Complying development certificate conditions—additional conditions
2.115 Complying development certificate conditions—additional conditions
A complying development certificate for development referred to in section 2.114 is subject to the following conditions (in addition to the conditions set out in section 2.23)—
suitable screens or barricades must be erected prior to any demolition, excavation or building work in order to control dust emissions from the site,
in the case of development referred to in section 2.114(b), (c) or (f)—the principal certifying authority for the development must be given the following survey certificates prepared by a registered land surveyor—
before any form work below the ground floor slab is completed or (if there is no such form work) before the concrete is poured for the ground floor slab—a survey certificate showing the location of the proposed building relative to the property boundaries,
on completion of the lowest floor—a survey certificate confirming that the levels correspond to the levels shown on the plans in respect of which the complying development certificate is issued.