1Where contracting parties informally agree to suspend contractual time limits and expert determination in favour of negotiated resolution, a notice given after remediation work has begun will not forfeit the contractual right to reimbursement, and a late objection is not rendered nugatory. On the facts, this occurred from 4 June 2015.
2Contractual contamination notices that are expressly cumulative are to be read with earlier notices and adopted reports, so that statements of health risk and necessity for Master Plan uses made in prior notices may satisfy the content requirements of later notices.
3Probabilistic cost modelling is admissible but, being dependent on assumptions, does not on its own produce the actual persuasion required to prove that any particular level of cost was incurred. Where actual loss is shown but precise proof is impracticable, quantum is to be fixed by informed estimation grounded on findings of material fact.