Commercial building work commenced before commencement
208 Commercial building work commenced before commencement
(1) This section applies in relation to commercial building work for which a building permit was granted before the commencement if the building permit was in force immediately before the commencement.
(2) The commercial building work may be carried out in accordance with this Act as if Part 3 of the amending Act had not commenced.
In this section:
amending Act means the Building Legislation Amendment Act 2024.
commencement means the day on which Part 3 of the amending Act commences.
commercial building work means work that is for or in connection with the construction of any of the following:
a building of Class 1b, 3, 4, 5, 6, 7, 8 or 9;
(b) a Class 10 building attached to a building referred to in paragraph (a) if it is constructed at the same time as that building;
(c) a retaining wall (whenever constructed) that is not attached to a building referred to in paragraph (a) but on which the integrity of such a building depends.
This Act’s bill:Second reading speech
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.