Quarterly reports by ACT electricity distributor
21 Quarterly reports by ACT electricity distributor
This section applies if, during a quarter, a large renewable energy generator in relation to which a FIT entitlement is granted is connected to the interconnected national electricity system.
The ACT electricity distributor must give the Minister a report for the quarter in relation to the generator.
The report must include the following:
if the generator was first connected to the ACT electricity distribution system during the quarter—the cost of connecting the generator to the ACT electricity distribution system, including any network augmentation that was required to facilitate the connection;
if the generator is connected to the ACT electricity distribution system—the cost of maintaining the connection of the generator to the ACT electricity distribution system and maintaining any network augmentation required to facilitate the connection;
the quantity of eligible electricity supplied by the generator to the interconnected national electricity system in a trading interval, and the spot price value for the electricity in each interval;
the FiT support payment paid by the ACT electricity distributor during the quarter to the holder of the FiT entitlement in relation to the generator.
The ACT electricity distributor must give the Minister the report for a quarter before the end of the next quarter.
The Minister must, within 3 months after receiving the report, make the report publicly available.
Example—publicly available published on a website operated by the administrative unit responsible for this Act
In this section:
trading interval—see the national electricity rules, chapter 10 (Glossary).
This Act’s bill:Explanatory statementSecond reading speech
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.