Issue of certificates of compliance
51 Issue of certificates of compliance
A registered operator may issue a certificate of compliance to a developer without serving a requirements notice on the developer.
A registered operator must issue a certificate of compliance to the developer if satisfied a requirements notice given to the developer has been complied with.
A registered operator must, at the developer’s request, issue a certificate of compliance to the developer if, within the relevant period—
a certificate of compliance has not been issued to the developer, and
a requirements notice has not been given to the developer.
A certificate of compliance may, instead of being issued in relation to all of the development, be issued progressively in relation to a stage of the development.
A certificate of compliance may be issued to replace a certificate of compliance previously granted.
In this section—
relevant period means—
60 days after the developer applies for a certificate of compliance, or
a further period approved by IPART and notified to the developer within the 60 days.