The applicant owner succeeded in full against the respondent builder, who did not appear, and was awarded $487,839.35 comprising unrecovered overpayments ($31,217.11), cost-of-completion damages ($322,197.10), interest ($109,425.14), and costs ($25,000). The Tribunal applied the [name withheld] v [name withheld] cost-of-rectification measure as the primary damages assessment, accepting a replacement builder's quotation as evidence of the increased completion cost over the original contract price. The Tribunal noted, following [name withheld] v [name withheld] and Westpoint Management Ltd v Chocolate Factory Apartments Ltd, that the applicant's present inability to engage an alternative builder did not of itself displace the prima facie [name withheld] measure, though it expressed some reservation on the point. Interest was awarded at the default 10% per annum rate under s 54 of the Queensland Building and Construction Commission Regulation 2018 (Qld).