Nil baselines
1 Nil baselines
1.1 The 1997 eligible renewable power baseline for a power station is nil if:
before 1 January 1997, the power station generated electricity using an energy source that was not an eligible energy source and, on or after that date, the power station began generating electricity using an eligible energy source; or
the power station began generating electricity for the first time on or after 1 January 1997, and all or part of the electricity was generated using an eligible energy source; or
the power station was built after 1 January 1997 to take advantage of a change in water flow as a result of an action or policy of the Commonwealth Government to divert water from one power station to another.
This Act’s bill:Explanatory statement
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.