Finalising draft order
536QN Finalising draft order
The FWC may make any changes it thinks appropriate to a draft road transport contractual chain order as proposed to be varied.
If changes proposed to be made under subsection (1) are significant, the FWC must:
decide not to vary the road transport contractual chain order based on the draft; and
publish a subsequent notice of intent under paragraph 536QL(1)(a) in relation to the revised draft road transport contractual chain order, and publish the revised draft; and
follow the process set out in section 536QM (as affected by subsection (3) or (4) of this section) in relation to the revised draft road transport contractual chain order.
For the purposes of paragraph (2)(c), the period of consultation under section 536QM in relation to the revised draft road transport contractual chain order is to be the period of at least 12 months starting when the subsequent notice of intent and the revised draft required by paragraph (2)(b) of this section were published.
However, the FWC may reduce that 12‑month period to another period that the FWC considers is reasonable if the order is a time‑sensitive road transport contractual chain order.