Time limit for accepting or not accepting pipeline management plan
24 Time limit for accepting or not accepting pipeline management plan
(1) Within 28 days after a pipeline licensee submits a pipeline management plan under regulation 23, the Minister must:
accept the plan under regulation 25;
refuse to accept the plan; or
(c) give written notice to the pipeline licensee stating that the Minister is unable to make a decision about the plan within the period of 28 days and setting out a proposed timetable for consideration of the plan.
(2) A decision by the Minister to accept, or refuse to accept, a pipeline management plan is not invalid only because the Minister did not comply with subregulation (1) in relation to the plan.
(3) This regulation applies to a pipeline management plan resubmitted under regulation 25(2) in the same way as it applies to the plan when first submitted.