Relevant former reassessment fee
87 Relevant former reassessment fee
This section applies if —
before the commencement—
a person submitted amended plans and specifications for stated building work for approval; and
the service did not finish reassessing the required special fire services for the stated building work under section 24(2) of the repealed regulation; and
the person has not paid the relevant former reassessment fee for the reassessment.
For reassessing, and paying the relevant former reassessment fee for, the required special fire services for the stated building work, section 24 of the repealed regulation, as it was in force on the day the service started the reassessment, continues to apply as if the section had not been amended or repealed.
In this section—
relevant former reassessment fee, for reassessment of required special fire services, means—
if the reassessment started before 8 February 2008—the fee stated in section 24(5), definition reassessment fee of the repealed regulation, as it was in force on the day the reassessment started; or
if the reassessment started on or after 8 February 2008—the reassessment fee stated in schedule 3 of the repealed regulation, as it was in force on that day.