WHS management plan—review
311 WHS management plan—review
The principal contractor for a construction project must review and as necessary revise the WHS management plan to ensure that it remains up‑to‑date.
Maximum penalty: tier G monetary penalty.
Note Strict liability applies to each physical element of each offence under this regulation, unless otherwise stated (see s 6A).
The principal contractor for a construction project must ensure, so far as is reasonably practicable, that each person carrying out construction work in connection with the project is made aware of any revision to the WHS management plan.
Maximum penalty: tier G monetary penalty.
Note Strict liability applies to each physical element of each offence under this regulation, unless otherwise stated (see s 6A).
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.