24A
In forceContracting party to report failure to establish project trust
Chapter 2Statutory trusts
Part 2Project trusts
Division 6Obligations of contracting party
24A Contracting party to report failure to establish project trust
(1)
This section applies if the contracting party for a contract knows or ought reasonably to know—
(a)
a project trust is required for the contract; and
(b)
a project trust account has not been opened for the trust as required under section 18.
(2)
The contracting party must, using an approved way, report the matter to the commissioner.
Maximum penalty—100 penalty units.