Reinstatement of land
20 Reinstatement of land
The promoter for a motor race must do the following work unless otherwise authorised by the government coordinating agency—
remove any rubbish from the event area,
for land, including fixtures, damaged or otherwise affected by the activities of the promoter, including the conduct of the motor race, associated events and ancillary activities—
repair all damage, and
reinstate the land as far as is practicable to the condition it was in before the activities.
The work must be completed within a reasonable time after the event period for the motor race.
If the race promoter fails to carry out the work within the time, the government coordinating agency for the motor race may cause the work to be carried out.
The government coordinating agency may recover the cost of carrying out the work from the promoter as a debt in a court of competent jurisdiction.
A document signed by the head of the government coordinating agency certifying the cost of carrying out the work is admissible in the proceedings and is evidence of the cost.