Crown building work—commenced
4B Crown building work—commenced
This clause applies to Crown building work if—
it is carried out before 1 August 2021, and
the Crown building project to which it relates has not been completed by that day.
The following requirements of the Act do not apply to the Crown building work, or a design in relation to the Crown building work, to which this clause applies—
provisions requiring regulated designs to be prepared for the Crown building work, including requirements for compliance declarations,
provisions requiring a person to be registered to carry out the Crown building work,
provisions requiring a building compliance declaration to be prepared for the Crown building work.
The building practitioner for the Crown building work must provide copies of all designs relied on to carry out the Crown building work—
to the Secretary in the approved way, and
before the completion of the Crown building project to which the Crown building work relates.
Maximum penalty—1,500 penalty units for a body corporate or 500 penalty units for an individual.