1Citation
These Regulations may be cited as the Building (Resolution of
Residential Building Work Disputes) Regulations 2012.
These Regulations may be cited as the Building (Resolution of
Residential Building Work Disputes) Regulations 2012.
These Regulations commence on the commencement of the Building
Amendment (Residential Building Consumer Protection) Act 2012.
Prescribed residential building work carried out, or to be carried out, in relation to a residential building owned by Defence Housing
Australia is exempt from the operation of section 54A(2) of the
Act.
Note for regulation 3
The effect of this regulation is that a person may make an application under these Regulations in relation to such residential building work.
Part 1.2 Interpretation
Division 1 Defined terms
In these Regulations:
affected person, for a reviewable decision, see regulation 74(2).
alleged contravention, in relation to an application, means the contravention of a consumer guarantee specified in the application.
alleged defect, in relation to a consumer guarantee dispute application or a technical inspection application, means the non‑structural defect or structural defect, specified in the application.
alleged defective work, in relation to a consumer guarantee dispute application or technical inspection application, means the residential building work to which the application relates.
application means one of the following:
a consumer guarantee dispute application;
a mediation or conciliation application;
a technical inspection application.
builder means a residential builder.
business day means a day other than a Saturday, Sunday or public holiday.
compensation does not include damages as defined in section 3 of the Proportionate Liability Act 2005.
compliance period, for a dispute decision, see regulation 35(2).
conciliation conference means a conciliation conference under Part 2.3, Division 2.
conference means a preliminary conference, mediation conference or conciliation conference.
consumer guarantee dispute application means an application made to the Commissioner under section 54FC of the Act.
contract means a residential building contract.
contravention, of a consumer guarantee, see regulation 8(1).
convenor, for a conference, see regulation 46(1).
current owner, of land or a residential building, means a current owner mentioned in section 54AD(a) or (b) of the Act.
decision maker, for Chapter 4, means the Commissioner or Tribunal.
Defence Housing Australia means the body (however named) under the Defence Housing Australia Act 1987 (Cth) on which is conferred the function of providing housing for, and related services to, members of the Defence Force.
dispute decision, see regulation 32(1).
effective period, for a consumer guarantee, see regulation 7(1).
legally qualified person includes a person:
who is, or has been, a lawyer or legal practitioner; or
who has the qualifications to be enrolled as a lawyer or legal practitioner in the Territory.
mediation conference means a mediation conference under Part 2.3, Division 2.
mediation or conciliation application, see regulation 10.
negotiated agreement process means the process under Part 2.3.
non-completion, of residential building work, is the failure of a builder to complete the work under the residential contract relating to the work.
non-structural defect, in relation to a residential building, see regulation 9(1).
notice means a written notice.
party means a party to an application.
preliminary conference means a conference under Part 2.3, Division 1.
prescribed fee means a fee prescribed under regulation 66(3).
proceeding means a proceeding started by an application.
qualified person, see regulation 55(2)(a).
relevant application, for Part 2.4, means a technical inspection application mentioned in regulation 55(1).
residential building, see regulation 5(3).
residential building work, in relation to:
a mediation or conciliation application – see regulation 5(1); and
a technical inspection application or a consumer guarantee dispute application – see regulation 6(2).
respondent means:
in a consumer guarantee dispute application – the builder specified in the application; or
in a mediation or conciliation application or technical inspection application:
if the application is made by the current owner of a residential building – the residential builder specified in the application; or
if the application is made by a residential builder – the current owner of the residential building specified in the application.
response, in relation to a consumer guarantee dispute application, means the response mentioned in regulation 24.
reviewable decision, see regulation 74(1).
specified circumstance, for a consumer guarantee dispute application, see regulation 18(1).
structural defect, in relation to a residential building, see regulation 9(2).
technical inspection means a technical inspection of alleged defective work as mentioned in section 54FB(4) of the Act.
technical inspection application, see regulation 14.
technical report means a report following a technical inspection as mentioned in section 54FB(4) of the Act.
work means residential building work.
Division 2 Important concepts
For section 54AB(1) of the Act, this regulation prescribes the building work in relation to which a mediation or conciliation application may be made (the residential building work).
The residential building work is building work, of any value, in connection with the construction of a residential building.
A residential building is any of the following:
a Class 1a building;
a Class 2 building;
a Class 10 building.
However, the residential building work does not include any work that does not require a building permit.
A reference in this regulation to a residential building of a particular Class is a reference to a building of that Class as specified under the classification of buildings in the Building Code as defined in regulation 2(1) of the Building Regulations 1993.
