 553 [188].
[97] See [50] and [56] above.
[98] Amann Aviation [1991] HCA 54; (1991)
174 CLR 64 at 88.
[99] See, eg, Chaplin v Hicks
[1911] UKLawRpKQB 104; [1911] 2 KB 786.
[100] Bellgrove v Eldridge
[1954] HCA 36; (1954) 90 CLR 613 at 617; White Arrow Express Ltd v Lamey's Distribution
Ltd [1995] CLC 1251 at 1254; Peel, "Excluding Liability for Wasted
Expenditure: CIS v IBM" [2021] Lloyd's Maritime and Commercial Law
Quarterly 425 at 429-430.
[101] [1991] HCA 54; (1991) 174 CLR 64 at 87-89,
94, 106, 126-128, 131, 142, 156. See also Berry v CCL Secure Pty Ltd
[2020] HCA 27; (2020) 271 CLR 151 at 169-170 [29].
[102] Environmental Planning
and Assessment Act 1979 (NSW), s 72 (as it was then).
[103] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [255].
[104] A claim under s 21(1)
of the Australian Consumer Law of unconscionable conduct by the Council
was dismissed by the primary judge and no appeal was brought from that
finding.
[105] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [207].
[106] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [211].
[107] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [219].
[108] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [241].
[109] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [223].
[110] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 498 [108].
[111] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 485-488 [64]- [73], 495
[97].
[112] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 495-496 [98].
[113] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 499 [109].
[114] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 509 [134].
[115] (1854) 9 Ex 341 [156 ER
145].
[116] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 514-515 [149].
[117] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 487-488 [72]- [73], 517
[161].
[118] See also Jackson v Royal
Bank of Scotland Plc [2005] 1 WLR 377 at 390-391 [46]-[47]; [2005] UKHL 3; [2005] 2 All ER
71 at 83-84; European Bank Ltd v Evans [2010] HCA 6; (2010) 240 CLR 432 at 438
[13].
[119]
Chitty, A Practical Treatise on The Law of
Contracts (1826) at 5-6.
[120] Ibbetson, A Historical
Introduction to the Law of Obligations (1999) at 213, 229.
[121] Lobban, "Contractual
Remedies", in Cornish et al (eds), The Oxford History of the Laws of
England (2010), vol 12, 522 at 534, 543.
[122] Alder v Keighley
[1846] EngR 340; (1846) 15 M & W 117 at 120 [153 ER 785 at 786].
[123] Wenham v Ella [1972] HCA 43; (1972)
127 CLR 454 at 460, 471; The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991)
174 CLR 64 at 80, 99, 134, 161; Baltic Shipping Co v Dillon [1993] HCA 4; (1993)
176 CLR 344 at 372; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
[2009] HCA 8; (2009) 236 CLR 272 at 286 [13]; European Bank Ltd v Evans [2010] HCA 6; (2010) 240
CLR 432 at 437-438 [11]; Clark v Macourt [2013] HCA 56; (2013) 253 CLR 1 at 6 [7], 11
[26], 19 [60], 30 [106].
[124] Robinson v Harman
[1848] EngR 135; (1848) 1 Ex 850 at 855 [154 ER 363 at 365].
[125] Sutherland Shire Council
v Heyman [1985] HCA 41; (1985) 157 CLR 424 at 490-491, quoting Darley Main Colliery Co v
Mitchell [1886] UKLawRpAC 2; (1886) 11 App Cas 127 at 132-133.
[126] Carter, Contract Law in
Australia, 8th ed (2023) at 801-802 [35-11].
[127] TC Industrial Plant Pty
Ltd v Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180 CLR 130 at 138-142; The
Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 82, 85, 108, 155,
162-163.
[128] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 82; Moore v Scenic Tours Pty Ltd
[2020] HCA 17; (2020) 268 CLR 326 at 348 [63].
[129] Barnett, Damages for
Breach of Contract, 2nd ed (2022) at 81 [3-007]. See also
Barnett, "Great Expectations: a Dissection of Expectation Damages in Contract in
Australia and England"
(2016) 33 Journal of Contract Law 163 at 180.
[130] Omak Maritime Ltd v
Mamola Challenger Shipping Co [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at 55 [42]. See
also Yam Seng Pte Ltd v International Trade Corporation Ltd [2013] EWHC 111; [2013] 1
Lloyd's Rep 526 at 552 [186].
