In forceDamages payable for failure to give information
Chapter 4Subcontractors’ charges
Part 3Information to be given to subcontractor
120 Damages payable for failure to give information
(1)
This section applies if a person fails to give a subcontractor information as required under section 119.
(2)
The person is liable to pay the subcontractor an amount for damages that the subcontractor incurred as a consequence of the failure.
(3)
Damages under subsection (2) must be decided by the court on the application of the subcontractor.
(4)
In a proceeding mentioned in subsection (3) the person is excused from the liability under subsection (2) if the person satisfies the court that the person has a reasonable excuse for the failure.