Lease, licence etc under NPW Act for Snowy 2.0 electricity transmission
39A Lease, licence etc under NPW Act for Snowy 2.0 electricity transmission
The power to grant a lease, licence, easement or right of way under Part 12 of the NPW Act over the Kosciuszko National Park or any other land reserved or dedicated under the NPW Act may be exercised for the purposes of enabling TransGrid (or the holder of a transmission operator’s licence under the Electricity Supply Act 1995) to operate an electricity transmission system from the electricity generating works associated with the Snowy 2.0 project.
TransGrid (or the holder of a transmission operator’s licence) is entitled to such a grant by the Minister administering the NPW Act for the purposes of, and in connection with, the Snowy 2.0 electricity transmission system.
The term of such a grant may be the same as the term of a Snowy 2.0 lease.
Such a grant may contain provisions for its variation or revocation.
The regulations may modify the application of provisions of Part 12 of the NPW Act that specify steps precedent to such a grant.
Regulations under subsection (5) must not be made unless the Minister certifies to the Governor that the Minister has—
consulted with the Minister administering the NPW Act in connection with those regulations, and
given that Minister at least 28 days to make submissions regarding those regulations.