[131] Burrows, Remedies for
Torts, Breach of Contract, and Equitable Wrongs, 4th ed (2019) at 75. See
also at 79.
[132] Arsalan v Rixon
[2021] HCA 40; (2021) 274 CLR 606 at 624-625 [32]. See also TC Industrial Plant Pty Ltd
v Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180 CLR 130 at 138. As to remoteness,
compare Armstead v Royal & Sun Alliance Insurance Co Ltd [2024] UKSC 6; [2024] 2 WLR
632 at 650 [62]- [63].
[133] (1949) 178 F 2d 182.
[134] [1991] HCA 54; (1991) 174 CLR 64.
[135] American Law Institute,
Restatement (First) of Contracts (1932).
[136] See [120]-[121] above.
[137] American Law Institute,
Restatement (First) of Contracts (1932), §329, comment a.
[138] American Law Institute,
Restatement (First) of Contracts (1932), §333.
[139] American Law Institute,
Restatement (First) of Contracts (1932), §333, comment b.
[140] American Law Institute,
Restatement (Second) of Contracts (1981).
[141] American Law Institute,
Restatement (Second) of Contracts (1981), §344.
[142] American Law Institute,
Restatement (Second) of Contracts (1981), §347 and comment a.
[143] American Law Institute,
Restatement (Second) of Contracts (1981), §349. See also comment
a.
[144] American Law Institute,
Restatement (Second) of Contracts (1981), §344, Reporter's Note,
citing Fuller and Perdue, "The Reliance Interest in Contract Damages: 1" (1936)
46 Yale Law Journal 52 and Fuller and Perdue, "The Reliance Interest in
Contract Damages: 2" (1937) 46 Yale Law Journal 373. See also Craswell,
"Against Fuller and Perdue" (2000) 67 University of Chicago Law Review 99
at 105-106.
[145] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 52-54. See also Sullivan v O'Connor (1973) 296 NE 2d 183 at 189.
[146] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 56.
[147] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 61-62.
[148] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 77-79.
[149] See above at [116].
[150] Friedmann, "A Comment on
Fuller and Perdue, the Reliance Interest in Contract Damages" (2001) 1 Issues
in Legal Scholarship, Article 3 at 2. See also Zhu v Treasurer of New
South Wales [2004] HCA 56; (2004) 218 CLR 530 at 574-575 [128].
[151] Skelton v Collins
[1966] HCA 14; (1966) 115 CLR 94 at 99.
[152] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 137, quoting McGregor on
Damages, 15th ed (1988) at 1134 [1779] fn 2.
[153] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 142, 156, 165. See also Berry v CCL
Secure Pty Ltd [2020] HCA 27; (2020) 271 CLR 151 at 169 [29], referring to an "evidentiary
burden".
[154] Williams, "Burdens and
Standards in Civil Litigation" [2003] SydLawRw 9; (2003) 25 Sydney Law Review 165 at
168.
[155] See
The Commonwealth v Amann Aviation Pty Ltd
[1991] HCA 54; (1991) 174 CLR 64 at 165-166; Amann Aviation Pty Ltd v The
Commonwealth [1990] FCA 55; (1990) 22 FCR 527 at 571.
[156] McRae v Commonwealth
Disposals Commission [1951] HCA 79; (1951) 84 CLR 377 at 414; Amann Aviation Pty Ltd v
The Commonwealth [1990] FCA 55; (1990) 22 FCR 527 at 571.
[157] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 87, 126; Berry v CCL Secure Pty Ltd
[2020] HCA 27; (2020) 271 CLR 151 at 169-170 [29].
[158] Masson v Parsons
[2019] HCA 21; (2019) 266 CLR 554 at 575 [32], referring to Thayer, "Presumptions and the Law
of Evidence" (1889) 3 Harvard Law Review 141 and Thayer, A Preliminary
Treatise on Evidence at the Common Law (1898), ch 8.
[159] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 81, 87.
[160] (1774) 1 Cowper 63 at 65 [1774] EngR 2; [98
ER 969 at 970].
[161] (1722) 1 Strange 505 [1722] EWHC KB J94; [93 ER
664].
[162] [1931] USSC 49; (1931) 282 US 555 at
563.
[163] See Allen v Tobias
[1958] HCA 13; (1958) 98 CLR 367 at 375.
