Barrister AI
All legislation
ACTAct
In force
This is the latest official compilation.Check the official source →
s 33

Variation of approval

In force
Part 5Assessment entities

33 Variation of approval

(1)

On written application by an assessment entity, the director‑general may vary the approval of the entity if the director‑general—

(a)

has considered any reasons provided by the entity in its application to vary the approval; and

(b)

is satisfied that it is appropriate to vary the approval.

(2)

The director‑general may vary the approval of an assessment entity on the director‑general’s own initiative if the director‑general—

(a)

has given the entity a written notice that—

(i)

states how the director‑general proposes to vary the approval; and

(ii)

states the reason the director‑general proposes to vary the approval; and

(iii)

tells the entity that it may give a written response to the director‑general about the matters stated in the notice not later than 28 days after the entity receives the notice; and

(b)

has considered any response given in accordance with paragraph (a) (iii); and

(c)

is satisfied that it is appropriate to vary the approval.

(3)

A variation of an approval takes effect on the day stated in the variation.

(4)

A variation of an approval is a notifiable instrument.

(5)

In this section:

vary, in relation to an approval—

(a)

includes—

(i)

varying the term of the approval; and

(ii)

adding, amending or removing a condition of the approval; but

(b)

does not include amending the approval to authorise the assessment entity to conduct an assessment scheme for an additional area of engineering.

Research tools for this sectionPro

The statute text is free to read above. View Pro plans to unlock the case-law research tools for each provision.

Professional Engineers Act 2023 s 33 — Variation of approval (Australian Capital Territory) — Barrister AI