41
In forceMultiple or part building commencement notice
Part 3Building work
Division 3.4Building commencement notices and building work signs
41 Multiple or part building commencement notice
(1)
Two or more building commencement notices for the same building work may be in force at the same time.
(2)
A building commencement notice continues to operate for building work even if the building work being done is only part of the building work for which the commencement notice was issued.
This Act’s bill:Explanatory statementSecond reading speech