[164] Murphy v Overton
Investments Pty Ltd [2004] HCA 3; (2004) 216 CLR 388 at 416 [74]. See also LJP
Investments Pty Ltd v Howard Chia Investments Pty Ltd (1990) 24 NSWLR 499 at
508; Houghton v Immer (No 155) Pty Ltd [1997] NSWSC 608; (1997) 44 NSWLR 46 at
59.
[165] [1874] UKLawRpCh 24; (1874) LR 9 Ch App 279 at
285-286.
[166] [1874] UKLawRpCh 24; (1874) LR 9 Ch App 279 at
286.
[167] (1949) 178 F 2d 182.
[168] (1949) 178 F 2d 182 at
189.
[169] (1949) 178 F 2d 182 at
189.
[170] (1949) 178 F 2d 182 at
189.
[171] [1951] HCA 79; (1951) 84 CLR 377.
[172] [1951] HCA 79; (1951) 84 CLR 377 at
419.
[173] [1951] HCA 79; (1951) 84 CLR 377 at
411.
[174] [1951] HCA 79; (1951) 84 CLR 377 at
414.
[175] See also Ng, "The Onus of
Proof in a Claim for Reliance Damages for Breach of Contract" (2006) 22
Journal of Contract Law 139 at 153; Winterton, "Commonwealth v Amann
Aviation Pty Ltd 25 Years On: Re-examining the Problem of Pre-breach Expenditure
in
Contract Law", in Degeling, Edelman and Goudkamp (eds), Contract in
Commercial Law (2016) 333 at 338.
[176] Mummery v Irvings Pty Ltd
[1956] HCA 45; (1956) 96 CLR 99 at 120-121.
[177] Schellenberg v Tunnel
Holdings Pty Ltd [2000] HCA 18; (2000) 200 CLR 121 at 132-133 [22]. See also at 163
[110].
[178] Yam Seng Pte Ltd v
International Trade Corporation Ltd [2013] EWHC 111; [2013] 1 Lloyd's Rep 526 at 553 [188].
See also Omak Maritime Ltd v Mamola Challenger Shipping Co [2010] EWHC 2026; [2011]
1 Lloyd's Rep 47 at 50-57 [11]- [57].
[179] Wilson v Northampton and
Banbury Junction Railway Co [1874] UKLawRpCh 24; (1874) LR 9 Ch App 279 at 286.
[180] Browning v Brachers
[2005] EWCA Civ 753 at [210].
[181] Porton Capital Technology
Funds v 3M UK Holdings Ltd [2011] EWHC 2895 (Comm) at [349].
[182] Kramer, "Proving Contract
Damages", in Virgo and Worthington (eds), Commercial Remedies: Resolving
Controversies (2017) 228 at 232.
[183] [1963] HCA 57; (1963) 180 CLR 130.
[184] [1963] HCA 57; (1963) 180 CLR 130 at
142.
[185] [1991] HCA 54; (1991) 174 CLR 64.
[186] [1991] HCA 54; (1991) 174 CLR 64 at 74.
[187] [1991] HCA 54; (1991) 174 CLR 64 at 80, 98,
148.
[188] [1991] HCA 54; (1991) 174 CLR 64 at 85,
107-108, 155.
[189] [1991] HCA 54; (1991) 174 CLR 64 at 83.
[190] [1991] HCA 54; (1991) 174 CLR 64 at 86,
115, 154.
[191] [1991] HCA 54; (1991) 174 CLR 64 at 86,
109, 113, 153, 155-156.
[192] [1991] HCA 54; (1991) 174 CLR 64 at 86. See
also at 105.
[193] [1991] HCA 54; (1991) 174 CLR 64 at 89.
[194] [1991] HCA 54; (1991) 174 CLR 64 at
154.
[195] [1991] HCA 54; (1991) 174 CLR 64 at 87,
105-106, 156.
[196] [1991] HCA 54; (1991) 174 CLR 64 at 87,
105, citing L Albert & Son v Armstrong Rubber Co (1949) 178 F 2d 182
at 189.
[197] [1991] HCA 54; (1991) 174 CLR 64 at 97-98.
See also at 114, 158.
[198] [1991] HCA 54; (1991) 174 CLR 64 at
115.
[199] [1991] HCA 54; (1991) 174 CLR 64 at
86-90.
[200] [1991] HCA 54; (1991) 174 CLR 64 at 106,
107-108.
[201] [1991] HCA 54; (1991) 174 CLR 64 at
108.
[202] [1991] HCA 54; (1991) 174 CLR 64 at 156.
