Black Sheep Building Pty Ltd v A J Portelli Medical Pty Ltd atf A J Portelli Medical Trust [2025] NSWSC 1472 — Building And Construction — Barrister AI
Black Sheep Building Pty Ltd v A J Portelli Medical Pty Ltd atf A J Portelli Medical Trust
payment claims served but no payment schedules provided
claim for unpaid portion of payment claims under s 15(2)(a)(ii) of the Building and Construction Industry Security of Payment Act 1999 (NSW)
application for summary judgment
Quick Take
1A payment claim that expressly states it is made under SOPA engages the statutory scheme even where the construction contract provides its own payment claim and quantity surveyor assessment process; the two regimes operate concurrently and the respondent must still serve a payment schedule within the statutory timeframe.
2High physical support accommodation comprising ensuite bedrooms with shared kitchen, living, laundry and outdoor areas — designed for persons with disability under NDIS standards and subject to centralised management — falls within the exception in cl 3(3)(d) of Schedule 1 to the Home Building Act 1989 (NSW) for accommodation specially designed for persons with disability, and does not constitute 'self-contained units' within the carve-out to that exception.
3Interest under s 11(2) SOPA on unpaid progress payments is recoverable as part of a summary judgment application for the unpaid amount of a payment claim; a separate proceeding is not required.
Case Details
Citation[2025] NSWSC 1472
CourtNSWSC
JurisdictionNew South Wales
Unlock so much more with Barrister AI
The full text is available to signed-in members, including the 1 later case that cites this judgment.
1 of the 1 citing case carries a classified treatment. How each court treated it is available to signed-in members.