Implementation of stage of development otherwise than as indicated in scheme statement

In force
Chapter 2Basic operation of a scheme
Part 2.4Development of a scheme
Division 2Progressive development of a scheme

65 Implementation of stage of development otherwise than as indicated in scheme statement

(1) This section applies if:

(a) a scheme is intended to be developed progressively; and

(b) the developer proposes to implement a stage of the development otherwise than as indicated in the scheme statement.

(2) Without limiting subsection (1)(b), the implementation of a stage of the development is otherwise than as indicated in the scheme statement if:

(a) the stage is not specified in the statement; or

(b) the stage will not be implemented in the order specified in the statement; or

(c) the implementation will affect or change the nature or purposes of the development otherwise than as specified in the statement; or

(d) the implementation will involve a further subdivision or consolidation of land not specified in the statement.

(3) The developer must give written notice of the implementation of the stage to the following at least 1 month before applying for the development permit or exceptional development permit for the implementation:

(a) the body corporate;

(b) anyone who has entered into a contract with the developer to buy a unit that will come into existence as a result of the implementation of the stage, or a later stage, of the development.

Fault element: Strict liability offence.

Maximum penalty: 100 penalty units.