See also at 142. See also Berry v CCL Secure Pty Ltd [2020] HCA 27; (2020) 271 CLR 151
at 169-170 [29], 188 [65]-[66].
[203] [1991] HCA 54; (1991) 174 CLR 64 at 81. See
also at 156.
[204] [1991] HCA 54; (1991) 174 CLR 64 at 87.
[205] [1991] HCA 54; (1991) 174 CLR 64 at
105.
[206] [2020] HCA 27; (2020) 271 CLR 151 at
169-170 [29].
[207] (1722) 1 Strange 505 at 505
[1722] EWHC KB J94; [93 ER 664 at 664].
[208] Browning v Brachers
[2005] EWCA Civ 753 at [210]. See also Hickman v Blake Lapthorn
[2006] PNLR 371 at 391 [62], 392 [73]; The Law Debenture Trust
Corporation Plc v Elektrim SA [2009] EWHC 1801 (Ch) at [165]; Double G
Communications Ltd v News Group International Ltd [2011] EWHC 961 (QB) at
[5]; Porton Capital Technology Funds v 3M UK Holdings Ltd [2011] EWHC
2895 (Comm) at [239]; University of Wales v London College of Business
Ltd [2016] EWHC 888 (QB) at [9]; Marathon Asset Management LLP v Seddon
[2017] EWHC 300; [2017] ICR 791 at 834 [165]; Redbourn Group Ltd v Fairgate Developments
Ltd (2018) 177 ConLR 207 at 222 [59].
[209] Yam Seng Pte Ltd v
International Trade Corporation Ltd [2013] EWHC 111; [2013] 1 Lloyd's Rep 526 at 552
[186].
[210] [2010] EWHC 2026; [2011] 1 Lloyd's Rep
47.
[211] [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at
56-57 [55].
[212] [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at
56 [52]- [53].
[213] [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at
52-53 [33], citing Hutchison J in CCC Films (London) Ltd v Impact
Quadrant Films Ltd [1985] QB 16 at 40.
[214] [2010] EWHC 2026; [2011] 1 Lloyd's Rep 47 at
55-56 [46]- [47], [49].
[215] [2013] EWHC 111; [2013] 1 Lloyd's Rep 526.
[216] [2013] EWHC 111; [2013] 1 Lloyd's Rep 526 at
553 [188].
[217] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082
at 1095 [42], 1096 [45].
[218] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082
at 1090 [24], 1091 [26].
[219] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082
at 1103 [69], [71],
[220] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082
at 1095 [40], citing Anglia Television Ltd v Reed [1972] 1 QB 60 at
63-64.
[221] [2022] EWCA Civ 440; [2022] 2 All ER (Comm) 1082
at 1103 [70].
[222] Badenach v Calvert
[2016] HCA 18; (2016) 257 CLR 440 at 454 [40]. See also Sellars v Adelaide Petroleum NL
(1994) 179 CLR 332 at 364-365, 368; Badenach v Calvert [2016] HCA 18; (2016) 257 CLR
440 at 467 [98].
[223] Sellars v Adelaide
Petroleum NL (1994) 179 CLR 332 at 364; Tabet v Gett [2010] HCA 12; (2010) 240 CLR
537 at 560 [49]; Badenach v Calvert [2016] HCA 18; (2016) 257 CLR 440 at 454 [39], 467
[98].
[224] Berry v CCL Secure Pty
Ltd [2020] HCA 27; (2020) 271 CLR 151 at 170 [30], referring to "either of the presumptions
considered in Amann Aviation".
[225] Berry v CCL Secure Pty
Ltd [2020] HCA 27; (2020) 271 CLR 151 at 170 [29].
[226] [1991] HCA 54; (1991) 174 CLR 64 at 88.
[227] [1991] HCA 54; (1991) 174 CLR 64 at 130,
157.
[228] Compare The Commonwealth
v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 88, citing Aldwell v Bundey
[1876] SALawRp 20; (1876) 10 SALR 118.
[229] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 73-74, 78.
[230] Fuller and Perdue, "The
Reliance Interest in Contract Damages: 1" (1936) 46 Yale Law Journal 52
at 79; Fuller and Perdue, "The Reliance Interest in Contract Damages: 2" (1937)
46 Yale Law Journal 373 at 374 fn 78.
[231] American Law Institute,
Restatement (Second) of Contracts (1981), §349, comment a and
illustration 4.
[232] (1949) 178
F 2d 182 at 191.
