A payment claim under the SOP Act is not invalid merely because it may be characterised as a claim for damages or restitution rather than for construction work; there is no implied precondition requiring the claim to have the objective character of being 'for' construction work, and a respondent who fails to serve a payment schedule effectively forfeits the right to resist the claim on this basis.