For section 54AB(1) of the Act, this regulation prescribes the building work (the residential building work) in relation to which either of the following applications may be made:
a technical inspection application;
a consumer guarantee dispute application.
The residential building work is building work to which an authorised RBI policy or fidelity certificate applies.
For section 54B(2) of the Act, this regulation prescribes the effective period for the consumer guarantees (the effective period) during which a current owner mentioned in section 54BB may make a consumer guarantee dispute application.
The effective period for a contravention of a consumer guarantee resulting in the non-completion of residential building work under a contract is the period:
that starts:
if the builder has started to carry out the work – on the day the builder completely ceases to do so; or
if the builder has not started to carry out the work and the contract specifies a starting date – on the specified starting date; or
if the builder has not started to carry out the work and the contract does not specify a starting date – on the date the contract was entered into; and
that ends 90 days after the relevant day or date mentioned in paragraph (a).
The effective period for a contravention of a consumer guarantee resulting in defective residential building work is the total of the following 2 periods:
the construction period mentioned in subregulations (4) and (5);
the defect period mentioned in subregulations (6) and (7).
Subject to subregulation (5), the construction period is the period:
that starts:
if there is a contract for the residential building work – on the day the contract is entered into; or
if there is no contract for the work – on the day the building permit is granted for the work; and
that ends:
if occupancy certification is required for the work – on the day an occupancy permit or certificate of substantial compliance is granted for the work; or
if occupancy certification is not required for the work – on the day the builder has made all the declarations required under the Act in relation to the work.
If the work mentioned in subregulation (4) is not fully completed before the day the building permit expires, the construction period ends on that day.
The defect period starts immediately after the last day of the construction period and, subject to subregulation (7), continues for the following period:
for alleged defective work resulting in a non-structural defect – 1 year;
for alleged defective work resulting in a structural defect –6 years.
If the current owner becomes aware of the alleged defective work within 30 days before the end of the defect period, the defect period is extended for 30 days after the day on which the owner became aware of the defect.
A contravention of the consumer guarantees by a builder occurs if the builder contravenes a consumer guarantee in relation to residential building work the builder:
has agreed to carry out; or
is carrying out; or
has carried out.
A non-structural defect, in a residential building, is a defect in a non-structural element of the building as a result of defective residential building work.
A structural defect, in a residential building:
is a defect in a structural element of the building as a result of defective residential building work; or
is a defect, as a result of defective residential building work, that is reasonably likely to cause a defect in a structural element of the building.
Example for subregulation (2)(b)
A waterproof membrane attached to a wall or floor of a bathroom.
In this regulation:
non-structural element, of a residential building, means a component of the building that is not a structural element.
structural element, of a residential building, means:
a load-bearing component of the building (whether internal or external) that is essential to the stability of the building or part of the building; or
a component (including weatherproofing) forming part of the external walls or roof of the building.
Examples for paragraph (a)
A foundation, floor, wall, roof, column or beam.
Chapter 2 Applications to Commissioner
Part 2.1 Making applications and decisions about acceptance
Division 1 Procedures for mediation or conciliation application
A mediation or conciliation application is an application to the Commissioner that:
relates to any of the residential building work prescribed by regulation 5(2) and a dispute about that work between:
the current owner of the land or residential building to which the application relates; and
the residential builder in relation to the work; and
is made by either the owner or the builder; and
requests the Commissioner to facilitate a negotiated agreement process between the owner and builder.
A mediation or conciliation application must be in the approved form.
The application must include the following:
the name and contact details of the applicant;
the name and contact details of the respondent;
the location of the land or residential building and a concise description of the residential building work to which the application relates;
a concise description of the dispute between the parties to the application;
all other information the approved form requires.
Within 10 business days after a mediation or conciliation application is made, or as soon as is reasonably practicable after that time, the Commissioner must decide whether to accept the application.
The Commissioner may accept the application only if satisfied:
the application relates to residential building work prescribed by regulation 5(1); and
the parties to the application are the current owner and residential builder in relation to the work; and
the prescribed fee for the application has been paid.
If there is insufficient information for the Commissioner to be satisfied about the matters mentioned in subregulation (2), the Commissioner may give the applicant a notice specifying:
the further information required; and
a reasonable time within which the information must be given.
If the Commissioner decides to accept the application, the Commissioner must follow the relevant procedures specified in regulation 40.
Showing the first 12 of 93 provisions. See all provisions