[233] [1991] HCA 54; (1991) 174 CLR 64 at 97-98,
111-112, 158.
[234] [2020] HCA 27; (2020) 271 CLR 151 at 170
[29].
[235] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 113, cited in Berry v CCL Secure
Pty Ltd [2020] HCA 27; (2020) 271 CLR 151 at 170 [29] fn 52.
[236] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [258].
[237] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 471 [24].
[238] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 508 [132].
[239] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [241].
[240] 123 259 932 Pty Ltd v
Cessnock City Council [No 2] [2021] NSWSC 1329 at [255], [257]-[258].
[241] [1848] EngR 135; (1848) 1 Ex 850 at 855 [154
ER 363 at 365].
[242] (1854) 9 Ex 341 at 354 [156
ER 145 at 151].
[243] McRae v Commonwealth
Disposals Commission [1951] HCA 79; (1951) 84 CLR 377 at 414.
[244] TC Industrial Plant Pty
Ltd v Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180 CLR 130 at 141.
[245] [1951] HCA 79; (1951) 84 CLR 377.
[246] [1963] HCA 57; (1963) 180 CLR 130.
[247] The Commonwealth v Amann
Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64 at 89, 119, 126, 154.
[248] Section 23G(d) of the
Conveyancing Act 1919 (NSW) provides for the registration of a lease of
part of an existing lot for a period that does not exceed five years. Otherwise,
s 23F applies, the effect of which is that a lease for a period greater
than five years may be refused to be registered.
[249] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 498 [108].
[250] Conveyancing Act 1919
(NSW), ss 23F, 23G(d).
[251] McRae v Commonwealth
Disposals Commission [1951] HCA 79; (1951) 84 CLR 377 at 414.
[252] [1951] HCA 79; (1951) 84 CLR 377 at
414.
[253] [1991] HCA 54; (1991) 174 CLR 64.
[254] [1991] HCA 54; (1991) 174 CLR 64 at 89.
[255] [1991] HCA 54; (1991) 174 CLR 64 at 90.
[256] [1991] HCA 54; (1991) 174 CLR 64 at 89.
[257] [1991] HCA 54; (1991) 174 CLR 64 at 88.
[258] [1991] HCA 54; (1991) 174 CLR 64 at
104.
[259] [1991] HCA 54; (1991) 174 CLR 64 at
106.
[260] [1991] HCA 54; (1991) 174 CLR 64 at 119,
quoting Takaro Properties Ltd v Rowling [1986] NZCA 27; [1986] 1 NZLR 22 at 69.
[261] [1991] HCA 54; (1991) 174 CLR 64 at
126.
[262] [1991] HCA 54; (1991) 174 CLR 64 at
126‑127.
[263] [1848] EngR 135; (1848) 1 Ex 850 at 855 [154
ER 363 at 365].
[264] [1991] HCA 54; (1991) 174 CLR 64 at
135.
[265] [1991] HCA 54; (1991) 174 CLR 64 at
136.
[266] [1991] HCA 54; (1991) 174 CLR 64 at
137.
[267] [1991] HCA 54; (1991) 174 CLR 64 at
138.
[268] [1991] HCA 54; (1991) 174 CLR 64 at
142‑143.
[269] [1991] HCA 54; (1991) 174 CLR 64 at 154.
[270] [1991] HCA 54; (1991) 174 CLR 64 at
155‑156 (footnote omitted).
[271] [1991] HCA 54; (1991) 174 CLR 64 at
156.
[272] [1991] HCA 54; (1991) 174 CLR 64 at
156.
[273] [1991] HCA 54; (1991) 174 CLR 64 at
157.
[274] [1991] HCA 54; (1991) 174 CLR 64 at
166.
[275] [1991] HCA 54; (1991) 174 CLR 64 at
166‑167.
[276] [2020] HCA 27; (2020) 271 CLR 151.
[277] [2020] HCA 27; (2020) 271 CLR 151 at 169
[29] (footnotes omitted).
[278] [2020] HCA 27; (2020) 271 CLR 151 at 170
[29].
[279] [2020] HCA 27; (2020) 271 CLR 151 at 170
[30].
[280] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 487‑488 [73].
[281] (1854) 9 Ex 341 [156 ER
145].
[282] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 505 [126].
[283] 123 259 932 Pty Ltd v
Cessnock City Council [2023] NSWCA 21; (2023) 110 NSWLR 464 at 507 [131].