Copy of notice of claim to the holder of a security
124 Copy of notice of claim to the holder of a security
This section applies if—
a subcontractor gives a notice of claim to a person (the recipient) obliged to pay money to a contractor under a contract; and
a person other than the recipient holds a security for the contract.
The subcontractor must give a copy of the notice of claim to the person who holds the security.
If a copy of the notice of claim is not given as required under subsection (2), the claimed subcontractor’s charge does not attach to the security.
To remove any doubt, it is declared that subsection (3) does not affect a subcontractor’s charge to the extent it otherwise attaches under this chapter.