1Name of Regulation
This Regulation is the Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2019.
This Regulation is the Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2019.
This Regulation commences on 1 September 2019 and is required to be published on the NSW legislation website.
Note.
This Regulation replaces the Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2014, which is repealed on 1 September 2019 by section 10(2) of the Subordinate Legislation Act 1989.
In this Regulation—
commission, in relation to a storage system or leak detection system, means to bring the system into use for the first time following its installation, modification or repair.
current “as-built” drawings, in relation to a storage system, means drawings that depict the current configuration of the system in relation to the storage site.
decommission, in relation to a storage system, means to remove the system or to render the system permanently unusable.
Note.
Other legislation may require the cessation of the use of certain storage systems.
duly qualified person, in relation to any activity, means a person who has competence and experience in relation to that activity that is—
recognised by a peak body in the relevant industry as appropriate for that activity, or
recognised generally in the relevant industry as appropriate for that activity.
EPA guideline means a guideline in force under clause 30.
fuel system operation plan means documentation for a storage system that contains the procedures and other information required by clause 18.
installation of a storage system means the original installation of the system on the storage site, and includes any work in the vicinity of the storage site necessary for the installation, and anything done to the system before it is commissioned.
leak, in relation to a storage system, means any loss of petroleum from the system because it is not providing full and continuous containment of petroleum.
leak detection system means a system designed to detect contamination by, or failure of, a storage system in the event of a failure in loss monitoring systems that consists of either—
groundwater monitoring wells, or
an alternative leak detection system.
loss monitoring system for a storage system means the system referred to in clause 18(2)(a) as included in the fuel system operation plan for the system.
modification of a storage system includes any upgrade, extension, alteration or replacement of the system, or any component of the system, but does not include—
anything done to the system before it is first commissioned, or
anything done to the system after it is decommissioned, or
anything done to the system as part of routine maintenance (including any repairs to the system that are done in the course of regular scheduled upkeep of the system), or
anything done to the system before 1 June 2008, or
anything done to a storage site, or any building on a storage site, that does not directly affect the system.
modified storage system means a storage system that has been modified.
person responsible for a storage system—see clause 4.
petroleum means any fuel that consists predominantly of a mixture of hydrocarbons, whether or not the fuel includes additives (such as ethanol), and includes used oil.
Note.
Clause 5 provides that this Regulation does not apply to a liquefied petroleum gas storage system.
significant modification of a storage system means any modification to the system that results in—
the replacement of the whole of the system, or
the replacement of a half or more of the tanks in the system.
storage site of a storage system means the premises (or the part of the premises) in or on which the system is situated.
storage system means a system of tanks, pipes, valves and other equipment that is designed—
to contain petroleum, or
to control the passage of petroleum into, out of, through or within the system,
and includes any structure through which petroleum routinely passes from one part of the system to another.
the Act means the Protection of the Environment Operations Act 1997.
use a storage system includes allow petroleum to remain in the system.
Note.
The Act and the Interpretation Act 1987 contain definitions and other provisions that affect the interpretation and application of this Regulation.
For example, appropriate regulatory authority is defined in section 6 of the Act. When this Regulation commenced, the EPA was the appropriate regulatory authority for matters arising under this Regulation in relation to some existing notices, directions or requirements: see clause 91 of the Protection of the Environment Operations (General) Regulation 2009. Otherwise the default position in section 6 of the Act had effect.
Notes included in this Regulation do not form part of this Regulation.
In this Regulation, person responsible for a storage system means—
if the storage system has not yet been commissioned—the person who has management and control of the storage system, or
if the storage system is in use—the person who has management and control of the storage system, or
if the storage system is no longer in use but has not been decommissioned—
the person who had management and control of the storage system immediately before the storage system ceased to be used, or
if that person cannot be located—the person who owns the land on which the storage system is located.
This Regulation applies to all storage systems other than the following—
a storage system whose tanks are situated wholly above ground, together with any associated pipes, valves and other equipment (whether situated above or below ground),
a sump, separator, stormwater or wastewater collection system, catchment basin, pit, septic tank or other like structure (unless petroleum routinely passes through the structure from one part of a storage system to another),
a bunded tank situated below ground level but not in the ground (such as in a basement, cellar or tunnel),
a liquefied petroleum gas storage system.
The person responsible for a storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the system has been designed by a duly qualified person, and
the person by whom the system has been designed has provided the person responsible for the system with—
a list of the industry standards that have been followed in connection with the design of the system, and
a copy of the design specifications for the system.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the system has been installed by a duly qualified person, and
the person by whom the system has been installed has provided the person responsible for the system with—
a list of the industry standards that have been followed in connection with the installation of the system, and
a copy of the installation specifications for the system, and
current “as-built” drawings for the system.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the system includes the equipment required by AS 4897–2008: The design, installation and operation of underground petroleum storage systems, as in force from time to time, and
a leak detection system is installed on the storage site in accordance with Part 3.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
an equipment integrity test of the system has been carried out in accordance with the written directions of a duly qualified person, and
the system has been certified, by the person by whom the test was carried out, as having satisfied the test, and
the person responsible has been provided with the certificate and the results of the equipment integrity test.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a modified storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the modification has been designed by a duly qualified person, and
the person by whom the modification has been designed has provided the person responsible for the system with—
a list of the industry standards that have been followed in connection with the design of the modification, and
a copy of the design specifications for the modification.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a modified storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the modification has been implemented by a duly qualified person, and
the person by whom the modification has been implemented has provided the person responsible for the system with—
a list of the industry standards that have been followed in connection with the implementation of the modification, and
a copy of the implementation specifications for the modification, and
current “as-built” drawings for the system.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
The person responsible for a modified storage system must not commission the system, or authorise or permit the commissioning of the system, unless—
the system includes the equipment required by AS 4897–2008: The design, installation and operation of underground petroleum storage systems, as in force from time to time, and
a leak detection system is installed on the storage site in accordance with Part 3.
Maximum penalty—200 penalty units (in the case of an individual) and 400 penalty units (in the case of a corporation).
Subclause (1)(a) does not require a system commissioned before 1 June 2008 to include the equipment referred to in that paragraph unless the modification is a significant modification.